Q. When a train is working on T/D912 in automatic block in system, the train must be piloted into the station during reception by

Correct Answer

T/409

More Questions on Indian Railway

  • Q. During power failure in automatic block section, on which authority relief engine will proceed?
    A)TC-912
    B)TA-912
    C)TB-912
    D)TD-912
    Answer: TC-912
  • Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
    A)Both
    B)Temporary Working Order.
    C)Permanent working order.
    D)None of these
    Answer: Temporary Working Order.
  • Q. Which of the following will become the first central paramilitary force to opt for e – ticketing instead of Railway warrant?
    A)Central Reserve Police Force
    B)Assam Rifles
    C)National Security Guard
    D)Sashastra Seema Bal
    Answer: National Security Guard
  • Q. When the rail failure is rectified by the train can pass at speed
    A)30 kmph
    B)20 kmph
    C)25 kmph
    D)None of these
    Answer: 30 kmph
  • Q. W/L board will be provided at not less than ________ metres from the gate.
    A)600
    B)400
    C)500
    D)800
    Answer: 600
  • Q. Nil Caution order number is ________
    A)T/C409
    B)T/A-409
    C)T/B-409
    D)None of these
    Answer: T/A-409
  • Q. General Manager is responsible for
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)Finance Ministry
    Answer: Railway Board
  • Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. In the enroute, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 90
  • Q. Between which of the destinations the first Indian train was started?
    A)From Mumbai to Surat
    B)From Kolkata to Delhi
    C)From Mumbai to Thane
    D)From Mumbai to Madras
    Answer: From Mumbai to Thane
  • Q. At the starting station, passenger train must have ________ kg/cm2 of FP pressure and 5 kg/cm2 of BP pressure in the engine.
    A)6
    B)10
    C)8
    D)4
    Answer: 6
  • Q. The distance between two automatic signals is normally
    A)3 km
    B)2 km
    C)1 km
    D)None of these
    Answer: 1 km
  • Q. When a train is working on T/D912 in automatic block in system, the train must be piloted into the station during reception by
    A)T/369(1)
    B)T/369(3b)
    C)T/369(2)
    D)T/409
    Answer: T/409
  • Q. “Act” means the Railway Act is ________.
    A)1989 (22 of 1989)
    B)1989 (24 of 1989)
    C)1989 (23 of 1989)
    D)None of these
    Answer: 1989 (24 of 1989)
  • Q. Termination indication board will be
    A)Rectangular
    B)Square
    C)Round
    D)None of these
    Answer: Round
  • Q. On which speed BG engine shall be run while speedometer is defective during run?
    A)25 kmph
    B)50 kmph
    C)40 kmph
    D)Maximum 10% less of MPS
    Answer: Maximum 10% less of MPS
  • Q. Train is to be passed through loop line.
    A)30 kmph
    B)15 kmph
    C)25 kmph
    D)Normal speed
    Answer: 15 kmph
  • Q. When the section is occupied, the arrow indication in the panel in Twin single line working will be
    A)No light
    B)White
    C)Red
    D)None of these
    Answer: Red
  • Q. The zone with the minimum length is
    A)South - East Railway
    B)North - Eastern Railway
    C)North - Eastern Frontier Railway
    D)South - Central Railway
    Answer: North - Eastern Frontier Railway
  • Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
    A)Walkie-Talkie
    B)Walkie
    C)VHF
    D)None of these
    Answer: Walkie-Talkie

Leave a Comment