Q. Whenever new signal is put into use, signal sighting committee submits its joint report on

Correct Answer

T/102B

More Questions on Indian Railway

  • Q. Speed of train when whistle becomes defective is ________ km/h.
    A)45/8
    B)30/8
    C)25/8
    D)40/8
    Answer: 25/8
  • Q. Normal condition of automatic stop signal is ________.
    A)Yellow
    B)Red
    C)Green
    D)None of these
    Answer: Green
  • Q. To protect his train, Guard must first proceed ________ meters in rear and place one detonator in BG in absolute block system.
    A)1200
    B)600
    C)800
    D)None of these
    Answer: 600
  • Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
    A)Walkie-Talkie
    B)Walkie
    C)VHF
    D)None of these
    Answer: Walkie-Talkie
  • Q. S mark on the EMU coach means ________.
    A)Scroll
    B)Release
    C)Spare
    D)None of these
    Answer: Spare
  • Q. Not more than ________ officials can travel in the locomotive unless authorised by operating official.
    A)3
    B)2
    C)4
    D)6
    Answer: 3
  • Q. During TFC on single line, when line clear is obtained for more than one train, trains are run at an interval of ________ minutes.
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?
    A)Source of raw material and production centers
    B)Source of raw material and export centers
    C)Source of raw material and ports
    D)Source of raw material and markets
    Answer: Source of raw material and production centers
  • Q. Cotton in closed wagon shall be attached ________ position from engine on a goods train.
    A)Third
    B)First
    C)Second
    D)None of these
    Answer: Second
  • Q. During accident or Engine failure in the mid section the report sent to SM must be signed by ________.
    A)Both
    B)GDR
    C)TDR
    D)None of these
    Answer: GDR
  • Q. How many stations to be redeveloped through PPP?
    A)350
    B)100
    C)200
    D)600
    Answer: 600
  • Q. Sounding of 4 hooters means ________.
    A)ART & MRV requirement at home Station
    B)ART
    C)MRV
    D)None of these
    Answer: ART & MRV requirement at home Station
  • Q. The manufacturing of steam engine in Chittranjan Locomotive Works was stopped in
    A)1972
    B)1974
    C)1961
    D)1973
    Answer: 1972
  • Q. In block section trains entered simultaneously from either direction and finally stopped before collision and distance between both the trains was 400 mtrs, which type of accident occured?
    A)Save collision
    B)Violation of block rules
    C)Passingn danger signal
    D)All of above
    Answer: All of above
  • Q. Which of the following zones administers the Matheran Hill Railway?
    A)Central Railways
    B)Konkan Railways
    C)Western Railways
    D)Southern Railways
    Answer: Central Railways
  • Q. Consider the following statements with regard to ‘Ad Hoc’ Committees of the parliament: 1)They are temporary in nature and appointed for a specific purpose 2)Railway Convention Committee is an ad hoc committee Which among the above statements is / are correct?
    A)Both 1 & 2 are correct
    B)Only 1 is correct
    C)Only 2 is correct
    D)Neither 1 nor 2 is correct
    Answer: Both 1 & 2 are correct
  • Q. On the electrified area in sections at 25 KV A.C., when the gross clearance is between 390 MM and 340 MM the speed must be
    A)8 kmph
    B)10 kmph
    C)15 kmph
    D)None of these
    Answer: 15 kmph
  • Q. Accident drill is ordered by DRM and is conducted under the supervision of ________
    A)DOM
    B)ADRM/Sr.DSO/DSO
    C)Sr.DOM
    D)None of these
    Answer: ADRM/Sr.DSO/DSO
  • Q. How many members did the railway board had?
    A)4
    B)3
    C)5
    D)8
    Answer: 4
  • Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the engine.
    A)3
    B)5
    C)2
    D)4
    Answer: 5

Leave a Comment