Q. When a train is working on T/D912 in automatic block in system, the train must be piloted into the station during reception by

Correct Answer

T/409

More Questions on Indian Railway

  • Q. On which speed BG train should be run while speedometer failed in block section?
    A)No need to reduced speed
    B)10% less of sectional speed
    C)10% less of booked speed
    D)40 kmph
    Answer: 10% less of sectional speed
  • Q. When a stream engine is running tender foremost the speed shall not exceed ________.
    A)30 kmph
    B)40 kmph
    C)20 kmph
    D)None of these
    Answer: 40 kmph
  • Q. Second train during all communication failure shall be dispatched after an interval of
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. Speed of the following tower wagon is ________ km/h.
    A)9
    B)10
    C)8
    D)4
    Answer: 8
  • Q. passing through station during day when running without brakevan and tail board.
    A)25 kmph
    B)10 kmph
    C)20 kmph
    D)Normal speed
    Answer: 20 kmph
  • Q. Number of the Nil caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 408
    D)None of these
    Answer: T/A 409
  • Q. In two aspects areas where shunting in the face of approaching train is not permitted, shunting can be permitted during ________ and under certain conditions (UP to FSS).
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. A vehicle which can be bodily lifted off the line by ________ is a trolley
    A)3 man
    B)02 man
    C)04 man
    D)None of these
    Answer: 04 man
  • Q. When was the construction work for the first Railway line Started?
    A)1823
    B)1821
    C)1828
    D)1830
    Answer: 1821
  • Q. Goods warning board will be provided from FSS in BG at
    A)560 meters
    B)1400 meters
    C)1000 meters
    D)None of these
    Answer: 1400 meters
  • Q. In case of continuous category/preparatory and /or complementary work between 15 and 45 meters should be treated as ________.
    A)30 meters
    B)20 meters
    C)25 meters.
    D)None of these
    Answer: 30 meters
  • Q. Where the caution indicator placed in BG if the engineering work is more than one days and train not to be require to stop at site?
    A)800 Meter
    B)1200 Meter
    C)1000 Meter
    D)500 Meter
    Answer: 800 Meter
  • Q. Which of the following has been adjudged as the cleanest railway station in category A1, as per recently released report by the Ministry of Railways?
    A)Secunderabad
    B)Vishakhapatnam
    C)Jammu Tawi
    D)Anand ViharTerminal
    Answer: Vishakhapatnam
  • Q. EMU trains of harbour line has ________ number of wooden wedges.
    A)6
    B)2
    C)4
    D)8
    Answer: 4
  • Q. Engineering allowance, loco gain and traffic gain are mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. Food Safety and Standards Authority of India (FSSAI) certified ________ as India’s first Eat Right Station.
    A)Mumbai Central railway station
    B)Chennai Central railway station
    C)Chhatrapati Shivaji Maharaj railway station
    D)Bengaluru Central railway station
    Answer: Mumbai Central railway station
  • Q. Booked speed of a train is ________ percent less than maximum permissible speed
    A)15
    B)5
    C)10
    D)20
    Answer: 10
  • Q. Adequate distance mentioned in the automatic block system is ________ meters.
    A)105
    B)110
    C)120
    D)115
    Answer: 120
  • Q. The number of line clear ticket in up direction is ________.
    A)T/A 1425
    B)T/C 1425
    C)T/D 1426
    D)T/B 1425
    Answer: T/C 1425
  • Q. What will be the speed of second train running on T/C 602?
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: Normal speed

Leave a Comment