More Questions on Indian Railway
- Q. During hand shunting only ________ Bogies can be hand shunted.
A)3
B)1
C)2
D)None of these
Answer: 1
- Q. Loco and traffic running staff are entitled for ________ hours rest at head quarters after running duty of 08 hours or more
A)12 hours
B)04 hours
C)08 hours
D)16 hours
Answer: 16 hours
- Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A)30
B)20
C)10
D)None of these
Answer: 30
- Q. When did the first ignition engine develop?
A)1900
B)1890
C)1892
D)1904
Answer: 1892
- Q. Wagon with livestock shall be attached ________ position from engine on a passenger train.
A)Third
B)First
C)Second
D)None of these
Answer: Second
- Q. Cancellation facility through ________ helpline number will be provided using ‘One Time Password’ sent on registered phone number.
A)139
B)144
C)123
D)119
Answer: 139
- Q. Which authority shall be issued to pass a starter signal during advanced starter single is failed and starter is interlocked with Ad. Starter at a station equipped with single line token less block?
A)Memo + Hand Signal
B)T-369(3b)
C)PLCT
D)Starter should be taken off
Answer: T-369(3b)
- Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5
B)10
C)20
D)None of these
Answer: 10
- Q. When the Loco pilot should contact with SM on telephone while IBS in “ON” position?
A)Immediate
B)After 5 minutes
C)After 2 minutes
D)After 1 miutes in day and 2 minutes in night
Answer: After 1 miutes in day and 2 minutes in night
- Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.
A)15 km
B)8 km
C)10 km
D)25 km
Answer: 25 km
- Q. Block instrument and Advanced starter being failed after line clear?
A)T-369(3B) with P. NO. of line clear
B)T/C 1425
C)T/D 602 + T-511
D)T/D 1425
Answer: T-369(3B) with P. NO. of line clear
- Q. Duplicate signal is ________.
A)Co-acting signal
B)Home Signal
C)Warner Signal
D)None of these
Answer: Co-acting signal
- Q. In automatic block system SL, the signal that can be dispensed with is
A)Automatic Stop signal
B)Home
C)Starter
D)None of these
Answer: Automatic Stop signal
- Q. Guard of goods train shall sign on ________ minutes before the actual departure of the train.
A)40
B)45
C)30
D)35
Answer: 45
- Q. The turning out time off BD SPL. During day is ________ minutes
A)50
B)30
C)20
D)None of these
Answer: 30
- Q. In case of train parting ________ bell code is given on block instrument.
A)000000-000
B)00000-0
C)000000-0
D)0000-00
Answer: 000000-000
- Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
A)Green
B)White
C)Red
D)NIL
Answer: NIL
- Q. Mountain Railways of India refer to the railway lines built in the mountains of India in the nineteenth and early twentieth century, during the British Raj, even being run today by the Indian Railways. How many railway lines refer to the Mountain Railways of India ?
A)5
B)3
C)4
D)6
Answer: 3
- Q. Besides Mahrashtra, Karnataka and Goa, which of the following is the fourth State for Konkan Railway Project?
A)Gujarat
B)Kerala
C)Tamil Nadu
D)Andhra Pradesh
Answer: Kerala
- Q. India’s first – ever railways disaster management centre will come up in which city?
A)Lucknow
B)Kolkata
C)Bengaluru
D)Pune
Answer: Bengaluru