More Questions on Indian Railway
- Q. Shunt signal is a ________ signal.
A)Both
B)Subsidiary
C)Ordinary
D)None of these
Answer: Subsidiary
- Q. A jumper is remote control and is used for ________.
A)Control on Light, Fan etc.
B)Light
C)Fans
D)None of these
Answer: Control on Light, Fan etc.
- Q. When the driver reports rough running or lurch on the run, the SM to issue caution order with speed ________ kmph
A)20
B)10
C)15
D)None of these
Answer: 10
- Q. In case of ACP, Guard of EMU shall give ________ bell.
A)0-00-00
B)00-00-00
C)00-0-00
D)000-0-00
Answer: 00-0-00
- Q. Station manager of a big station shall inspect the cabins at least once in ________.
A)Thrice in a week.
B)Once in a week
C)Twice in a week
D)None of these
Answer: Once in a week
- Q. Motor vehicle in closed wagon shall be attached ________ position from engine on a goods train.
A)Third
B)First
C)Second
D)None of these
Answer: Third
- Q. In one train only system, information of lost of metal token is given to ________.
A)DRM
B)DOM
C)AOM
D)None of these
Answer: DRM
- Q. EMU train has ________ and automatic types of working brakes.
A)Hand Brake
B)EP Brakes
C)Power Brake
D)None of these
Answer: EP Brakes
- Q. If the patrol man does not turn up within ________ minutes, caution order must be issued.
A)15
B)10
C)5
D)20
Answer: 20
- Q. The Driver of goods train must stop his train as close as possible to ________.
A)Both
B)Starter
C)Advance Starter
D)None of these
Answer: Starter
- Q. When the calling on signal is taken off, it indicates the loco pilot to proceed ________ and be prepared to stop short of any obstruction.
A)Defective
B)Caution
C)Cautiously
D)None of these
Answer: Cautiously
- Q. If the block instrument becomes defective on a double line, ________ signal is also treated as defective.
A)Stop signal
B)Fisrt Stop signal
C)Last stop signal
D)None of these
Answer: Last stop signal
- Q. Number of train signal register of single line is ________.
A)T/166 B
B)T/136 A
C)T/137 B
D)T/135
Answer: T/137 B
- Q. Joint sighting committee shall inspect the visibility of signals once in
A)6 months
B)A month
C)3 months
D)None of these
Answer: 3 months
- Q. How many Class of Accident?
A)20
B)14
C)16
D)None of these
Answer: 16
- Q. Maximum speed of trains during thick & foggy weather in absolute block system is ________ when signal is showing green.
A)50
B)50
C)40
D)60
Answer: 60
- Q. Loss of railway property of Rs. more than 2 Crores is treaed as ________ accident.
A)Both
B)Minor
C)Serious
D)None of these
Answer: Serious
- Q. Material train is a ________ train.
A)Both
B)Departmental
C)Permanent
D)None of these
Answer: Departmental
- Q. EMU train has ________ type of couplings.
A)Shakuu
B)Shakau
C)Shakua
D)None of these
Answer: Shakau
- Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?
A)Source of raw material and production centers
B)Source of raw material and export centers
C)Source of raw material and ports
D)Source of raw material and markets
Answer: Source of raw material and production centers
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State