Q. Whenever new signal is put into use, signal sighting committee submits its joint report on

Correct Answer

T/102B

More Questions on Indian Railway

  • Q. In case of continuous category/preparatory and /or complementary work between 15 and 45 meters should be treated as ________.
    A)30 meters
    B)20 meters
    C)25 meters.
    D)None of these
    Answer: 30 meters
  • Q. Loss of Railway property of ________ is treated as serious accident.
    A)75 Lakhs
    B)More than 50 lakhs
    C)01 crore
    D)More than 02 crore
    Answer: More than 02 crore
  • Q. Notice station caution order No. is ________
    A)T/C-409
    B)T/409
    C)T/B-409
    D)None of these
    Answer: T/409
  • Q. What is the maximum speed in block section during thick & foggy weather?
    A)15 kmph
    B)30 kmph
    C)60 kmph
    D)Not to move
    Answer: 60 kmph
  • Q. The world’s highest railway bridge will come up over which Indian River?
    A)Ganga
    B)Narmada
    C)Godavari
    D)Chenab
    Answer: Chenab
  • Q. What is shunting order number?
    A)T-806
    B)T-609
    C)T/A-602
    D)T-409
    Answer: T-806
  • Q. In one train only system, information of lost of metal token is given to ________.
    A)DRM
    B)DOM
    C)AOM
    D)None of these
    Answer: DRM
  • Q. Launched three Trains to improve Quality of Travel (for reserved passengers), these are:
    A)Dirubhargh, Sahayak and Humsafar
    B)Humsafar, Tejas and Uday
    C)Tejas, Antyodaya and Gatiman
    D)Sahayak,Antyodaya and Gatiman
    Answer: Humsafar, Tejas and Uday
  • Q. In block section trains entered simultaneously from either direction and finally stopped before collision and distance between both the trains was 400 mtrs, which type of accident occured?
    A)Save collision
    B)Violation of block rules
    C)Passingn danger signal
    D)All of above
    Answer: All of above
  • Q. Matheran Hill Railway is a narrow gauge heritage railway located in which state?
    A)Maharashtra
    B)Tamil Nadu
    C)Himachal Pradesh
    D)Meghalaya
    Answer: Maharashtra
  • Q. Train is to be started from non signalled line
    A)T/D 602
    B)T-511
    C)T-512
    D)Simple memo
    Answer: T-511
  • Q. Calling on signal shows ________ light in off position in two aspect signalling system.
    A)Green
    B)White
    C)RED
    D)Yellow
    Answer: Yellow
  • Q. On seeing defective stop signal during train working, Loco Pilot will sound ________ whistle to inform the same.
    A)One long one short
    B)One Long Two Short
    C)Two long one short
    D)None of these
    Answer: One Long Two Short
  • Q. Sand hump is a substitute to ________ and also a means of isolation.
    A)Over signal
    B)Signal
    C)Signal overlap
    D)None of these
    Answer: Signal overlap
  • Q. In TALQ signalling system, ________ signal will be treated as defective if home signal becomes defective.
    A)Hand
    B)Outer
    C)Call-On
    D)Non eof these
    Answer: Outer
  • Q. When a front portion of a parted train gives one long one short one long one short whistle, SM to wave ________ signal four times above head from side to side and acknowledge.
    A)Yellow
    B)RED
    C)Green
    D)None of these
    Answer: RED
  • Q. Upto how many track machine shall be allowed for working within the block section?
    A)8
    B)2
    C)5
    D)10
    Answer: 5
  • Q. IN the BD Spl, the water must be filled ________.
    A)Three Week
    B)Once a week
    C)Two week
    D)None of these
    Answer: Once a week
  • Q. Headquarters of which one among the following Railway Zones in India is situated at the highest elevation from the mean sea level?
    A)South Western Railway
    B)East Central Railway
    C)South Eastern Railway
    D)West Central Railway
    Answer: South Western Railway
  • Q. Each motor coach shall consist of ________ Traction motors.
    A)4
    B)2
    C)3
    D)5
    Answer: 4

Leave a Comment