More Questions on Indian Railway
- Q. On which time the watch shall be set by loco pilot with Station masters watch?
A)A & B both
B)At 8.00 Hrs
C)At 16.00 Hrs
D)At the time of on duty
Answer: At the time of on duty
- Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the brake van.
A)6.8
B)7.8
C)5.8
D)4.7
Answer: 4.7
- Q. Normally maximum gradient in station yards in BG is (at present)
A)1 in 1000
B)1 in 260
C)1 - 400
D)None of these
Answer: 1 - 400
- Q. Maximum speed of the train while unloading ballast is ________ km/h.
A)6
B)8
C)4
D)10
Answer: 8
- Q. passing through station during day when running without brakevan and tail board.
A)25 kmph
B)10 kmph
C)20 kmph
D)Normal speed
Answer: 20 kmph
- Q. What is maximum width of coaching stock in BG?
A)3250 mm
B)3050 mm
C)3200 mm
D)3300 mm
Answer: 3250 mm
- Q. The form number of authority to proceed without line clear is ________.
A)T/B1408
B)T/1408
C)T/A1408
D)None of these
Answer: T/1408
- Q. When four wheeler attached, speed of passenger train will be ________ km/h.
A)85
B)80
C)75
D)90
Answer: 75
- Q. What is the maximum speed in block section during thick & foggy weather?
A)15 kmph
B)30 kmph
C)60 kmph
D)Not to move
Answer: 60 kmph
- Q. Line clear is obtained from ________ / ________ to send the train upto IBS.
A)Counter circuit
B)Track circuit/axle counter
C)Circuit
D)None of these
Answer: Track circuit/axle counter
- Q. If the Loco Pilot stops after passing the home siGnal and sounds long short long short whistle, it means ________.
A)Received train
B)Train Divided
C)Thorugh train
D)None of these
Answer: Train Divided
- Q. Length of a standard BG loop line is
A)720 meters
B)686 meters
C)670 meters
D)None of these
Answer: 686 meters
- Q. TSL is started between those two stations at which cross over facility are available and
A)D Class/IBC
B)A Class/IBS
C)C Class/IBS
D)None of these
Answer: C Class/IBS
- Q. In which country was flange wheel invented?
A)Europe
B)Germany
C)Japan
D)Russia
Answer: Germany
- Q. In case of vehicles escaping on wrong line, ________ bell code is given on block Instrument to inform the station in advance.
A)0000-000
B)000000-0000
C)00000-0
D)0000-0000
Answer: 000000-0000
- Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A)30
B)20
C)10
D)None of these
Answer: 30
- Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
A)Both
B)Temporary Working Order.
C)Permanent working order.
D)None of these
Answer: Temporary Working Order.
- Q. Which Zone is the largest in Indian Railways?
A)Eastern Railway
B)Central Railway
C)Northern Railway
D)Western Railway
Answer: Eastern Railway
- Q. Which authority shall be issued to pass a starter signal during advanced starter single is failed and starter is interlocked with Ad. Starter at a station equipped with single line token less block?
A)Memo + Hand Signal
B)T-369(3b)
C)PLCT
D)Starter should be taken off
Answer: T-369(3b)
- Q. Which of the following committee gave recommendations on separation of Policy – making, Regulation & Operations in Indian Railways and setting up of a Railway Regulatory Authority of India (RRAI)?
A)Rajinder Sachar Committee
B)Bibek Deberoy committee
C)Rangarajan committee
D)Mihir Shah Committee
Answer: Bibek Deberoy committee