More Questions on Indian Railway
- Q. Impact speed of shunting of one box wagon is ________ km/h.
A)6
B)2
C)5
D)8
Answer: 5
- Q. Section controller is responsible for ________ on a section of a railway provided with the system of speech communication.
A)Station Traffic
B)Movement of traffic
C)None of Traffic
D)None of these
Answer: Movement of traffic
- Q. To receive the train which has entered the block section without authority to proceed, SM to issue ________ and pilot the train or by signal post telephone.
A)T/369(B)
B)T/369(3b)
C)T/369(2b)
D)None of these
Answer: T/369(2b)
- Q. When a token is lost, the lost token notice is issued and it is valid for ________ months.
A)3
B)6
C)4
D)2
Answer: 6
- Q. When a Goods train is working without guard or BV or Guard and BV the speed is
A)10
B)25
C)20
D)None of these
Answer: 25
- Q. On which authority relief train shall be dispatched for obstructed block section?
A)On memo
B)PLCT
C)T/A602
D)None of these
Answer: T/A602
- Q. Which is the fastest train in India?
A)Duronto Express
B)Rajdhani Express
C)Shatabdi Express
D)Tejas Express
Answer: E
- Q. In which year Indian Railway was nationalized?
A)1952
B)1947
C)1951
D)1955
Answer: 1951
- Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
A)Walkie-Talkie
B)Walkie
C)VHF
D)None of these
Answer: Walkie-Talkie
- Q. The zone with the minimum length is
A)South - East Railway
B)North - Eastern Railway
C)North - Eastern Frontier Railway
D)South - Central Railway
Answer: North - Eastern Frontier Railway
- Q. During single line working of DL the speed of the first train is ________ kmph
A)15
B)25
C)20
D)None of these
Answer: 25
- Q. On double line, when a running line is blocked by stabled load , the point to be set against are
A)Advance point
B)Either side points
C)Rear points
D)None of these
Answer: Rear points
- Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
A)25/10 kmph
B)15/8 kmph
C)25/8 kmph
D)25/12 kmph
Answer: 25/8 kmph
- Q. If the SE (P.way) is not with the train, maximum speed at the spot of lurch shall be ________ km/h.
A)10
B)15
C)20
D)25
Answer: 10
- Q. BSLB determines the limits of Station section and ________.
A)Station Limit
B)Block Section
C)Station Section
D)None of these
Answer: Block Section
- Q. Shunting to be done in D/L block section
A)T-806
B)PLCT
C)T-369(3b)
D)Simple memo
Answer: T-806
- Q. During failure of signals and communications in DL automatic area the authority to proceed is
A)T/B 912
B)T/D 912
C)T/A 912
D)None of these
Answer: T/B 912
- Q. The numbers of A, B and C coaches are 72, ________ and 76.
A)71
B)72
C)70
D)75
Answer: 70
- Q. At the starting station, M/E train must have ________ % of brake power.
A)90
B)75
C)50
D)100
Answer: 100
- Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
A)Shunt
B)Repeating
C)Call-on
D)None of these
Answer: Repeating