More Questions on Indian Railway
- Q. Which app has been launched by the Ministry of Railways to expedite & streamline passenger grievance redressal?
A)Rail Madad
B)Rail Sathi
C)Rail Dost
D)Rail Neer
Answer: Rail Madad
- Q. If the Distant signal of a Gate becomes defective in off condition, ________ is issued to Loco Pilot from the station in rear.
A)Nil caution order
B)Caution order
C)Reminder order
D)None of these
Answer: Caution order
- Q. How many copies of caution order shall be prepared for a train provided with banking engine?
A)5
B)3
C)4
D)None of these
Answer: 5
- Q. It is a Python Rake.
A)15 kmph
B)60 kmph
C)25 kmph
D)Normal speed
Answer: 60 kmph
- Q. How many Class of Accident?
A)20
B)14
C)16
D)None of these
Answer: 16
- Q. Nil Caution order number is ________
A)T/C409
B)T/A-409
C)T/B-409
D)None of these
Answer: T/A-409
- Q. Number of the Reminder caution order is ________.
A)T/C 410
B)T/A 409
C)T/B 409
D)None of these
Answer: T/B 409
- Q. Block overlap in multiple aspect signalling system is ________ meters.
A)180
B)200
C)300
D)208
Answer: 180
- Q. Which is the least signalto be installed on C class stations in multiple aspect signalling?
A)Warner, Home
B)Outer, Home
C)Distant, Home
D)Distant, Home, Starter
Answer: Distant, Home
- Q. At the starting station, passenger train must have ________ kg/cm2 of FP pressure and 4.8 kg/cm2 of BP pressure in the brake van.
A)5
B)4
C)2
D)8
Answer: 5
- Q. When the platform level is ________ MM and more second arriving train shall not be received and berthed on non platform line directly.
A)650
B)700
C)725
D)760
Answer: 760
- Q. when form T/D 912 is issued the driver shall not exceed the speed
A)25 kmph
B)15 kmph
C)20 kmph
D)None of these
Answer: 25 kmph
- Q. Notice station notified in?
A)SR
B)SWR
C)GR
D)Working Time Table
Answer: Working Time Table
- Q. In automatic section, temporary single line working on double line section what authority to proceed will be served to loco pilot from opposite direction?
A)TD-912
B)TA-912
C)TB-912
D)TC-1425
Answer: TA-912
- Q. When ISMD attached train is allowed to run through on PF line the speed must be
A)10 kmph
B)5 kmph
C)8 kmph
D)None of these
Answer: 5 kmph
- Q. During failure of signals and communications in DL automatic area the authority to proceed is
A)T/B 912
B)T/D 912
C)T/A 912
D)None of these
Answer: T/B 912
- Q. Which of the following two countries have largest electrified railway network in the world?
A)Russia & China
B)Russia & US
C)US & China
D)India & US
Answer: Russia & China
- Q. In how many zones Indian Railway has been divided?
A)17
B)14
C)16
D)20
Answer: 17
- Q. Point indicator is provided to indicate ________.
A)Both
B)Points
C)Bar
D)None of these
Answer: Points
- Q. The world’s highest railway bridge will come up over which Indian River?
A)Ganga
B)Narmada
C)Godavari
D)Chenab
Answer: Chenab
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State