- Q. Written authority received to pass approach stop signal.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 15 kmph
- Q. Adequate distance kept beyond the starter signal to take off the home signal is called as ________.
A)Block instrument
B)Signal over lap
C)Over lap
D)None of these
Answer: Signal over lap
- Q. The time limit for starting BD special during day is ________.
A)30 meters
B)20 meters
C)15 meters
D)40 meters
Answer: 30 meters
- Q. A lorry shall be protected by banner flags and detonators if it remains stationary within the station yard for more than
A)20 meters
B)15 meters
C)10 meters
D)None of these
Answer: 15 meters
- Q. Which hooters shall be blown in case of accident on a goods train at outside from ART HQ station?
A)Two
B)Four
C)Three
D)Any one
Answer: Three
- Q. During TFC in single line section what authority to proceed will be served to driver of Dn train during return.
A)TH-602
B)T/A-602
C)TG-602
D)TB-602
Answer: TH-602
- Q. WTT will be issued ________.
A)Three in Year
B)Once in a Year
C)Two in a Year
D)None of these
Answer: Once in a Year
- Q. Yearly goods stock census is taken on ________.
A)30st November
B)31st December
C)31st October
D)31st March
Answer: 30st November
- Q. Between which of the destinations the first Indian train was started?
A)From Mumbai to Surat
B)From Kolkata to Delhi
C)From Mumbai to Thane
D)From Mumbai to Madras
Answer: From Mumbai to Thane
- Q. IBP is a Station in which class?
A)C-Class
B)A-Class
C)B-Class
D)D-Class
Answer: C-Class
- Q. Only ________ persons other than the motor man/guard are authorized to travel in the cab in EMU
A)6
B)2
C)4
D)8
Answer: 2
- Q. Shunting restrictions of station is written in ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: SWR
- Q. ________ tail board will be used is EMU train.
A)Turn Over & Turn Flow
B)Turnover
C)Turn Flow
D)None of these
Answer: Turnover
- Q. At which of the following places Diesel Component Works is established?
A)Perambur
B)Jamshedpur
C)Patiala
D)Varanasi
Answer: Patiala
- Q. Where there is no TSR, station master shall make entries in ________.
A)Mid section
B)Station diary
C)Diary
D)None of these
Answer: Station diary
- Q. Which Zone is the largest in Indian Railways?
A)Eastern Railway
B)Central Railway
C)Northern Railway
D)Western Railway
Answer: Eastern Railway
- Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A)30
B)20
C)10
D)None of these
Answer: 30
- Q. SCOR maintains ________ register when serious accident occurs.
A)Chronological
B)Logical
C)Un-logical
D)None of these
Answer: Chronological
- Q. During shunting, outer, home and ________ signals are not taken off.
A)Both
B)Last stop signal
C)First stop signal
D)None of these
Answer: First stop signal
- Q. While receiving train on an obstructed line and danger signal must be shown to LP at
A)40 meters from obstruction
B)45 meters
C)30 meters
D)None of these
Answer: 45 meters