Q. Besides Maharashtra, Karnataka and Goa, which of the following is the fourth State for Konakan Railway Project?

Correct Answer

Kerala

More Questions on Indian Railway

  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. At the starting station, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 100
  • Q. When the train has not cleared the fouling marks. Driver to give ________ whistle
    A)01 long
    B)03 long
    C)02 long
    D)None of these
    Answer: 03 long
  • Q. Passenger warning board is placed at a distance of ________ meters from the first stop signal.
    A)1500
    B)1200
    C)1000
    D)1800
    Answer: 1000
  • Q. In automatic areas when all signals have failed and communication is available, the driver is issued ________ as authority to proceed.
    A)T/C-912
    B)T/B-912
    C)T/D-912
    D)None of these
    Answer: T/D-912
  • Q. In Automatic Block system , in BG when there is obstruction in the adjacent line, driver to protect the adjacent line first by placing one detonator at not less than ________ , metres.
    A)1200
    B)600
    C)800
    D)None of these
    Answer: 600
  • Q. Which type Authority to proceed shall be used at without starter signal station on single line?
    A)Any one
    B)Non Tangible
    C)Tangible
    D)None of these
    Answer: Tangible
  • Q. Flasher light is of ________ colour.
    A)Green
    B)Red
    C)Amber
    D)None of these
    Answer: Amber
  • Q. Semi-automatic signal is identified by ________.
    A)Illuminated a marker
    B)Marker
    C)Semi marker
    D)None of these
    Answer: Illuminated a marker
  • Q. Corridor block is mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. Loco Pilot shall sound _________ whistle to acknowledge the Guard hand signal.
    A)Three Long
    B)One Long
    C)Two Long
    D)None of these
    Answer: One Long
  • Q. Maximum speed of B’ class ODC is ________ km/h.
    A)60
    B)50
    C)40
    D)75
    Answer: 40
  • Q. BSLB determines the limits of block section and ________ .
    A)Station Limit
    B)Block Section
    C)Station Section
    D)None of these
    Answer: Station Section
  • Q. Distance between outer and home signals on a single line is ________ meters when there is advanced starter or SLB in the opposite direction.
    A)540
    B)900
    C)580
    D)570
    Answer: 580
  • Q. What is maximum width of coaching stock in BG?
    A)3250 mm
    B)3050 mm
    C)3200 mm
    D)3300 mm
    Answer: 3250 mm
  • Q. Sounding of ________ hooters means accident of goods train at home station.
    A)6
    B)2
    C)4
    D)8
    Answer: 2
  • Q. What action shall be taken by loco pilot if Guard failed to exchange all right signal after passing engineering speed restriction zone?
    A)Stop his train and find the cause
    B)Proceed further with same speed up to next station
    C)Proceed further with normal speed
    D)None of these
    Answer: Stop his train and find the cause
  • Q. In case of ACP, Assistant Loco Pilot shall proceed towards the rear from ________ side.
    A)Back
    B)Left
    C)Right
    D)Noe of these
    Answer: Right
  • Q. In TALQ signalling system, ________ signal will be treated as defective if home signal becomes defective.
    A)Hand
    B)Outer
    C)Call-On
    D)Non eof these
    Answer: Outer
  • Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
    A)5
    B)10
    C)20
    D)None of these
    Answer: 10

Leave a Comment