- Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
A)25/10 kmph
B)15/8 kmph
C)25/8 kmph
D)25/12 kmph
Answer: 25/8 kmph
- Q. All the authorities related to TSL working are examined by TI and its report is submitted to DRM within ________ days of resumption of normal working.
A)10
B)7
C)9
D)15
Answer: 7
- Q. During TFC on single line, when line clear is obtained for more than one train, trains are run at an interval of ________ minutes.
A)35
B)20
C)25
D)30
Answer: 30
- Q. The time limit for starting BD special during day is ________.
A)30 meters
B)20 meters
C)15 meters
D)40 meters
Answer: 30 meters
- Q. Distance between two automatic signals is called as ________.
A)Signalling Section
B)Block section
C)Mid Section
D)None of these
Answer: Signalling Section
- Q. Impact speed of shunting of one box wagon is ________ km/h.
A)6
B)2
C)5
D)8
Answer: 5
- Q. In Automatic areas when there are no signals and communication, the speed of the train is ________ kmph while working on T/B 912 during day.
A)15
B)25
C)20
D)10
Answer: 25
- Q. Written authority received to pass approach stop signal.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 15 kmph
- Q. Guard’s assistance is required by LP.
A)0
B)0
C)0
D)____
Answer: 0
- Q. If the train passes through without headlight, SM shall give ________ bell code and advise the reason.
A)0000-0
B)000000-0
C)00000-0
D)0000-00
Answer: 000000-0
- Q. Block overlap in two aspect signalling system is ________ meters.
A)400
B)500
C)600
D)600
Answer: 400
- Q. The maximum speed of the assistance train to be sent on T/A 602
A)30 kmph
B)10 kmph
C)15 kmph
D)40 kmph
Answer: 15 kmph
- Q. Which research arm of Indian Railways has launched “New Online Vendor Registration System”?
A)National Academy of Indian Railways
B)Indian Railway Institute of Signal Engineering and Telecommunication
C)Research Designs and Standards Organisation
D)Indian Railway Service of Electrical Engineers
Answer: Research Designs and Standards Organisation
- Q. ISMD must be attached always
A)In the middle
B)Next to Engine
C)In rear
D)None of these
Answer: Next to Engine
- Q. In case of 1 in 100 rising gradient, ________ siding is provided.
A)Slip
B)Long
C)Catch
D)None of these
Answer: Slip
- Q. General Manager is responsible for
A)Both railway Board and Railway Ministry
B)Railway Board
C)Railway Ministry
D)Finance Ministry
Answer: Railway Board
- Q. Indian Railways is constructing the country’s longest railway tunnel and tallest bridge in which of the following states?
A)Assam and Maharashtra
B)Manipur and Jammu & Kashmir
C)Jammu & Kashmir & Assam
D)Maharashtra and Jammu & Kashmir
Answer: Manipur and Jammu & Kashmir
- Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A)30
B)20
C)10
D)None of these
Answer: 30
- Q. Station Working Rules of Non-interlocked station is signed by ________.
A)AOM & ADEN
B)DOM & DEN
C)Sr. DOM & Sr. DEN
D)None of these
Answer: Sr. DOM & Sr. DEN
- Q. By whom the rear portion of train left behind in block section protected?
A)By engineearing official
B)By Guard
C)By LP
D)No need to protect the load
Answer: By Guard