Q. Which aspect of signal on Automatic section while showing “A” & “AG” both light-up?

Correct Answer

Defective signal

More Questions on Indian Railway

  • Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: 2 Only
  • Q. WTT will be issued ________.
    A)Three in Year
    B)Once in a Year
    C)Two in a Year
    D)None of these
    Answer: Once in a Year
  • Q. Consider the following steps in Budget Procedure in India: 1)The demands for grants of various ministries and departments including railways are considered by the concerned standing committees 2)Broad contours of the budget and the principles and policies underlying it are discussed. 3)A cut motion is moved in the Lok Sabha 4)Budget is presented in the House. Which among the following is the correct sequence of the above steps?
    A)4 2 1 3
    B)1 2 3 4
    C)1 2 4 3
    D)3 1 4 2
    Answer: 4 2 1 3
  • Q. When a passenger carrying train is working with engine running tender foremost the speed is ________ if cow catcher and head light is not provided.
    A)15 kmph
    B)25 kmph
    C)20 kmph
    D)None of these
    Answer: 20 kmph
  • Q. The number of line clear ticket in down direction is ________.
    A)T/A 1425
    B)T/C 1425
    C)T/D 1426
    D)T/D 1425
    Answer: T/D 1425
  • Q. In automatic block area SL. The LSS shall not be taken of unless the line is clear upto
    A)Automatic stop signal+180 Meters
    B)next automatic stop signal
    C)Automatic stop signal+120 Meters
    D)None of these
    Answer: next automatic stop signal
  • Q. Speed of a passenger train passing through loop line on a station equipped with STD III interlocking?
    A)75 kmph
    B)140 kmph
    C)160 kmph
    D)15 kmph
    Answer: 15 kmph
  • Q. Which train in India has the longest route length?
    A)Kanyakumari - Dibrugarh Vivek Express
    B)Howrah - Jammu Tawi Himgiri Express
    C)Kanyakumari - Jammu Tawi Himsagar Express
    D)Guwahati - Tiruvananthapuram Express
    Answer: Kanyakumari - Dibrugarh Vivek Express
  • Q. In case of vehicles escaping on wrong line, ________ bell code is given on block Instrument to inform the station in advance.
    A)0000-000
    B)000000-0000
    C)00000-0
    D)0000-0000
    Answer: 000000-0000
  • Q. The extended life of Detonator is ________ Years.
    A)4
    B)5
    C)6
    D)10
    Answer: 10
  • Q. Normally the train with hot axle is admitted on ________.
    A)Main Line
    B)Loop Line
    C)Siding Line
    D)None of these
    Answer: Main Line
  • Q. In one train only system, information of lost of metal token is given to ________.
    A)DRM
    B)DOM
    C)AOM
    D)None of these
    Answer: DRM
  • Q. Read the Following Railway Headquarters and Identify which is False?
    A)South Railway - Chennai
    B)South - Central Railway - Secunderabad
    C)Central railway - Bhopal
    D)North Railway - New Delhi
    Answer: Central railway - Bhopal
  • Q. The speed of lorry shall not exceed
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 10 kmph
  • Q. In double Distant signalling, outermost signal post is painted with ________.
    A)Green & Yellow
    B)White & yellow
    C)Black & Yellow
    D)None of these
    Answer: Black & Yellow
  • Q. How much block overlap is required at the station equipped with MACLS?
    A)120 meters
    B)400 meters
    C)180 meters
    D)Zero meters
    Answer: 180 meters
  • Q. Indian Railway will publish new Magazine in all regional language. The name of that Magazine is:
    A)Rail Prakashan
    B)Rail Line
    C)Big Thing, Big Way
    D)Rail Bandhu
    Answer: Rail Bandhu
  • Q. What is the position of the Indian Railway under the zonal system?
    A)Third
    B)First
    C)Second
    D)Forth
    Answer: Second
  • Q. The speed of Motor Trolly over points and crossings is
    A)15 kmph
    B)10 kmph
    C)8 kmph
    D)None of these
    Answer: 15 kmph
  • Q. Block overlap in two aspect signalling system is ________ meters.
    A)400
    B)500
    C)600
    D)600
    Answer: 400

Leave a Comment