More Questions on Indian Railway
- Q. Guard shall exchange alright hand signal from ________ side while the train is started from the station.
A)Both
B)Path
C)Platform
D)None of these
Answer: Platform
- Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
A)T/407
B)T/409
C)T/408
D)T/406
Answer: T/409
- Q. How much time a railway employee associated with train operation can not drink alcohol before coming to his work?
A)6 hours
B)12 hours
C)8 hours
D)2 Hours
Answer: 8 hours
- Q. The first locomotive which was manufactured in Chittaranjan on
A)Sep - 1949
B)Nov - 1950
C)Oct - 1950
D)Oct - 1954
Answer: Nov - 1950
- Q. The time taken for formation of a goods train in flat yard is
A)3 kmph
B)2 hrs
C)1 hr
D)None of these
Answer: 2 hrs
- Q. Warner signal is of ________ shape in TALQ signalling system.
A)Both
B)Fish Tailed
C)Long
D)None of these
Answer: Fish Tailed
- Q. Yearly goods stock census is taken on ________.
A)30st November
B)31st December
C)31st October
D)31st March
Answer: 30st November
- Q. Slip siding protects
A)Station section
B)Station limit
C)Block section
D)None of these
Answer: Block section
- Q. When an incomplete parted portion arrives at a station the Driver to stop his train at ________ and give one long one short one long one short whistle.
A)Both
B)Outer Most facing Points
C)Inner Most facing signal
D)None of these
Answer: Outer Most facing Points
- Q. Normally the train with hot axle is admitted on ________.
A)Main Line
B)Loop Line
C)Siding Line
D)None of these
Answer: Main Line
- Q. Is general manager responsible for?
A)Both railway Board and Railway Ministry
B)Railway Board
C)Railway Ministry
D)None of these
Answer: Railway Board
- Q. Which Zone is the largest in Indian Railways?
A)Eastern Railway
B)Central Railway
C)Northern Railway
D)Western Railway
Answer: Eastern Railway
- Q. Normally maximum gradient in station yards in BG is (at present)
A)1 in 1000
B)1 in 260
C)1 - 400
D)None of these
Answer: 1 - 400
- Q. In double Distant signalling, outermost signal is called as ________.
A)Stop
B)Distant
C)Call-on
D)None of these
Answer: Distant
- Q. When unsafe condition of river bund is reported. CO to be issued for speed for day is
A)20 kmph
B)10 kmph
C)15 kmph
D)None of these
Answer: 15 kmph
- Q. What will be the speed of second train running on T/C 602?
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: Normal speed
- Q. Dead engine is attached at ________ position on a Mail / Express train.
A)Both
B)Engine to engine
C)Next to engine
D)None of these
Answer: Next to engine
- Q. No passenger train shall be started from a station before the ________ time
A)Both
B)Advertised
C)Non-advertised
D)None of these
Answer: Advertised
- Q. After getting T/369(I) speed over the points while passing the signal is ________ km/h.
A)25
B)75
C)15
D)30
Answer: 15
- Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
A)Sectional
B)Corner
C)Warner
D)None of these
Answer: Warner