Q. When a portion of a train is left in a block section, ________ Must be shown on the front vehicle of the rear portion of the train during night.

Correct Answer

Red Light

More Questions on Indian Railway

  • Q. When a stream engine is running tender foremost the speed shall not exceed ________.
    A)30 kmph
    B)40 kmph
    C)20 kmph
    D)None of these
    Answer: 40 kmph
  • Q. If the patrol man does not turn up within ________ minutes, caution order must be issued.
    A)15
    B)10
    C)5
    D)20
    Answer: 20
  • Q. Caution order is carried forward at stations on ________ at 09:00 hours.
    A)Monday
    B)Tueday
    C)Sunday
    D)None of these
    Answer: Monday
  • Q. Flasher lights will be provided in all ________ engines working on DL and Automatic areas.
    A)Power
    B)Electrical & Diesel
    C)Diesel
    D)None of these
    Answer: Electrical & Diesel
  • Q. When was the Central Railway established?
    A)14th April 1951
    B)5th Nov 1951
    C)14th Nov 1951
    D)16th August, 1951
    Answer: 5th Nov 1951
  • Q. Kacheguda railway station has declared the India’s first Energy – Efficient ‘A1 Category’ Railway Station. It is situated in which city?
    A)Kochi
    B)Hyderabad
    C)Chennai
    D)Kolkata
    Answer: Hyderabad
  • Q. ________ tail board will be used is EMU train.
    A)Turn Over & Turn Flow
    B)Turnover
    C)Turn Flow
    D)None of these
    Answer: Turnover
  • Q. Only ________ persons other than the motor man/guard are authorized to travel in the cab in EMU
    A)6
    B)2
    C)4
    D)8
    Answer: 2
  • Q. Number of train signal register of double line is ________.
    A)T/66 B
    B)T/66 A
    C)T/66 C
    D)T/66
    Answer: T/66 B
  • Q. Where is the extreme north of India a railway station?
    A)Pathankot
    B)Jammu Tawi
    C)Baramulla
    D)Guwahati
    Answer: Baramulla
  • Q. What will be the speed of second train running on T/C 602?
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: Normal speed
  • Q. Distant signal shows ________ light in normal condition in double distant signalling is provided.
    A)Three yellow
    B)One Yellow
    C)Two yellow
    D)Four yellow
    Answer: Two yellow
  • Q. All the authorities related to TSL working are examined by TI and its report is submitted to DRM within ________ days of resumption of normal working.
    A)10
    B)7
    C)9
    D)15
    Answer: 7
  • Q. Weight required minimum for testing IC Apparatus is the
    A)7 - 10 kg
    B)6 kg
    C)10 kg
    D)None of these
    Answer: 7 - 10 kg
  • Q. When an accident occurs the GDR must their report to next SM in form.
    A)ACC5
    B)ACC1
    C)ACC2
    D)ACC3
    Answer: ACC3
  • Q. Notice station caution order No. is ________
    A)T/C-409
    B)T/409
    C)T/B-409
    D)None of these
    Answer: T/409
  • Q. What is shunting order number?
    A)T-806
    B)T-609
    C)T/A-602
    D)T-409
    Answer: T-806
  • Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
    A)30
    B)20
    C)10
    D)None of these
    Answer: 30
  • Q. The turning out time of an MRV Spl. When in is kept in one exit siding is ________ minutes.
    A)20
    B)25
    C)15
    D)None of these
    Answer: 25
  • Q. D class station board is placed ________ meters from the end of the platform.
    A)600
    B)400
    C)500
    D)800
    Answer: 500