More Questions on Indian Railway
- Q. Which of the following sectors are included as part of multi – modal logistics hubs in India? 1)Aviation 2)National Highways 3) Ports 4)Inland waterways 5)Railways Select the correct option from codes given below:
A)1, 2, 3, 4 & 5
B)Only 2, 3 & 4
C)Only 2, 3, 4, 5
D)Only 2, 3 & 5
Answer: 1, 2, 3, 4 & 5
- Q. During accident or Engine failure in the mid section the report sent to SM must be signed by ________.
A)Both
B)GDR
C)TDR
D)None of these
Answer: GDR
- Q. What will be the speed of a train running through from station without brake van provoded with Tail lamp?
A)15 kmph
B)20 kmph
C)Stop & Start
D)Normal speed
Answer: Normal speed
- Q. Capacity of a catch siding is ________.
A)Station
B)Equivalent to length of full train
C)Length
D)None of these
Answer: Equivalent to length of full train
- Q. General Manager is responsible for
A)Both railway Board and Railway Ministry
B)Railway Board
C)Railway Ministry
D)Finance Ministry
Answer: Railway Board
- Q. Number of train signal register of double line is ________.
A)T/66 B
B)T/66 A
C)T/66 C
D)T/66
Answer: T/66 B
- Q. How many members did the railway board had?
A)4
B)3
C)5
D)8
Answer: 4
- Q. In token territory, ________ is authority for shunting up to FSS.
A)T/806
B)Shunt Mental Token+T/806
C)Shunt Mental
D)None of these
Answer: Shunt Mental Token+T/806
- Q. When the Head light fails during night the speed of train is ________ in BG. If there is no other caution for less speed is the Block section
A)25 kmph
B)30 kmph
C)40 kmph
D)None of these
Answer: 40 kmph
- Q. Under approved special instructions, Distant signal can be placed along with the
A)Both
B)Last Stop
C)First Stop
D)None of these
Answer: Last Stop
- Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the engine.
A)3
B)5
C)2
D)4
Answer: 5
- Q. If the IBS signal is ON and Telephone is defective, Loco Pilot shall wait for 5 minutes and proceed at a speed of ________
A)15/6
B)15/8
C)15/4
D)15/2
Answer: 15/8
- Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
A)8 kmph
B)15 kmph
C)10 kmph
D)Normal
Answer: 10 kmph
- Q. During shunting if load move toward the person signalling hand signal should be given at night by railway staff.
A)White light left and right
B)Green light up and down
C)Green light left and right
D)Green light without any movement
Answer: Green light left and right
- Q. In the panel working for cancellation of route the number in the counter changes and white indication appears after
A)50 seconds
B)120 seconds
C)90 seconds
D)None of these
Answer: 120 seconds
- Q. Booked speed of a train is ________ percent less than maximum permissible speed
A)15
B)5
C)10
D)20
Answer: 10
- Q. Which of the following is the largest railway junction in India?
A)Mathura
B)Delhi
C)Bhatinda
D)Allahabad
Answer: E
- Q. The consumption of fuel during idle run per hour is
A)25 Lts
B)15 Lts
C)20 Lts
D)None of these
Answer: 25 Lts
- Q. What will be the maximum speed of B-Class ODC in Broad guage?
A)40 kmph
B)15 kmph
C)25 kmph
D)75 kmph
Answer: 40 kmph
- Q. Signal failure advised to the driver through the station in rear will be inform
A)T/369(3b)
B)T/369
C)T/370
D)None of these
Answer: T/369
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State