More Questions on Indian Railway
- Q. While clearing the load with an invalid brake power certificate, if train examiner is not available, Loco Pilot and Guard shall ensure safety of the train and take the train upto ________.
A)Executive
B)Examine
C)Next Examine
D)None of these
Answer: Next Examine
- Q. Notice station caution order No. is ________
A)T/C-409
B)T/409
C)T/B-409
D)None of these
Answer: T/409
- Q. What will be the maximum speed to pass IBS home signal in ON position when received authority from previous station?
A)8 kmph
B)15 kmph
C)10 kmph
D)Normal
Answer: Normal
- Q. Shatabdi Express train was started in ________.
A)1990
B)1984
C)1988
D)1985
Answer: 1988
- Q. Number of train signal register of single line is ________.
A)T/166 B
B)T/136 A
C)T/137 B
D)T/135
Answer: T/137 B
- Q. When VP vehicles are attached in a goods train the maximum number of VPvehicle in one group is
A)8
B)10
C)6
D)None of these
Answer: 6
- Q. To call the Guard to the driving cab, Motorman of EMU train will give ________ bell code.
A)0
B)0
C)0
D)0
Answer: 0
- Q. Indian Railway Act means ________.
A)Part 23 of 1989
B)Part 22 of 1989
C)Part 24 of 1989
D)Part 21 of 1989
Answer: Part 24 of 1989
- Q. In context with the Indian railways what is TPWS?
A)Train Protection Warning Stopper
B)Train Passenger Warning System
C)Train Protection Warning System
D)Transmission Protection warning Stopper
Answer: Train Protection Warning System
- Q. Amount of vaccum level required in high speed train loco is
A)56 cm
B)50 cm
C)55 cm
D)None of these
Answer: 56 cm
- Q. The driver shall sound the following whistle to indicate that the fouling marks is not clear
A)One long
B)Three long
C)Short one long
D)None of these
Answer: Three long
- Q. On seeing defective stop signal during train working, Loco Pilot will sound ________ whistle to inform the same.
A)One long one short
B)One Long Two Short
C)Two long one short
D)None of these
Answer: One Long Two Short
- Q. Calling on signal is a ________ signal.
A)Subsidiary
B)Permissive
C)Home
D)None of these
Answer: Subsidiary
- Q. The zone with the minimum length is
A)South - East Railway
B)North - Eastern Railway
C)North - Eastern Frontier Railway
D)South - Central Railway
Answer: North - Eastern Frontier Railway
- Q. In which city is the Wheel and Axle Plant of the Indian Railways located?
A)Bangalore
B)Kapurthala
C)Varanasi
D)Rae Barelly
Answer: Bangalore
- Q. On November 14, 2019, With which locomotive factory, Indian Railways & French multinational company Alstom have entered into procurement cum maintenance agreement to deliver the 10 locomotives in FY (fiscal year) 2019 – 20?
A)Rail Wheel Factory
B)Modern Coach Factory
C)Integral Coach Factory
D)Madhepura Electric Locomotive Pvt. Ltd. (MELPL)
Answer: Madhepura Electric Locomotive Pvt. Ltd. (MELPL)
- Q. TCAS full form is:
A)Train Collision Avoidance Software
B)Train Collision Advance System
C)Train Complement Accident Software
D)Traffic Collision Avoidance System
Answer: Traffic Collision Avoidance System
- Q. Where there is no TSR, station master shall make entries in ________.
A)Mid section
B)Station diary
C)Diary
D)None of these
Answer: Station diary
- Q. Introduced ________ in Konkan Railway to help old and disabled passengers.
A)Divyang Express
B)Sahayak Express
C)Viklang Seva Express
D)Sarathi Seva
Answer: Sarathi Seva
- Q. Shunt signal is a ________ signal.
A)Both
B)Subsidiary
C)Ordinary
D)None of these
Answer: Subsidiary
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway