Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?

Correct Answer

30 meters

More Questions on Indian Railway

  • Q. Hand shunting is performed at speed not exceeding
    A)05 kmph
    B)10 kmph
    C)08 kmph
    D)None of these
    Answer: 05 kmph
  • Q. D class stations are called as ________.
    A)Station Limit
    B)Halt Station
    C)Class station
    D)None of these
    Answer: Halt Station
  • Q. Shunt signal is a ________ signal.
    A)Both
    B)Subsidiary
    C)Ordinary
    D)None of these
    Answer: Subsidiary
  • Q. How many members did the railway board had?
    A)4
    B)3
    C)5
    D)8
    Answer: 4
  • Q. Is general manager responsible for?
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board
  • Q. What is shunting order number?
    A)T-806
    B)T-609
    C)T/A-602
    D)T-409
    Answer: T-806
  • Q. Over which of the following rivers is the world’s highest railway bridge in Kashmir being constructed?
    A)Sutlej
    B)Chenab
    C)Jhelum
    D)Indus
    Answer: Chenab
  • Q. In case of ACP Guard shall proceed towards the front from ________ side.
    A)Back
    B)Left
    C)Right
    D)Noe of these
    Answer: Left
  • Q. Continuity test is to be done.
    A)_____00
    B)0
    C)0
    D)00------
    Answer: 00------
  • Q. If the SE (P.way) is not with the train, maximum speed at the spot of lurch shall be ________ km/h.
    A)10
    B)15
    C)20
    D)25
    Answer: 10
  • Q. Where the caution indicator placed in BG if the engineering work is more than one days and train not to be require to stop at site?
    A)800 Meter
    B)1200 Meter
    C)1000 Meter
    D)500 Meter
    Answer: 800 Meter
  • Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.
    A)15 km
    B)8 km
    C)10 km
    D)25 km
    Answer: 25 km
  • Q. When was the Jammu City appeared on the map of Indian Railway?
    A)1967
    B)1956
    C)1963
    D)1965
    Answer: 1965
  • Q. BSLB determines the limits of Station section and ________.
    A)Station Limit
    B)Block Section
    C)Station Section
    D)None of these
    Answer: Block Section
  • Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
    A)Block sectiond
    B)Next whole block section
    C)Back whole block section
    D)None of these
    Answer: Next whole block section
  • Q. Colour of the semaphore shunt signal is ________.
    A)Green
    B)Red
    C)Yellow
    D)None of these
    Answer: Red
  • Q. Which authority shall be issued to pass a starter signal during advanced starter single is failed and starter is interlocked with Ad. Starter at a station equipped with single line token less block?
    A)Memo + Hand Signal
    B)T-369(3b)
    C)PLCT
    D)Starter should be taken off
    Answer: T-369(3b)
  • Q. Consider the following statements about Operating Ratio in Indian Railways: 1)The higher the operating ratio of Indian Railways the better is the condition of Indian Railways. 2)Operating ratio of Indian Railways is high on account of social service obligation imposed in Budget. Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: 2 Only
  • Q. Danger zone in 25 KV AC traction is ________ meters from OHE.
    A)3
    B)1
    C)2
    D)4
    Answer: 2
  • Q. Weight required minimum for testing IC Apparatus is the
    A)7 - 10 kg
    B)6 kg
    C)10 kg
    D)None of these
    Answer: 7 - 10 kg

Leave a Comment