More Questions on Indian Railway
- Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
A)30
B)20
C)25
D)15
Answer: 15
- Q. At which of the following places Diesel Component Works is established?
A)Perambur
B)Jamshedpur
C)Patiala
D)Varanasi
Answer: Patiala
- Q. In one train only system, information of lost of metal token is given to ________.
A)DRM
B)DOM
C)AOM
D)None of these
Answer: DRM
- Q. Competency certificate of the gateman of non- interlocked engineering gate is signed by ________.
A)PWI
B)CI
C)LI
D)TI
Answer: PWI
- Q. The passenger bogies of the Indian Railways are manufactured at which of the following places?
A)Perambur
B)Kapurthala
C)Chittranjan
D)Bangalore
Answer: Perambur
- Q. Which of the following is the largest zone in terms of route kilometers?
A)Northern Railways
B)Western Railways
C)Eastern Railways
D)Southern Railways
Answer: Northern Railways
- Q. When was the first train in India started?
A)1853
B)1851
C)1852
D)1854
Answer: 1853
- Q. Duplicate signal is ________.
A)Co-acting signal
B)Home Signal
C)Warner Signal
D)None of these
Answer: Co-acting signal
- Q. Maximum No. of ________ track machines can be sent for working in a block section.
A)25
B)20
C)15
D)30
Answer: 25
- Q. On which time the watch shall be set by loco pilot with Station masters watch?
A)A & B both
B)At 8.00 Hrs
C)At 16.00 Hrs
D)At the time of on duty
Answer: At the time of on duty
- Q. In case of 1 in 100 rising gradient, ________ siding is provided.
A)Slip
B)Long
C)Catch
D)None of these
Answer: Slip
- Q. On which place the competent Railway servant shall be appointed to show proceed hand signal while receive a train on obstructed line on calling-on signal?
A)45 meters beyond the obstruction
B)At 1st facing point of station
C)Facing point of concern line
D)No need
Answer: 45 meters beyond the obstruction
- Q. What will be the prescribed form for DMT Block?
A)E/223
B)T/409
C)T/806
D)E/233
Answer: E/223
- Q. While shunting a complete train from one line to the other, ________ shall be present in the brakevan.
A)ALP
B)Driver
C)Guard
D)None of these
Answer: Guard
- Q. “C” class ODC is run with the permission of ________.
A)Head Quarter
B)DOM
C)CRS
D)None of these
Answer: CRS
- Q. Speed of following tower wagon in the block section is ________ km/h.
A)8
B)5
C)2
D)4
Answer: 8
- Q. Signals are normally located to the ________ side of the line.
A)Both
B)Right
C)Left
D)None of these
Answer: Left
- Q. When a Goods train is working without guard or BV or Guard and BV the speed is
A)10
B)25
C)20
D)None of these
Answer: 25
- Q. Consider the following railway zones with their headquarters: West Central Railway→ Jabalpur East Coast Railway → Bhubaneswar Western Railway→ Mumbai Which of the above is / are correct?
A)1, 2 & 3
B)1 & 2 Only
C)2 & 3 Only
D)None
Answer: 1, 2 & 3
- Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
A)25/10 kmph
B)15/8 kmph
C)25/8 kmph
D)25/12 kmph
Answer: 25/8 kmph
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State