Q. What is the normal aspect of an Automatic stop signal on double line Automatic section?

Correct Answer

GREEN

More Questions on Indian Railway

  • Q. By whom General Rule is prepared?
    A)PCOM
    B)Railway Board
    C)Zonal Railway
    D)GM
    Answer: Railway Board
  • Q. Block competency certificate is given in the prescribed form ________.
    A)T/115A
    B)T/115B
    C)T/115C
    D)T/115D
    Answer: T/115B
  • Q. Shunting restrictions of station is written in ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: SWR
  • Q. Distance between outer and home signals on a single line is ________ meters when there is advanced starter or SLB in the opposite direction.
    A)540
    B)900
    C)580
    D)570
    Answer: 580
  • Q. In automatic block system SL, the minimum equipment of signal shall be
    A)Home, Starter, Advance Starter
    B)Home, Starter
    C)Distance Home Starter
    D)None of these
    Answer: Home, Starter
  • Q. High flood level mark shall be painted in
    A)Blue
    B)Red
    C)White
    D)None of these
    Answer: Red
  • Q. General Manger is responsible for
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board
  • Q. IBP is a Station in which class?
    A)C-Class
    B)A-Class
    C)B-Class
    D)D-Class
    Answer: C-Class
  • Q. Motorman of EMU shall give ________ bell code while passing A marker lit gate signal in ON position.
    A)0-00
    B)00-00
    C)000-000
    D)None of these
    Answer: 00-00
  • Q. Capacity of a slip siding is ________
    A)06 or 07 wagon
    B)03 or 04 wagon
    C)04 or 05 wagon
    D)None of these
    Answer: 03 or 04 wagon
  • Q. When was the new Harbour rail line inaugurated?
    A)1931
    B)1925
    C)1928
    D)1933
    Answer: 1925
  • Q. Speed of a passenger train passing through loop line on a station equipped with STD III interlocking?
    A)75 kmph
    B)140 kmph
    C)160 kmph
    D)15 kmph
    Answer: 15 kmph
  • Q. Maximum permissible speed is fixed by ________.
    A)MT
    B)CRS
    C)GM
    D)None of these
    Answer: CRS
  • Q. The turning out time off BD SPL. During day is ________ minutes
    A)50
    B)30
    C)20
    D)None of these
    Answer: 30
  • Q. Matheran Hill Railway is a narrow gauge heritage railway located in which state?
    A)Maharashtra
    B)Tamil Nadu
    C)Himachal Pradesh
    D)Meghalaya
    Answer: Maharashtra
  • Q. Maximum speed of the train while unloading ballast is ________ km/h.
    A)6
    B)8
    C)4
    D)10
    Answer: 8
  • Q. The manufacturing of steam engine in Chittranjan Locomotive Works was stopped in
    A)1972
    B)1974
    C)1961
    D)1973
    Answer: 1972
  • Q. When was the North – Eastern frontier Railway (NEFR) established?
    A)2nd Jan, 1956
    B)15th Jan, 1958
    C)15th Jan, 1955
    D)14th April, 1952
    Answer: 15th Jan, 1958
  • Q. When the rail failure is rectified by the train can pass at speed
    A)30 kmph
    B)20 kmph
    C)25 kmph
    D)None of these
    Answer: 30 kmph
  • Q. What will be the speed of a train running through from station without brake van provoded with Tail lamp?
    A)15 kmph
    B)20 kmph
    C)Stop & Start
    D)Normal speed
    Answer: Normal speed