- Q. Block instrument and Advanced starter being failed after line clear?
A)T-369(3B) with P. NO. of line clear
B)T/C 1425
C)T/D 602 + T-511
D)T/D 1425
Answer: T-369(3B) with P. NO. of line clear
- Q. In automatic block system SL, the signal that can be dispensed with is
A)Automatic Stop signal
B)Home
C)Starter
D)None of these
Answer: Automatic Stop signal
- Q. While receiving train on an obstructed line and danger signal must be shown to LP at
A)40 meters from obstruction
B)45 meters
C)30 meters
D)None of these
Answer: 45 meters
- Q. The Mughalsarai junction has recently renamed as Deen Dayal Upadhyaya railway station. It is located in which state?
A)Uttarakhand
B)Bihar
C)Uttar Pradesh
D)Delhi
Answer: Uttar Pradesh
- Q. Load infringing standard moving dimensions (ISMD) shall be moved by
A)Work trains
B)Through train
C)Shunting trains
D)None of these
Answer: Through train
- Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?
A)Source of raw material and production centers
B)Source of raw material and export centers
C)Source of raw material and ports
D)Source of raw material and markets
Answer: Source of raw material and production centers
- Q. Cycle trollies shall be treated as ________.
A)Motor Trolley
B)Push Trollies
C)Trolley
D)None of these
Answer: Push Trollies
- Q. Any person aggrieved by a decision if labour commissioner may prefer an appeal to the central government within ________ days from the Regional Labour Commissioner
A)30
B)10
C)20
D)None of these
Answer: 30
- Q. Loco Pilot shall sound ________ whistle if SM do not exchange hand signals.
A)One short
B)Two short
C)Three short
D)Noen of these
Answer: Two short
- Q. In case of train parting ________ bell code is given on block instrument.
A)000000-000
B)00000-0
C)000000-0
D)0000-00
Answer: 000000-000
- Q. What is the means of EA in WTT?
A)Extra recovery time
B)Extra allowances
C)Engineering allowances
D)None of these
Answer: Engineering allowances
- Q. When the platform level is ________ MM and more second arriving train shall not be received and berthed on non platform line directly.
A)650
B)700
C)725
D)760
Answer: 760
- Q. If the Loco Pilot stops after passing the home siGnal and sounds long short long short whistle, it means ________.
A)Received train
B)Train Divided
C)Thorugh train
D)None of these
Answer: Train Divided
- Q. In automatic block system SL, the minimum equipment of signal shall be
A)Home, Starter, Advance Starter
B)Home, Starter
C)Distance Home Starter
D)None of these
Answer: Home, Starter
- Q. General Manger is responsible for
A)Both railway Board and Railway Ministry
B)Railway Board
C)Railway Ministry
D)None of these
Answer: Railway Board
- Q. When a crane is attached to a goods train with jib trailing the speed in BG is ________.
A)25 kmph
B)50 kmph
C)40 kmph
D)None of these
Answer: 40 kmph
- Q. What will be the maximum speed of train passing through loop line of a station name suffixed by “II” in working time table.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 15 kmph
- Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
A)Both 1 & 2
B)1 Only
C)2 Only
D)Neither 1 nor 2
Answer: 2 Only
- Q. The time limit for starting BD special during day is ________.
A)30 meters
B)20 meters
C)15 meters
D)40 meters
Answer: 30 meters
- Q. The use of block instrument shall be governed by special instructions to be issued with the prior approval of
A)CSO
B)Railway Board
C)CRS
D)None of these
Answer: CRS