Q. Except ________ signal, cabin master shall not show any other signal from his cabin during shunting.

Correct Answer

Red hand signal

More Questions on Indian Railway

  • Q. Speed of train shall not be more than ________ km/h in case of whistle failure in block section.
    A)25
    B)20
    C)15
    D)30
    Answer: 25
  • Q. Notice station caution order No. is ________
    A)T/C-409
    B)T/409
    C)T/B-409
    D)None of these
    Answer: T/409
  • Q. Motor Trolly can follow another motor trolly during
    A)Day and Night clear weather
    B)Day and Night
    C)Day only
    D)None of these
    Answer: Day and Night clear weather
  • Q. passing through station during day when running without brakevan and tail board.
    A)25 kmph
    B)10 kmph
    C)20 kmph
    D)Normal speed
    Answer: 20 kmph
  • Q. Distant signal is a ________ signal.
    A)Subsidiary
    B)Permissive
    C)Home
    D)None of these
    Answer: Permissive
  • Q. Motorman shall give ________ beat to release the hand brakes.
    A)00-00-00
    B)00-0-00
    C)0-0-0
    D)0-00-00
    Answer: 00-0-00
  • Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?
    A)27 meters
    B)30 meters
    C)3 meters
    D)100 meters
    Answer: 30 meters
  • Q. If the driver does not receive all right signal from the guard, he must call by giving.
    A)On long
    B)Two sharp whistles
    C)One long one short
    D)None of these
    Answer: Two sharp whistles
  • Q. Sand hump is a substitute to ________ and also a means of isolation.
    A)Over signal
    B)Signal
    C)Signal overlap
    D)None of these
    Answer: Signal overlap
  • Q. The headquarters of South Railways is situated at
    A)Delhi
    B)Kolkata
    C)Chennai
    D)Mumbai
    Answer: Chennai
  • Q. Distant signal shows ________ light in normal condition in double distant signalling is provided.
    A)Three yellow
    B)One Yellow
    C)Two yellow
    D)Four yellow
    Answer: Two yellow
  • Q. Time taken by train running at MPS is called as ________.
    A)Normal running time
    B)Long time
    C)Minimum running time
    D)None of these
    Answer: Minimum running time
  • Q. Whenever new signal is put into use, signal sighting committee submits its joint report on
    A)T/104C
    B)T/105B
    C)T/106B
    D)T/102B
    Answer: T/102B
  • Q. Mixed and Goods trains worked with vacuum throughout, the following number of vehicles can be attached in rear of BV.
    A)Not more than two bogies or their equivalent
    B)Two Bogies
    C)04 four wheelers only
    D)None of these
    Answer: Not more than two bogies or their equivalent
  • Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
    A)8 kmph
    B)15 kmph
    C)10 kmph
    D)Normal
    Answer: 10 kmph
  • Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
    A)LI
    B)TI
    C)CI
    D)None of these
    Answer: TI
  • Q. Last stop signal means the ________ of a station controlling the entry of trains into the next block section.
    A)Call-on Signal
    B)Fixed stop signal
    C)Hand Signal
    D)None of these
    Answer: Fixed stop signal
  • Q. High flood level mark shall be painted in
    A)Blue
    B)Red
    C)White
    D)None of these
    Answer: Red
  • Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: 2 Only
  • Q. Which of the following stations was formerly known as Victoria Terminus?
    A)Lokmanya Tilak Terminus
    B)Churchgate Railway Station
    C)Mumbai Central
    D)Chhatrapati Shivaji Terminus
    Answer: Chhatrapati Shivaji Terminus

Leave a Comment