More Questions on Indian Railway
- Q. Isolation shall be provided at an interlocked station when the speed is
A)Above 50 kmph
B)50 kmph
C)75 kmph
D)None of these
Answer: Above 50 kmph
- Q. Length of a standard BG loop line is
A)720 meters
B)686 meters
C)670 meters
D)None of these
Answer: 686 meters
- Q. Consider the following statements about the proposed Rail Development Authority: 1)It will act within the parameters of the Railway Act, 1989 2)The authority will consist of four members 3)It will regulate the sector opened to the private sector for investment Which of the above statements is/are correct?
A)2 & 3 Only
B)1 & 2 Only
C)3 Only
D)1, 2 & 3
Answer: 1, 2 & 3
- Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
A)Both
B)Temporary Working Order.
C)Permanent working order.
D)None of these
Answer: Temporary Working Order.
- Q. Cotton in closed wagon shall be attached ________ position from engine on a goods train.
A)Third
B)First
C)Second
D)None of these
Answer: Second
- Q. Diesel locomotives are built in?
A)Perambur
B)Banglore
C)Varanasi
D)Hubli
Answer: Varanasi
- Q. Notice station notified in?
A)SR
B)SWR
C)GR
D)Working Time Table
Answer: Working Time Table
- Q. When ISMD attached train is allowed to run through on PF line the speed must be
A)10 kmph
B)5 kmph
C)8 kmph
D)None of these
Answer: 5 kmph
- Q. On which authority relief train shall be dispatched for obstructed block section?
A)On memo
B)PLCT
C)T/A602
D)None of these
Answer: T/A602
- Q. Visibility test object is placed at a distance of ________ meters from the station building.
A)180
B)108
C)100M
D)200
Answer: 180
- Q. How many systems of working in Indian Railways for train operation?
A)8
B)6
C)7
D)9
Answer: 6
- Q. Railway staff collage is situated at ________.
A)Chennai
B)Vadodara
C)Kanyakumari
D)New Delhi
Answer: Vadodara
- Q. Standard moving dimensions Load infringing (ISMD) shall be moved by
A)Work trains
B)Through train
C)Shunting trains
D)None of these
Answer: Through train
- Q. During emergency, in the absence of tail board ________ can be used with the DRM.
A)Yellow flag
B)GREAN FLAG
C)RED FLAG
D)None of these
Answer: RED FLAG
- Q. Normally material train will work during ________.
A)Both
B)Day
C)Night
D)None of these
Answer: Day
- Q. Target time for dispatch of ARME from single exit siding at night is ________ minutes.
A)8
B)10
C)5
D)25
Answer: 25
- Q. What is the speed of A class ODC in BG?
A)40 kmph
B)15 kmph
C)25 kmph
D)Normal speed
Answer: Normal speed
- Q. D class stations are called as ________.
A)Station Limit
B)Halt Station
C)Class station
D)None of these
Answer: Halt Station
- Q. When a portion of a train is left in a block section, ________ Must be shown on the front vehicle of the rear portion of the train during night.
A)Both
B)Red Light
C)Green Light
D)None of these
Answer: Red Light
- Q. The Maitree Express connects India with which of the following countries?
A)Bangladesh
B)Myanmar
C)Pakistan
D)Nepal
Answer: Bangladesh