- Q. Goods warning board will be provided from FSS in BG at
A)560 meters
B)1400 meters
C)1000 meters
D)None of these
Answer: 1400 meters
- Q. Notice station notified in?
A)SR
B)SWR
C)GR
D)Working Time Table
Answer: Working Time Table
- Q. To send the assisting engine into obstructed block section T/A 602 authority is issued ________ and the speed of engine shall be ________.
A)15/10 km/h
B)25/10 km/h
C)20/10 km/h
D)None of these
Answer: 15/10 km/h
- Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
A)30
B)20
C)25
D)15
Answer: 15
- Q. In which year palace on wheels train inaugurated?
A)1982
B)1988
C)1978
D)1965
Answer: 1982
- Q. Interchange point of Central and Western railway is ________.
A)Both
B)Dadar
C)Jalgaon
D)None of these
Answer: Both
- Q. Which hooters shall be blown in case of accident on a goods train at outside from ART HQ station?
A)Two
B)Four
C)Three
D)Any one
Answer: Three
- Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
A)20 kmph
B)15 kmph
C)10 kmph
D)None of these
Answer: 15 kmph
- Q. For Temporary diversions, the permission must be obtained from
A)CE
B)CRS
C)Railway Board
D)None of these
Answer: Railway Board
- Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?
A)Source of raw material and production centers
B)Source of raw material and export centers
C)Source of raw material and ports
D)Source of raw material and markets
Answer: Source of raw material and production centers
- Q. Accident drill is to be conducted once in ________ if no real accident occurs during this period.
A)01 month
B)04 month
C)02 month
D)03 Months
Answer: 02 month
- Q. Length of a BG ICF Coach is
A)21.337 meters
B)22.089 meters
C)21.494 meters
D)None of these
Answer: 21.337 meters
- Q. First Train started in India?
A)1853
B)1851
C)1852
D)1854
Answer: 1853
- Q. If the motorman of EMU passes the automatic stop signal at ON, he shall proceed at a speed of 15/8 km/h and stop the train before ________ meters of the obstruction on the track.
A)80
B)70
C)75
D)85
Answer: 75
- Q. What is the means of EA in WTT?
A)Extra recovery time
B)Extra allowances
C)Engineering allowances
D)None of these
Answer: Engineering allowances
- Q. How many Class of Accident?
A)20
B)14
C)16
D)None of these
Answer: 16
- Q. Hand shunting is performed at speed not exceeding
A)05 kmph
B)10 kmph
C)08 kmph
D)None of these
Answer: 05 kmph
- Q. When baking a train from one line to the other line, it is necessary to present the train guard.
A)Break van
B)Point
C)Station
D)Any Place
Answer: Break van
- Q. In which of the following cities is the National Rail Museum located ?
A)Hyderabad
B)Mumbai
C)New Delhi
D)Chennai
Answer: New Delhi
- Q. Flasher light is of ________ colour.
A)Green
B)Red
C)Amber
D)None of these
Answer: Amber