- Q. If leakage in LPG Tank, how long area is prohibited to carry to burn the burning fire ?
A)100 meters
B)45 meters
C)50 meters
D)1000 meters
Answer: 45 meters
- Q. Competency certificate of the gateman of interlocked engineering gate is signed by
A)Both
B)SSE/P.way
C)SSE/Sig.
D)None of these
Answer: Both
- Q. Where is the Indian Railways Institute of Mechanical and Electrical Engineering institute situated?
A)Jamalpur
B)Nasik
C)Baroda
D)Pune
Answer: Jamalpur
- Q. In automatic block system SL, the signal that can be dispensed with is
A)Automatic Stop signal
B)Home
C)Starter
D)None of these
Answer: Automatic Stop signal
- Q. Station Working Rules of Non-interlocked station is signed by ________.
A)AOM & ADEN
B)DOM & DEN
C)Sr. DOM & Sr. DEN
D)None of these
Answer: Sr. DOM & Sr. DEN
- Q. During thick & foggy weather, line must be clear upto ________ for granting line clear at a B’ class station in TALQ signalling system on Double line.
A)Shunt signal
B)Calling-on Signal
C)Home Signal
D)None of these
Answer: Home Signal
- Q. What is the target time for ART during night hours?
A)60 minutes
B)30 minutes
C)45 minutes
D)20 minutes
Answer: 45 minutes
- Q. ________ is measured with the help of anemometer.
A)Both
B)Wind
C)Velocity
D)None of these
Answer: Both
- Q. To attach the 12 coach EMU rake, ________ units are to be attached.
A)8
B)5
C)6
D)4
Answer: 4
- Q. Minimum distance apart of refuges in Tunnels in BG is (at present)
A)200 meters
B)100 meters
C)150 meters
D)None of these
Answer: 100 meters
- Q. When water level is just above top of rail speed of electric locomotive shall apply ?
A)15 kmph
B)5 kmph
C)10 kmph
D)20 kmph
Answer: 10 kmph
- Q. The turning out time of an MRV Spl. When in is kept in one exit siding is ________ minutes.
A)20
B)25
C)15
D)None of these
Answer: 25
- Q. Minimum depth of space for wheel flange from rail level in BG is
A)3"
B)2"
C)1 (1/2)"
D)None of these
Answer: 1 (1/2)"
- Q. The time taken for formation of a goods train in flat yard is
A)3 kmph
B)2 hrs
C)1 hr
D)None of these
Answer: 2 hrs
- Q. The speed of the train over neutral section shall not be less than ________ kmph
A)40
B)20
C)30
D)None of these
Answer: 30
- Q. Suburban Working time table is signed by ________ , COM and CPTM.
A)DRM
B)DOM
C)AOM
D)None of these
Answer: DRM
- Q. During shunting, outer, home and ________ signals are not taken off.
A)Both
B)Last stop signal
C)First stop signal
D)None of these
Answer: First stop signal
- Q. In Material train, vehicles shall not be detached on gradient.
A)1-400
B)ST 1-260
C)1-100 or steeper
D)None of these
Answer: 1-100 or steeper
- Q. Train is to be started from non signalled line
A)T/D 602
B)T-511
C)T-512
D)Simple memo
Answer: T-511
- Q. Traffic gates are those located between ________.
A)First signal
B)Outermost stop signal
C)Stop signal
D)None of these
Answer: Outermost stop signal