Q. What action shall be taken by loco pilot if Guard failed to exchange all right signal after passing engineering speed restriction zone?

Correct Answer

Stop his train and find the cause

More Questions on Indian Railway

  • Q. If outside the station limits the distance between two trains is ________ in averted collusion, such occurrence may not be treated as an averted collision.
    A)100 meter
    B)200 meter
    C)250 meter
    D)400 meters and more
    Answer: 400 meters and more
  • Q. Gateman competency certificate of interlocked traffic gate is signed by TI and SE (Sig) and counter signed by ________.
    A)DOM
    B)AOM(G)
    C)AOM(Chg)
    D)None of these
    Answer: AOM(G)
  • Q. In Material train, vehicles shall not be detached on gradient.
    A)1-400
    B)ST 1-260
    C)1-100 or steeper
    D)None of these
    Answer: 1-100 or steeper
  • Q. Distance between two automatic signals is called as ________.
    A)Signalling Section
    B)Block section
    C)Mid Section
    D)None of these
    Answer: Signalling Section
  • Q. Semi-automatic signal is identified by ________.
    A)Illuminated a marker
    B)Marker
    C)Semi marker
    D)None of these
    Answer: Illuminated a marker
  • Q. The railway station situated in the extreme south is
    A)Kanyakumari
    B)Chennai
    C)Cochin
    D)Trivandrum
    Answer: Kanyakumari
  • Q. Last stop signal means the ________ of a station controlling the entry of trains into the next block section.
    A)Call-on Signal
    B)Fixed stop signal
    C)Hand Signal
    D)None of these
    Answer: Fixed stop signal
  • Q. It is the responsibility of SM to see that shunting is performed as per ________.
    A)G&R
    B)WTT
    C)SWR
    D)None of these
    Answer: SWR
  • Q. Competency certificate of the gateman of interlocked engineering gate is signed by
    A)Both
    B)SSE/P.way
    C)SSE/Sig.
    D)None of these
    Answer: Both
  • Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
    A)30
    B)20
    C)25
    D)15
    Answer: 15
  • Q. It is a Python Rake.
    A)15 kmph
    B)60 kmph
    C)25 kmph
    D)Normal speed
    Answer: 60 kmph
  • Q. When was the North – Eastern frontier Railway (NEFR) established?
    A)2nd Jan, 1956
    B)15th Jan, 1958
    C)15th Jan, 1955
    D)14th April, 1952
    Answer: 15th Jan, 1958
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. TSL is started between those two stations at which cross over facility are available and
    A)D Class/IBC
    B)A Class/IBS
    C)C Class/IBS
    D)None of these
    Answer: C Class/IBS
  • Q. During shunting, outer, home and ________ signals are not taken off.
    A)Both
    B)Last stop signal
    C)First stop signal
    D)None of these
    Answer: First stop signal
  • Q. Distance between outer and home signals on a double line is ________ meters.
    A)400
    B)900
    C)800
    D)700
    Answer: 400
  • Q. By whom the rear portion of train left behind in block section protected?
    A)By engineearing official
    B)By Guard
    C)By LP
    D)No need to protect the load
    Answer: By Guard
  • Q. Number of the Reminder caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 409
    D)None of these
    Answer: T/B 409
  • Q. The time taken for formation of a goods train in flat yard is
    A)3 kmph
    B)2 hrs
    C)1 hr
    D)None of these
    Answer: 2 hrs
  • Q. During shunting if load move toward the person signalling hand signal should be given at night by railway staff.
    A)White light left and right
    B)Green light up and down
    C)Green light left and right
    D)Green light without any movement
    Answer: Green light left and right