More Questions on Indian Railway
- Q. Number of train signal register of single line is ________.
A)T/166 B
B)T/136 A
C)T/137 B
D)T/135
Answer: T/137 B
- Q. When was the Jammu City appeared on the map of Indian Railway?
A)1967
B)1956
C)1963
D)1965
Answer: 1965
- Q. By whom General Rule is prepared?
A)PCOM
B)Railway Board
C)Zonal Railway
D)GM
Answer: Railway Board
- Q. If the advanced starter and IBS are defective, SM shall issue T/369(3b) authority with private number of ________ station to pass both advanced starter and IBS.
A)Both
B)Back
C)Next
D)None of these
Answer: Next
- Q. When the points are set for main line, point indicator shows white target by day and ________ Light by night.
A)Yellow
B)Red
C)Green
D)White
Answer: White
- Q. Which of the following is the largest railway junction in India?
A)Mathura
B)Delhi
C)Bhatinda
D)Allahabad
Answer: E
- Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
A)Shunt
B)Repeating
C)Call-on
D)None of these
Answer: Repeating
- Q. In diesel engine, ignition is caused by
A)Compression
B)Spark
C)Automatic starter
D)Friction
Answer: Compression
- Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
A)3 kmph
B)2 kmph
C)2.5 kmph
D)3.5 kmph
Answer: 2.5 kmph
- Q. What will be the speed of goods train without brake van while passing station if tail lamp is not provided?
A)Normal
B)20 kmph
C)50 kmph
D)Stop at every station
Answer: 20 kmph
- Q. In which year the practice of presenting the railway budget separate from the general budget (or vice versa in true sense) started in India?
A)1925
B)1920
C)1924
D)1930
Answer: 1924
- Q. What is the massage of 000 (three short) whistle sound by loco pilot?
A)Train parting
B)Signal Approaching
C)Train out of control
D)Unable to proceed
Answer: Train out of control
- Q. Signals are normally located to the ________ side of the line.
A)Both
B)Right
C)Left
D)None of these
Answer: Left
- Q. Which whistle code shall be used by loco pilot while Guard’s assistance is required?
A)Three short
B)Long continue
C)Intermediate long continue
D)Three long
Answer: Three short
- Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
A)Both
B)Temporary Working Order.
C)Permanent working order.
D)None of these
Answer: Temporary Working Order.
- Q. Not more than ________ officials can travel in the locomotive unless authorised by operating official.
A)3
B)2
C)4
D)6
Answer: 3
- Q. What is the maximum speed in block section during thick & foggy weather?
A)15 kmph
B)30 kmph
C)60 kmph
D)Not to move
Answer: 60 kmph
- Q. Food Safety and Standards Authority of India (FSSAI) certified ________ as India’s first Eat Right Station.
A)Mumbai Central railway station
B)Chennai Central railway station
C)Chhatrapati Shivaji Maharaj railway station
D)Bengaluru Central railway station
Answer: Mumbai Central railway station
- Q. Patrolman becoming overdue during night.
A)40 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 10 kmph
- Q. If loco pilot do not work in any section for more than a year, road learning for 2 trips by day and ________ trip by night is given.
A)3
B)1
C)2
D)4
Answer: 2