Q. Section controller shall transmit the correct time at ________ hours daily to all the stations.

Correct Answer

16

More Questions on Indian Railway

  • Q. Which city is hosting the International Conference on Green Initiatives & Railway Electrification?
    A)Guwahati
    B)Kochi
    C)Chennai
    D)New Delhi
    Answer: New Delhi
  • Q. Where did Chapman form the committee?
    A)Edimbara
    B)Glassgo
    C)London
    D)Lords
    Answer: London
  • Q. Fog signal man must be on ________ Hrs duty.
    A)5
    B)3
    C)4
    D)None of these
    Answer: 3
  • Q. What is the width of broad gauge railway line in India?
    A)4 feet 11 inches
    B)5 feet 3 inches
    C)5 feet 6 inches
    D)5 feet 4 inches
    Answer: 5 feet 6 inches
  • Q. The following bell signal is prescribed between driver and guard to indicates ‘passing’ automatic signal at ON.
    A)Four
    B)Three
    C)Two
    D)None of these
    Answer: Two
  • Q. Maximum impact speed when shunting a single roller bearing fitted stock must be?
    A)5 kmph
    B)3 kmph
    C)4 kmph
    D)6 kmph
    Answer: 5 kmph
  • Q. ________ and ‘C’ class ODC shall not be crossed in the block section on double line.
    A)60
    B)50
    C)40
    D)75
    Answer: 40
  • Q. Which railway station entered Limca Book of Records 2018 for having all – women staff?
    A)Hazrat Nizamuddin railway station
    B)Chhatrapati Shivaji Terminus railway station
    C)Matunga railway station
    D)Kolkata railway station
    Answer: Matunga railway station
  • Q. Weight required minimum for testing IC Apparatus is the
    A)7 - 10 kg
    B)6 kg
    C)10 kg
    D)None of these
    Answer: 7 - 10 kg
  • Q. The number of Train examination report is ________.
    A)T/436
    B)T/431
    C)T/432
    D)T/436
    Answer: T/431
  • Q. Which authority shall be received to proceed for obstructed block section due to an Accident?
    A)T/A 602
    B)T-1425
    C)T-369(3b)+P.No.
    D)Simple memo
    Answer: T/A 602
  • Q. WTT will be issued ________.
    A)Three in Year
    B)Once in a Year
    C)Two in a Year
    D)None of these
    Answer: Once in a Year
  • Q. Rajasthan is under which of the following railway zones?
    A)North - Western region
    B)Northern region
    C)Western region
    D)Central Region
    Answer: North - Western region
  • Q. In context with the Indian railways what is TPWS?
    A)Train Protection Warning Stopper
    B)Train Passenger Warning System
    C)Train Protection Warning System
    D)Transmission Protection warning Stopper
    Answer: Train Protection Warning System
  • Q. Except ________ signal, cabin master shall not show any other signal from his cabin during shunting.
    A)Red hand signal
    B)Yellow signal
    C)Green signal
    D)None of these
    Answer: Red hand signal
  • Q. Tank engine can run at ________ speed if cow catcher and head light during night is provided.
    A)50 kmph
    B)Booked
    C)Sectional
    D)None of these
    Answer: Sectional
  • Q. Matheran Hill Railway is located in which state of India?
    A)Odisha
    B)Himachal Pradesh
    C)Maharashtra
    D)Meghalaya
    Answer: Maharashtra
  • Q. Consider the following steps in Budget Procedure in India: 1)The demands for grants of various ministries and departments including railways are considered by the concerned standing committees 2)Broad contours of the budget and the principles and policies underlying it are discussed. 3)A cut motion is moved in the Lok Sabha 4)Budget is presented in the House. Which among the following is the correct sequence of the above steps?
    A)4 2 1 3
    B)1 2 3 4
    C)1 2 4 3
    D)3 1 4 2
    Answer: 4 2 1 3
  • Q. During serious accident, ________ will be the in-charge of control office.
    A)Sr. DOM
    B)DOM
    C)AOM
    D)None of these
    Answer: Sr. DOM
  • Q. Maximum speed of tower wagon is ________ km/h.
    A)40
    B)25
    C)20
    D)50
    Answer: 40