Q. Flasher lights will be provided in all ________ engines working on DL and Automatic areas.

Correct Answer

Electrical & Diesel

More Questions on Indian Railway

  • Q. The headquarters of South Railways is situated at
    A)Delhi
    B)Kolkata
    C)Chennai
    D)Mumbai
    Answer: Chennai
  • Q. In automatic block area SL. The LSS shall not be taken off unless the line is clear upto
    A)Automatic stop signal+180 Meters
    B)Next automatic stop signal
    C)Automatic stop signal+120 Meters
    D)None of these
    Answer: Next automatic stop signal
  • Q. Which train in India has the longest route length?
    A)Kanyakumari - Dibrugarh Vivek Express
    B)Howrah - Jammu Tawi Himgiri Express
    C)Kanyakumari - Jammu Tawi Himsagar Express
    D)Guwahati - Tiruvananthapuram Express
    Answer: Kanyakumari - Dibrugarh Vivek Express
  • Q. In case of vehicles escaping on wrong line, ________ bell code is given on block Instrument to inform the station in advance.
    A)0000-000
    B)000000-0000
    C)00000-0
    D)0000-0000
    Answer: 000000-0000
  • Q. Approved special instructions are issued by ________.
    A)PCOM
    B)CRS
    C)MT
    D)None of these
    Answer: CRS
  • Q. When the engine is pushing a material train and BV is not leading, the speed shall not exceed.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)30 kmph
    Answer: 10 kmph
  • Q. When a Train carrying passengers does not arrive within ________ minutes plus running time. The SM must take action.
    A)15
    B)10
    C)20
    D)None of these
    Answer: 10
  • Q. Which of the following is / are eligible to receive Ways and Means Advances from RBI to handle their temporary mismatch in the cash flow? 1)State Governments 2)Central Government 3)Public Sector Companies 4)Indian Railways Select the correct option from the codes given below:
    A)Only 1 & 3
    B)Only 1
    C)Only 1 & 2
    D)Only 1, 3 & 4
    Answer: Only 1
  • Q. While stabling box load, hand brakes of ________ wagons at both ends shall be pinned down.
    A)7 - 7
    B)8 - 8
    C)6 - 6
    D)8 - 8
    Answer: 6 - 6
  • Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
    A)Sectional
    B)Corner
    C)Warner
    D)None of these
    Answer: Warner
  • Q. Where is the Research, Design and Standard Organization situated?
    A)Pune
    B)Lucknow
    C)Bangalore
    D)New Delhi
    Answer: Lucknow
  • Q. Danger zone in 1500 DC traction is ________ meters from OHE.
    A)3
    B)1
    C)2
    D)4
    Answer: 1
  • Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. High flood level mark shall be painted in
    A)Blue
    B)Red
    C)White
    D)None of these
    Answer: Red
  • Q. How many systems of working in Indian Railways for train operation?
    A)8
    B)6
    C)7
    D)9
    Answer: 6
  • Q. In the panel working for cancellation of route the number in the counter changes and white indication appears after
    A)50 seconds
    B)120 seconds
    C)90 seconds
    D)None of these
    Answer: 120 seconds
  • Q. When a motor trolley is in charge of office, the motor trolley can go upto outer most facing points after waiting for ________ minutes.
    A)20
    B)10
    C)15
    D)25
    Answer: 10
  • Q. What is the position of the Indian Railway in the world according to the length of rail lines?
    A)Third
    B)First
    C)Second
    D)Fourth
    Answer: Fourth
  • Q. Guard of goods train shall sign on ________ minutes before the actual departure of the train.
    A)40
    B)45
    C)30
    D)35
    Answer: 45
  • Q. IN the BD Spl, the water must be filled ________.
    A)Three Week
    B)Once a week
    C)Two week
    D)None of these
    Answer: Once a week