More Questions on Indian Railway
- Q. When a stream engine is running tender foremost the speed shall not exceed ________.
A)30 kmph
B)40 kmph
C)20 kmph
D)None of these
Answer: 40 kmph
- Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
A)30 kmph
B)Normal speed
C)15 kmph
D)60 kmph
Answer: 60 kmph
- Q. At the enroute, CC rake goods train must have ________ % of brake power.
A)90
B)75
C)50
D)100
Answer: 90
- Q. For imposition of line block application must be sent ________ Hours in advance.
A)18
B)24
C)12
D)22
Answer: 24
- Q. In which year Research, Design and Standard organization was established?
A)1959
B)1954
C)1957
D)1967
Answer: 1957
- Q. What is the position of the Indian Railway under one management are also credited with having a multi gauge and multi traction system?
A)Third
B)First
C)Second
D)Fourth
Answer: Second
- Q. Which authority shall be received from station in rear to pass defective home signal?
A)T-409
B)T-369(3b)
C)T-369(1)
D)Simple memo
Answer: T-369(1)
- Q. During TFC in double line which authority to serve the driver for train operation?
A)TC-602
B)TC-1425
C)TA-602
D)TD-1425
Answer: TC-602
- Q. Number of train signal register of single line is ________.
A)T/166 B
B)T/136 A
C)T/137 B
D)T/135
Answer: T/137 B
- Q. To apply for Line block, the notice shall be given to DRM not less than
A)12 hours
B)48 hours
C)24 hours
D)None of these
Answer: 24 hours
- Q. Approved special instructions are issued by ________.
A)PCOM
B)CRS
C)MT
D)None of these
Answer: CRS
- Q. Competency certificate of the gateman of interlocked engineering gate is issued by
A)SSE/C & W
B)SSE/P.way
C)SSE/Sig.
D)None of these
Answer: SSE/P.way
- Q. Departmental enquiry must be ordered by ________.
A)DRM
B)Sr. DPO
C)COM
D)Sr. DOM
Answer: DRM
- Q. Last stop signal means the ________ of a station controlling the entry of trains into the next block section.
A)Call-on Signal
B)Fixed stop signal
C)Hand Signal
D)None of these
Answer: Fixed stop signal
- Q. On which place the Guard should be presented at the time of train backed from one running line to another line?
A)In Break van
B)At Facing point
C)On Engine
D)At Anyplace
Answer: In Break van
- Q. If the G marker Gate signal is at ON, Loco pilot may pass it after stopping for 01 minute by day and ________ minutes by night.
A)8
B)5
C)2
D)4
Answer: 2
- Q. Diesel locomotives are built in?
A)Perambur
B)Banglore
C)Varanasi
D)Hubli
Answer: Varanasi
- Q. Consider the following statements about the Bio Toilet Project in Indian Railways: 1)The bio – toilets are joint initiative of Indian Railways and DRDO 2)The human excreta in the bio – toilets is treated through anaerobic digestion process 3)The bio toilet reduces the solid human waste to biogas and pure water Which of the above statements is/are correct?
A)2 & 3 Only
B)1 & 3 Only
C)2 Only
D)1, 2 & 3
Answer: 1, 2 & 3
- Q. What is the position of the Indian Railway under the zonal system?
A)Third
B)First
C)Second
D)Forth
Answer: Second
- Q. If the patrol man does not turn up within ________ minutes, he will be treated as delayed.
A)15
B)10
C)20
D)40
Answer: 15
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State