More Questions on Indian Railway
- Q. Where is the Indian Railways Institute of Civil Engineering Institute situated?
A)Nasik
B)Pune
C)Chennai
D)Secunderabad
Answer: Pune
- Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
A)25/10 kmph
B)15/8 kmph
C)25/8 kmph
D)25/12 kmph
Answer: 25/8 kmph
- Q. The minimum distance from centre to centre of track in BG is
A)13 feet
B)14 feet
C)12 feet
D)None of these
Answer: 14 feet
- Q. D class station board is placed ________ meters from the end of the platform.
A)600
B)400
C)500
D)800
Answer: 500
- Q. In token territory, ________ is authority for shunting up to FSS.
A)T/806
B)Shunt Mental Token+T/806
C)Shunt Mental
D)None of these
Answer: Shunt Mental Token+T/806
- Q. Where the caution indicator placed in BG if the engineering work is more than one days and train not to be require to stop at site?
A)800 Meter
B)1200 Meter
C)1000 Meter
D)500 Meter
Answer: 800 Meter
- Q. When a train is received at a station during signal failure on signal post telephone, the speed of train is
A)8 kmph
B)15 kmph
C)25 kmph
D)None of these
Answer: 15 kmph
- Q. Competency certificate of the gateman of interlocked engineering gate is issued by
A)SSE/C & W
B)SSE/P.way
C)SSE/Sig.
D)None of these
Answer: SSE/P.way
- Q. For work of long duration, the stop indicator must be erected at not less than
A)40
B)30
C)50
D)45
Answer: 30
- Q. If a staff is absent for ________ days from duty fresh declaration must be obtained
A)20 days
B)10 days
C)15 days
D)None of these
Answer: 15 days
- Q. Suburban Working time table is signed by ________ , COM and CPTM.
A)DRM
B)DOM
C)AOM
D)None of these
Answer: DRM
- Q. When the train is stopped at FSS for more than ________ minutes, the Driver must send his assistant to station after consulting with guard.
A)10
B)5
C)7
D)None of these
Answer: 5
- Q. When the derailing switch is open, trap indicator shows red target by day and ________ Light by night.
A)Yellow
B)Red
C)Green
D)White
Answer: Red
- Q. Approved special instructions are issued by ________.
A)PCOM
B)CRS
C)MT
D)None of these
Answer: CRS
- Q. Which research arm of Indian Railways has launched “New Online Vendor Registration System”?
A)National Academy of Indian Railways
B)Indian Railway Institute of Signal Engineering and Telecommunication
C)Research Designs and Standards Organisation
D)Indian Railway Service of Electrical Engineers
Answer: Research Designs and Standards Organisation
- Q. ________ and ‘C’ class ODC shall not be crossed in the block section on double line.
A)60
B)50
C)40
D)75
Answer: 40
- Q. While shunting a complete train from one line to the other, ________ shall be present in the brakevan.
A)ALP
B)Driver
C)Guard
D)None of these
Answer: Guard
- Q. In case of defective head light, ________ bell code is given on block instrument to the station in advance.
A)000000-000
B)00000-0
C)000000-0
D)0000-00
Answer: 000000-0
- Q. Number of the caution order is ________
A)T/410
B)T/409
C)T/408
D)None of these
Answer: T/409
- Q. How many institutions do give suggestions for railways technology?
A)Three
B)One
C)Two
D)Four
Answer: Two
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State