Q. “Act” means the Railway Act is ________.

Correct Answer

1989 (24 of 1989)

More Questions on Indian Railway

  • Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
    A)30
    B)20
    C)10
    D)None of these
    Answer: 30
  • Q. Who of the following was the first Railway Minister of independent India?
    A)Jawaharlal Nehru
    B)John Mathai
    C)Lal Bahadur Shastri
    D)Shanmugham Shetty
    Answer: John Mathai
  • Q. Gateman competency certificate of interlocked traffic gate is signed by TI and SE (Sig) and counter signed by ________.
    A)DOM
    B)AOM(G)
    C)AOM(Chg)
    D)None of these
    Answer: AOM(G)
  • Q. Night duty should not normally be performed by the running staff for more than ________ nights at a stretch.
    A)6
    B)10
    C)12
    D)None of these
    Answer: 6
  • Q. Single line working inforce on double line.
    A)T/D 602
    B)T-511
    C)T-512
    D)Simple memo
    Answer: T/D 602
  • Q. Read the Following Railway Headquarters and Identify which is False?
    A)South Railway - Chennai
    B)South - Central Railway - Secunderabad
    C)Central railway - Bhopal
    D)North Railway - New Delhi
    Answer: Central railway - Bhopal
  • Q. What should be done by guard if train entering in block section without authority to proceed?
    A)Protect the Train
    B)Stop the Train
    C)Inform to SM
    D)All of above
    Answer: All of above
  • Q. Max. Speed of passenger train attached with four wheeler wagon shall be ________ km/h.
    A)45
    B)70
    C)65
    D)75
    Answer: 75
  • Q. Where is the wheel and axle plant of Indian Railways situated?
    A)Bangalore
    B)Chittranjan
    C)Kapurthala
    D)Perambur
    Answer: Bangalore
  • Q. Normally material train will work during ________.
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. BD special shall be turned out during night within
    A)30 meters
    B)25 meters
    C)45 meters
    D)None of these
    Answer: 45 meters
  • Q. For extinguished home signal, Loco Pilot will be issued ________ authority form the station in rear in MACLS system.
    A)16
    B)20
    C)12
    D)10
    Answer: 16
  • Q. In which year palace on wheels train inaugurated?
    A)1982
    B)1988
    C)1978
    D)1965
    Answer: 1982
  • Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 15 kmph
  • Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the engine.
    A)3
    B)5
    C)2
    D)4
    Answer: 5
  • Q. Repeating signal shows ________ light in ON condition.
    A)Green
    B)Red
    C)Yellow
    D)None of these
    Answer: Red
  • Q. Length of a standard BG loop line is
    A)720 meters
    B)686 meters
    C)670 meters
    D)None of these
    Answer: 686 meters
  • Q. Which of the following committee gave recommendations on separation of Policy – making, Regulation & Operations in Indian Railways and setting up of a Railway Regulatory Authority of India (RRAI)?
    A)Rajinder Sachar Committee
    B)Bibek Deberoy committee
    C)Rangarajan committee
    D)Mihir Shah Committee
    Answer: Bibek Deberoy committee
  • Q. How many surrounding area may be sealed from fire in case of leakage in LPG tank wagon?
    A)1500 meters
    B)200 meters
    C)1000 meters
    D)2000 meters
    Answer: 1000 meters
  • Q. Guard of suburban train shall sign on ________ minutes before the actual departure of the train.
    A)40
    B)45
    C)30
    D)15
    Answer: 15