Q. Maximum speed of tower wagon is ________ km/h.

Correct Answer

40

More Questions on Indian Railway

  • Q. Presentation of the first ever railway budget in India held in
    A)1925
    B)1853
    C)1888
    D)1905
    Answer: 1925
  • Q. Ruling gradient of the division is mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. ________ form shall be used by GDR when a person falls out of train injured or killed.
    A)ACC4
    B)ACC2
    C)ACC3
    D)None of these
    Answer: ACC4
  • Q. Permissible limit of flat tyre in goods and coaching vehicles is 60mm and ________ respectively.
    A)80 mm
    B)60 mm
    C)70 mm
    D)50 mm
    Answer: 50 mm
  • Q. When was the nationalization of Indian Railways done?
    A)1951
    B)1952
    C)1950
    D)1954
    Answer: 1950
  • Q. To start the train from a line with common starter, ________ authority is issued.
    A)T/512
    B)T/516
    C)T/517
    D)T/511
    Answer: T/512
  • Q. Weight required minimum for testing IC Apparatus is the
    A)7 - 10 kg
    B)6 kg
    C)10 kg
    D)None of these
    Answer: 7 - 10 kg
  • Q. When a driver passing an automatic gate stop signal at ‘ON’ he must stop short of the gate of
    A)25 meters
    B)30 meters
    C)45 meters
    D)None of these
    Answer: None of these
  • Q. Gorakhpur which has the longest railway platform in the world is located in which of the following states?
    A)Uttar Pradesh
    B)Odisha
    C)West Bengal
    D)Chhattisgarh
    Answer: Uttar Pradesh
  • Q. Whenever new signal is placed, caution order is issued to Loco Pilot for ________ days.
    A)35
    B)15
    C)20
    D)10
    Answer: 10
  • Q. The headquarters of the South Central Railway zone is located in?
    A)Hyderabad
    B)Kolkata
    C)Secunderabad
    D)Gorakhpur
    Answer: Secunderabad
  • Q. What will be distance between fire affected train and rest of the train ?
    A)50 meters
    B)25 meters
    C)45 meters
    D)100 meters
    Answer: 45 meters
  • Q. During TFC in double line which authority to serve the driver for train operation?
    A)TC-602
    B)TC-1425
    C)TA-602
    D)TD-1425
    Answer: TC-602
  • Q. Form number of disconnection and reconnection is ________.
    A)S&T (T/350)
    B)S&T (T/351)
    C)S&T (T/352)
    D)S&T (T/315)
    Answer: S&T (T/351)
  • Q. During thick & foggy weather, line must be clear upto ________ for granting line clear at a B’ class station in TALQ signalling system on Double line.
    A)Shunt signal
    B)Calling-on Signal
    C)Home Signal
    D)None of these
    Answer: Home Signal
  • Q. Where was the B.B.C.I locomotive started?
    A)Boriville
    B)Jamalpur
    C)Parel
    D)Hyderabad
    Answer: Parel
  • Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
    A)T/407
    B)T/409
    C)T/408
    D)T/406
    Answer: T/409
  • Q. Approved special instructions are issued by ________.
    A)PCOM
    B)CRS
    C)MT
    D)None of these
    Answer: CRS
  • Q. For block forwarded form ________ must be issued.
    A)Both
    B)T/806+LSSS
    C)T/608
    D)None of these
    Answer: T/806+LSSS
  • Q. Calling on signal shows ________ light in off position in two aspect signalling system.
    A)Green
    B)White
    C)RED
    D)Yellow
    Answer: Yellow