Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?

Correct Answer

Source of raw material and production centers

More Questions on Indian Railway

  • Q. Special instructions are issued by ________.
    A)Both
    B)COM
    C)Sr. DOM
    D)None of these
    Answer: COM
  • Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.
    A)25
    B)20
    C)15
    D)None of these
    Answer: 25
  • Q. Signal sighting committee shall submit its report on form ________.
    A)T/101 B
    B)T/103 B
    C)T/102 B
    D)None of these
    Answer: T/102 B
  • Q. Information of caution notice stations is given in ________.
    A)Both A or B
    B)WTT
    C)Working time table
    D)None of these
    Answer: Both A or B
  • Q. Permission of ________ is required to work the material train in the night.
    A)DRM
    B)AOM
    C)DOM
    D)None of these
    Answer: DRM
  • Q. For work of long duration, the stop indicator must be erected at not less than
    A)40
    B)30
    C)50
    D)45
    Answer: 30
  • Q. Consider the following sectors: 1)Plantation Sector 2)Mining and Exploration of Metal 3)Railway Infrastructure In which of the above, government has permitted 100% FDI through automatic route?
    A)2 & 3 Only
    B)1 & 2 Only
    C)3 Only
    D)1, 2 & 3
    Answer: 1, 2 & 3
  • Q. Hand shunting of vehicles is prohibited in gradient
    A)1 - 400 or steeper
    B)1 - 260
    C)1 - 400
    D)None of these
    Answer: 1 - 400 or steeper
  • Q. Derailment will come under accident class ________.
    A)C
    B)A
    C)B
    D)D
    Answer: D
  • Q. How many members did the railway board had?
    A)4
    B)3
    C)5
    D)8
    Answer: 4
  • Q. Signal sighting committee consists of TI, SI/PWI and ________.
    A)T/C 912
    B)T/B 912
    C)T/D 912
    D)T/A 912
    Answer: T/D 912
  • Q. During shunting of a passenger train the train engine will be stopped ________ mtrs before attaching to load?
    A)10 meters
    B)20 meters
    C)15 meters
    D)5 meters
    Answer: 20 meters
  • Q. In which country was flange wheel invented?
    A)Europe
    B)Germany
    C)Japan
    D)Russia
    Answer: Germany
  • Q. India’s first Antyodaya Express has been launched by the Minister of Railways. The express will run between which stations?
    A)New Delhi and Kanyakumari
    B)Ernakulam and Howrah
    C)Sriganganagar and Tiruchirapalli
    D)Nizamuddin and Palakkad
    Answer: Ernakulam and Howrah
  • Q. Maximum speed of shunting of wagons with explosives is ________ km/h.
    A)15
    B)8
    C)10
    D)20
    Answer: 8
  • Q. The Speaker of Lok Sabha also works as the ex – officio Chairperson of which of the following committees? 1)Railway Convention Committee 2)Business Advisory Committee 3)Public Account Committee Select the correct option from the codes given below:
    A)1 & 3 Only
    B)1 & 2 Only
    C)2 Only
    D)1, 2 & 3
    Answer: 2 Only
  • Q. When the derailing switch is open, trap indicator shows red target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: Red
  • Q. Maximum No. of ________ coaches can be attached in rear of SLR of passenger train.
    A)4
    B)2
    C)3
    D)6
    Answer: 2
  • Q. On which place the Guard should be presented at the time of train backed from one running line to another line?
    A)In Break van
    B)At Facing point
    C)On Engine
    D)At Anyplace
    Answer: In Break van
  • Q. To apply for Line block, the notice shall be given to DRM not less than
    A)12 hours
    B)48 hours
    C)24 hours
    D)None of these
    Answer: 24 hours