More Questions on Indian Railway
- Q. Which is the least signalto be installed on C class stations in multiple aspect signalling?
A)Warner, Home
B)Outer, Home
C)Distant, Home
D)Distant, Home, Starter
Answer: Distant, Home
- Q. Impact speed of shunting of one box wagon is ________ km/h.
A)6
B)2
C)5
D)8
Answer: 5
- Q. Block competency certificate is given in the prescribed form ________.
A)T/115A
B)T/115B
C)T/115C
D)T/115D
Answer: T/115B
- Q. Isolation shall be provided at an interlocked station when the speed is
A)Above 50 kmph
B)50 kmph
C)75 kmph
D)None of these
Answer: Above 50 kmph
- Q. In case of home signal defective the speed of the train while passing over the points shall not be more than ________ km/h.
A)15 km
B)18 km
C)10 km
D)20 km
Answer: 15 km
- Q. Normally the train with hot axle is admitted on ________.
A)Main Line
B)Loop Line
C)Siding Line
D)None of these
Answer: Main Line
- Q. The headquarters of South Railways is situated at
A)Delhi
B)Kolkata
C)Chennai
D)Mumbai
Answer: Chennai
- Q. When a front portion of a parted train gives one long one short one long one short whistle, SM to wave ________ signal four times above head from side to side and acknowledge.
A)Yellow
B)RED
C)Green
D)None of these
Answer: RED
- Q. The banner flag is a ________
A)Both of these
B)Temporary stop signal
C)Permanent stop signal
D)None of these
Answer: Temporary stop signal
- Q. The maximum speed of a train while passing through station of interlocking std III is?
A)140 kmph
B)50 kmph
C)110 kmph
D)160 kmph
Answer: 140 kmph
- Q. D class station board is placed ________ meters from the end of the platform.
A)600
B)400
C)500
D)800
Answer: 500
- Q. What action shall be taken by loco pilot if Guard failed to exchange all right signal after passing engineering speed restriction zone?
A)Stop his train and find the cause
B)Proceed further with same speed up to next station
C)Proceed further with normal speed
D)None of these
Answer: Stop his train and find the cause
- Q. Weight required minimum for testing IC Apparatus is the
A)7 - 10 kg
B)6 kg
C)10 kg
D)None of these
Answer: 7 - 10 kg
- Q. Cotton in closed wagon shall be attached ________ position from engine on a goods train.
A)Third
B)First
C)Second
D)None of these
Answer: Second
- Q. Consider the following statements about the Bio Toilet Project in Indian Railways: 1)The bio – toilets are joint initiative of Indian Railways and DRDO 2)The human excreta in the bio – toilets is treated through anaerobic digestion process 3)The bio toilet reduces the solid human waste to biogas and pure water Which of the above statements is/are correct?
A)2 & 3 Only
B)1 & 3 Only
C)2 Only
D)1, 2 & 3
Answer: 1, 2 & 3
- Q. In which of the following cities is the National Rail Museum located ?
A)Hyderabad
B)Mumbai
C)New Delhi
D)Chennai
Answer: New Delhi
- Q. Loco and traffic running staff are eligible for ________ hours rest at Head quarters after running duty of less than 08 hours.
A)12 Hours
B)06 Hours
C)10 Hours
D)None of these
Answer: 12 Hours
- Q. During TFC in single line section what authority to proceed will be served to driver of Dn train during return.
A)TH-602
B)T/A-602
C)TG-602
D)TB-602
Answer: TH-602
- Q. Except ________ signal, cabin master shall not show any other signal from his cabin during shunting.
A)Red hand signal
B)Yellow signal
C)Green signal
D)None of these
Answer: Red hand signal
- Q. With respect to ‘Operating ratio’ in Railways, which of the following statement is/are correct? 1)The higher is the ‘Operating Ratio’; the better is the economic condition of railways. 2) ‘Operating ratio’ of Indian Railways is high on account of social service obligation imposed in Budget. Select the correct option from the codes given below
A)Both 1 & 2
B)Only 1
C)Only 2
D)Neither 1 nor 2
Answer: Only 2