Q. ISMD must be attached always

Correct Answer

Next to Engine

More Questions on Indian Railway

  • Q. To admit the train on loop line, generally the far end points are to be ser for ________.
    A)Both
    B)Loop line
    C)Main line
    D)None of these
    Answer: Main line
  • Q. At the starting station, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 100
  • Q. When the calling on signal is taken off, it indicates the loco pilot to proceed ________ and be prepared to stop short of any obstruction.
    A)Defective
    B)Caution
    C)Cautiously
    D)None of these
    Answer: Cautiously
  • Q. Block competency certificate is issued by ________.
    A)AOM
    B)Principal ZRTI
    C)SM
    D)None of these
    Answer: Principal ZRTI
  • Q. On the electrified area in sections at 25 KV A.C., when the gross clearance is between 390 MM and 340 MM the speed must be
    A)8 kmph
    B)10 kmph
    C)15 kmph
    D)None of these
    Answer: 15 kmph
  • Q. Normally maximum gradient in station yards in BG is (at present)
    A)1 in 1000
    B)1 in 260
    C)1 - 400
    D)None of these
    Answer: 1 - 400
  • Q. Target time for dispatch of ARME from single exit siding at night is ________ minutes.
    A)8
    B)10
    C)5
    D)25
    Answer: 25
  • Q. When the platform level is ________ MM and more second arriving train shall not be received and berthed on non platform line directly.
    A)650
    B)700
    C)725
    D)760
    Answer: 760
  • Q. The headquarters of South Railways is situated at
    A)Delhi
    B)Kolkata
    C)Chennai
    D)Mumbai
    Answer: Chennai
  • Q. In case of 1 in 100 rising gradient, ________ siding is provided.
    A)Slip
    B)Long
    C)Catch
    D)None of these
    Answer: Slip
  • Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
    A)5
    B)10
    C)20
    D)None of these
    Answer: 10
  • Q. The first Shatabdi express was introduced between which of the following locations?
    A)New Delhi and Jhansi
    B)Bombay and Thane
    C)Bombay and Kolkata
    D)New Delhi and Chennai
    Answer: New Delhi and Jhansi
  • Q. Signals are treated as ________ if connected points become defective.
    A)Both
    B)Defective
    C)Restricted
    D)None of these
    Answer: Defective
  • Q. Loss of Railway property of ________ is treated as serious accident.
    A)75 Lakhs
    B)More than 50 lakhs
    C)01 crore
    D)More than 02 crore
    Answer: More than 02 crore
  • Q. Signal sighting committee shall submit its report on form ________.
    A)T/101 B
    B)T/103 B
    C)T/102 B
    D)None of these
    Answer: T/102 B
  • Q. Between which of the destinations the first Indian train was started?
    A)From Mumbai to Surat
    B)From Kolkata to Delhi
    C)From Mumbai to Thane
    D)From Mumbai to Madras
    Answer: From Mumbai to Thane
  • Q. Clocks of control office shall be synchronized with All India Radio at 08:00 hours,
    A)15:30
    B)14:30
    C)12:30
    D)13:30
    Answer: 13:30
  • Q. The headquarters of North – East Frontier Railway (NFR) is
    A)Chennai
    B)Kolkata
    C)Maligaon (Guwahati)
    D)Gorakhpur
    Answer: Maligaon (Guwahati)
  • Q. When the engine is pushing a material train and BV is not leading, the speed shall not exceed.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)30 kmph
    Answer: 10 kmph
  • Q. Height gauge is for the safety of ________.
    A)Motor Trolley
    B)Trolley
    C)Ohe
    D)None of these
    Answer: Ohe