Q. Number of the Nil caution order is ________.

Correct Answer

T/A 409

More Questions on Indian Railway

  • Q. When the section is occupied, the arrow indication in the panel in Twin single line working will be
    A)No light
    B)White
    C)Red
    D)None of these
    Answer: Red
  • Q. D class stations are called as ________.
    A)Station Limit
    B)Halt Station
    C)Class station
    D)None of these
    Answer: Halt Station
  • Q. Consider the following statements about the Bio Toilet Project in Indian Railways: 1)The bio – toilets are joint initiative of Indian Railways and DRDO 2)The human excreta in the bio – toilets is treated through anaerobic digestion process 3)The bio toilet reduces the solid human waste to biogas and pure water Which of the above statements is/are correct?
    A)2 & 3 Only
    B)1 & 3 Only
    C)2 Only
    D)1, 2 & 3
    Answer: 1, 2 & 3
  • Q. Flasher light is of ________ colour.
    A)Green
    B)Red
    C)Amber
    D)None of these
    Answer: Amber
  • Q. General rules may be modified by ________.
    A)T/C 912
    B)T/B 912
    C)T/D 912
    D)T/A 912
    Answer: T/D 912
  • Q. In case of accident, siren is repeated at an interval of ________ minutes.
    A)20
    B)10
    C)15
    D)5
    Answer: 5
  • Q. To receive a train on unsignalled line, ________ authority is issued.
    A)T/369(4b) Pilot in MEMU
    B)T/369(3b) Pilot in MEMO
    C)T/369(2B) Pilot in MEMO
    D)T/369(5b) Pilot in MEMU
    Answer: T/369(3b) Pilot in MEMO
  • Q. Maximum impact speed when shunting a single roller bearing fitted stock must be?
    A)5 kmph
    B)3 kmph
    C)4 kmph
    D)6 kmph
    Answer: 5 kmph
  • Q. In which of the following cities are located 3 zonal headquarters of Indian Railways?
    A)New Delhi
    B)Guwahati
    C)Mumbai
    D)Kolkata
    Answer: Kolkata
  • Q. During prolonged failure of signals in automatic section, ________ authority is issued.
    A)T/C 912
    B)T/B 912
    C)T/D 912
    D)T/A 912
    Answer: T/D 912
  • Q. Station Master shall give line clear with ________ while granting line clear.
    A)Calling-on
    B)Shunt signal
    C)Private No.
    D)None of these
    Answer: Private No.
  • Q. When a motor trolley is in charge of office, the motor trolley can go upto outer most facing points after waiting for ________ minutes.
    A)20
    B)10
    C)15
    D)25
    Answer: 10
  • Q. During single line working of DL the speed of the first train is ________ kmph
    A)15
    B)25
    C)20
    D)None of these
    Answer: 25
  • Q. In double Distant signalling, outermost signal post is painted with ________.
    A)Green & Yellow
    B)White & yellow
    C)Black & Yellow
    D)None of these
    Answer: Black & Yellow
  • Q. SCOR maintains ________ register when serious accident occurs.
    A)Chronological
    B)Logical
    C)Un-logical
    D)None of these
    Answer: Chronological
  • Q. Motor vehicle in closed wagon shall be attached ________ position from engine on a goods train.
    A)Third
    B)First
    C)Second
    D)None of these
    Answer: Third
  • Q. By whom the rear portion of train left behind in block section protected?
    A)By engineearing official
    B)By Guard
    C)By LP
    D)No need to protect the load
    Answer: By Guard
  • Q. Depot in-charge is responsible to test the detonators once in ________.
    A)Year
    B)Monthly
    C)Weekly
    D)None of these
    Answer: Year
  • Q. Traffic gates are those located between ________.
    A)First signal
    B)Outermost stop signal
    C)Stop signal
    D)None of these
    Answer: Outermost stop signal
  • Q. To apply for Line block, the notice shall be given to DRM not less than
    A)12 hours
    B)48 hours
    C)24 hours
    D)None of these
    Answer: 24 hours