More Questions on Indian Railway
- Q. What is the maximum speed of a goods train pushed backed from block section ?
A)15/8 kmph
B)15 kmph
C)8 kmph
D)None of these
Answer: 8 kmph
- Q. In case of defective home signal of C’ class station, T/369(3b) authority is issued on which ________ of the staion in advance is written.
A)Authority
B)Private Number
C)Cuation Number
D)None of these
Answer: Private Number
- Q. Loco pilot must have ________ sets of spectacles in his personal store.
A)Three
B)Two
C)One
D)None of these
Answer: Two
- Q. Loco and traffic running staff are entitled for ________ hours rest at head quarters after running duty of 08 hours or more
A)12 hours
B)04 hours
C)08 hours
D)16 hours
Answer: 16 hours
- Q. In Automatic Block system , in BG when there is obstruction in the adjacent line, driver to protect the adjacent line first by placing one detonator at not less than ________ , metres.
A)1200
B)600
C)800
D)None of these
Answer: 600
- Q. Each motor coach shall consist of ________ Traction motors.
A)4
B)2
C)3
D)5
Answer: 4
- Q. Competency certificate of the gateman of non- interlocked engineering gate is signed by ________.
A)PWI
B)CI
C)LI
D)TI
Answer: PWI
- Q. Loco pilot shall not take alcoholic drinks before ________ hours from signing on duty.
A)8
B)5
C)4
D)10
Answer: 8
- Q. Mission PACE deals with
A)Fast Ticketing System
B)Protection of nature
C)Help Customers
D)Quality of Goods and Services
Answer: Quality of Goods and Services
- Q. Which road suburban railway station in Mumbai has been rechristened as Prabhadevi station?
A)Churchgate
B)Boisar
C)Andheri
D)Elphinstone
Answer: Elphinstone
- Q. If the IBS is defective and advanced starter is working, SM shall issue ________ authority with private number of next station to pass IBS.
A)T/369(4b)
B)T/369(3b)
C)T/369(2B)
D)T/369(5b)
Answer: T/369(3b)
- Q. Calling on signal is a ________ signal.
A)Subsidiary
B)Permissive
C)Home
D)None of these
Answer: Subsidiary
- Q. Which railway station entered Limca Book of Records 2018 for having all – women staff?
A)Hazrat Nizamuddin railway station
B)Chhatrapati Shivaji Terminus railway station
C)Matunga railway station
D)Kolkata railway station
Answer: Matunga railway station
- Q. High flood level mark shall be painted in
A)Blue
B)Red
C)White
D)None of these
Answer: Red
- Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?
A)27 meters
B)30 meters
C)3 meters
D)100 meters
Answer: 30 meters
- Q. Indian Railway Act means ________.
A)Part 23 of 1989
B)Part 22 of 1989
C)Part 24 of 1989
D)Part 21 of 1989
Answer: Part 24 of 1989
- Q. Section controller shall transmit the correct time at ________ hours daily to all the stations.
A)16
B)20
C)12
D)10
Answer: 16
- Q. How many copies of caution order shall be prepared for a train provided with banking engine?
A)5
B)3
C)4
D)None of these
Answer: 5
- Q. Speed of the last train during ACF on double line is ________ km/h.
A)20/15/Walking
B)25/10/Walking
C)20/10/Walking
D)None of these
Answer: 25/10/Walking
- Q. ________ and ‘C’ class ODC shall not be crossed in the block section on double line.
A)60
B)50
C)40
D)75
Answer: 40