Q. Cancellation facility through ________ helpline number will be provided using ‘One Time Password’ sent on registered phone number.

Correct Answer

139

More Questions on Indian Railway

  • Q. Whenever new signal is put into use, signal sighting committee submits its joint report on
    A)T/104C
    B)T/105B
    C)T/106B
    D)T/102B
    Answer: T/102B
  • Q. Running staff should not normally be away from head quarters for more than hours at a stretch.
    A)72
    B)24
    C)48
    D)None of these
    Answer: 72
  • Q. When the derailing switch is open, trap indicator shows red target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: Red
  • Q. The headquarters of North – Eastern railway is situated at
    A)Gorakhpur
    B)Mumbai (CST)
    C)Guwahati
    D)New Delhi
    Answer: Gorakhpur
  • Q. Section controller shall transmit the correct time at ________ hours daily to all the stations.
    A)16
    B)20
    C)12
    D)10
    Answer: 16
  • Q. While ordering ART/MRV each siren shall be sounded for ________ seconds.
    A)43
    B)41
    C)42
    D)45
    Answer: 45
  • Q. At the starting station, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 100
  • Q. When did the first ignition engine develop?
    A)1900
    B)1890
    C)1892
    D)1904
    Answer: 1892
  • Q. Who of the following was the first Railway Minister of independent India?
    A)Jawaharlal Nehru
    B)John Mathai
    C)Lal Bahadur Shastri
    D)Shanmugham Shetty
    Answer: John Mathai
  • Q. Maximum No. of ________ explosive wagons can be attached to a goods train.
    A)6
    B)5
    C)4
    D)10
    Answer: 5
  • Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
    A)30
    B)20
    C)10
    D)None of these
    Answer: 30
  • Q. Target time for dispatch of ARME from single exit siding at night is ________ minutes.
    A)8
    B)10
    C)5
    D)25
    Answer: 25
  • Q. During accident or Engine failure in the mid section the report sent to SM must be signed by ________.
    A)Both
    B)GDR
    C)TDR
    D)None of these
    Answer: GDR
  • Q. Semaphore of the signal is painted in the colour as it shows in the night in ________ condition.
    A)Both
    B)Off
    C)On
    D)None of these
    Answer: On
  • Q. When was Petrol Rail car started on Kalka – Shimla Rail route?
    A)1918
    B)1911
    C)1913
    D)1917
    Answer: 1911
  • Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
    A)T/407
    B)T/409
    C)T/408
    D)T/406
    Answer: T/409
  • Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
    A)8 kmph
    B)15 kmph
    C)10 kmph
    D)Normal
    Answer: 10 kmph
  • Q. When was the Central Railway established?
    A)14th April 1951
    B)5th Nov 1951
    C)14th Nov 1951
    D)16th August, 1951
    Answer: 5th Nov 1951
  • Q. What is the maximum speed of shunting of a petrol tank wagon?
    A)2 kmph
    B)15 kmph
    C)8 kmph
    D)5 kmph
    Answer: 8 kmph
  • Q. Competency certificate of the gateman of interlocked engineering gate is issued by
    A)SSE/C & W
    B)SSE/P.way
    C)SSE/Sig.
    D)None of these
    Answer: SSE/P.way