More Questions on Indian Railway
- Q. Train is to be passed through loop line.
A)30 kmph
B)15 kmph
C)25 kmph
D)Normal speed
Answer: 15 kmph
- Q. It is a Python Rake.
A)15 kmph
B)60 kmph
C)25 kmph
D)Normal speed
Answer: 60 kmph
- Q. When an incomplete parted portion arrives at a station the Driver to stop his train at ________ and give one long one short one long one short whistle.
A)Both
B)Outer Most facing Points
C)Inner Most facing signal
D)None of these
Answer: Outer Most facing Points
- Q. On double line, when a running line is blocked by stabled load , the point to be set against are
A)Advance point
B)Either side points
C)Rear points
D)None of these
Answer: Rear points
- Q. When VP vehicles are attached in a goods train the maximum number of VPvehicle in one group is
A)8
B)10
C)6
D)None of these
Answer: 6
- Q. Motor coach is a ________ coach.
A)Self Minor
B)Self Propelled
C)Self System
D)None of these
Answer: Self Propelled
- Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
A)30
B)20
C)25
D)15
Answer: 15
- Q. When was the Jammu City appeared on the map of Indian Railway?
A)1967
B)1956
C)1963
D)1965
Answer: 1965
- Q. Caution and Termination indication Boards will be fixed from the bridge or vulnerable places at
A)1000 meters
B)400 meters
C)600 meters
D)None of these
Answer: 600 meters
- Q. On which speed BG engine shall be run while speedometer is defective during run?
A)25 kmph
B)50 kmph
C)40 kmph
D)Maximum 10% less of MPS
Answer: Maximum 10% less of MPS
- Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
A)T/407
B)T/409
C)T/408
D)T/406
Answer: T/409
- Q. If the driver does not receive all right signal from the guard, he must call by giving.
A)On long
B)Two sharp whistles
C)One long one short
D)None of these
Answer: Two sharp whistles
- Q. In Automatic Block system , in BG when there is obstruction in the adjacent line, driver to protect the adjacent line first by placing one detonator at not less than ________ , metres.
A)1200
B)600
C)800
D)None of these
Answer: 600
- Q. Section controller is responsible for ________ on a section of a railway provided with the system of speech communication.
A)Station Traffic
B)Movement of traffic
C)None of Traffic
D)None of these
Answer: Movement of traffic
- Q. In which country was flange wheel invented?
A)Europe
B)Germany
C)Japan
D)Russia
Answer: Germany
- Q. Which of the following ran the first train from Bori Bunder to Thane in 1853?
A)Central India Railway
B)Bombay Baroda Railway
C)The Scindia Railway
D)Great Indian Peninsula Railway
Answer: Great Indian Peninsula Railway
- Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.
A)25
B)20
C)15
D)None of these
Answer: 25
- Q. In automatic block system SL, the signal that can be dispensed with is
A)Automatic Stop signal
B)Home
C)Starter
D)None of these
Answer: Automatic Stop signal
- Q. P marker is provided for a
A)Semaphore warner
B)Colour light distance
C)Semaphore distant
D)None of these
Answer: Colour light distance
- Q. Speed of train when whistle becomes defective is ________ km/h.
A)45/8
B)30/8
C)25/8
D)40/8
Answer: 25/8