Q. Wagon with livestock shall be attached ________ position from engine on a goods train.

Correct Answer

Second

More Questions on Indian Railway

  • Q. At the starting station, CC rake goods train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 100
  • Q. Which aspect of signal on Automatic section while showing “A” & “AG” both light-up?
    A)Gate opened and point is not set for main line
    B)Gate closed and point is set for main line
    C)Gate opened and point is set for main line
    D)Defective signal
    Answer: Defective signal
  • Q. Normally material train will work during ________.
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. Length of a BG ICF Coach is
    A)21.337 meters
    B)22.089 meters
    C)21.494 meters
    D)None of these
    Answer: 21.337 meters
  • Q. The first – ever Indian Railways Human Resources Round Table Conference has started in which city?
    A)Pune
    B)New Delhi
    C)Chennai
    D)Kochi
    Answer: New Delhi
  • Q. When a stream engine is running tender foremost the speed shall not exceed ________.
    A)30 kmph
    B)40 kmph
    C)20 kmph
    D)None of these
    Answer: 40 kmph
  • Q. The shuttle train service between Lahore and ________ railway station resumed its operation on 15 December after a gap of 22 years.
    A)Amritsar
    B)Wagah
    C)Islamabad
    D)Faridkot
    Answer: Wagah
  • Q. ________ form shall be used by GDR when a person falls out of train injured or killed.
    A)ACC4
    B)ACC2
    C)ACC3
    D)None of these
    Answer: ACC4
  • Q. Material train is a ________ train.
    A)Both
    B)Departmental
    C)Permanent
    D)None of these
    Answer: Departmental
  • Q. The largest national enterprise of India is
    A)Airways
    B)Indian Railway
    C)Indian Shipyard
    D)Waterways
    Answer: Indian Railway
  • Q. Trap indicator is provided to indicate ________.
    A)Provision Switch
    B)Indication Switch
    C)Derailing switch
    D)None of these
    Answer: Derailing switch
  • Q. The minimum distance from centre to centre of track in BG is
    A)13 feet
    B)14 feet
    C)12 feet
    D)None of these
    Answer: 14 feet
  • Q. Is general manager responsible for?
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board
  • Q. How many minimum BP pressure is require in engine to charge Goods train?
    A)5.8 kg/cm2 D. 5.00 kg/cm2
    B)4.8 kg/cm2 B. 6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
    C)6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
    D)5.00 kg/cm2
    Answer: 5.00 kg/cm2
  • Q. D class station board is placed ________ meters from the end of the platform.
    A)600
    B)400
    C)500
    D)800
    Answer: 500
  • Q. For which time Guard rough journal must be kept safe?
    A)Upto 3 Years
    B)Upto 1 Year
    C)Upto 2 Years
    D)Upto 6 Months
    Answer: Upto 3 Years
  • Q. When a running line is occupied ________ entry must be made in TSR.
    A)Yellow Ink
    B)Red Ink
    C)Green Ink
    D)None of these
    Answer: Red Ink
  • Q. Semi-automatic signal is identified by ________.
    A)Illuminated a marker
    B)Marker
    C)Semi marker
    D)None of these
    Answer: Illuminated a marker
  • Q. When a driver passing an automatic gate stop signal at ‘ON’ he must stop short of the gate of
    A)25 meters
    B)30 meters
    C)45 meters
    D)None of these
    Answer: None of these
  • Q. On the electrified area in sections at 25 KV A.C., when the gross clearance is between 390 MM and 340 MM the speed must be
    A)8 kmph
    B)10 kmph
    C)15 kmph
    D)None of these
    Answer: 15 kmph