More Questions on Indian Railway
- Q. Depot in-charge is responsible to test the detonators once in ________.
A)Year
B)Monthly
C)Weekly
D)None of these
Answer: Year
- Q. Maximum impact speed when shunting a single roller bearing fitted stock must be?
A)5 kmph
B)3 kmph
C)4 kmph
D)6 kmph
Answer: 5 kmph
- Q. Passenger warning board is placed at a distance of ________ meters from the first stop signal.
A)1500
B)1200
C)1000
D)1800
Answer: 1000
- Q. At which place the detonators shall be placed during thick & foggy weather on The Absolute block section?
A)180-10 Meters from outermost signal
B)270-10 Meters from outermost signal
C)270-10 Meters from First stop signal
D)No need to place detonators
Answer: 270-10 Meters from First stop signal
- Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?
A)27 meters
B)30 meters
C)3 meters
D)100 meters
Answer: 30 meters
- Q. To pick up the part load from the section, ________ authority is issued if the same loco pilot is proceeding.
A)T/407
B)T/409
C)T/408
D)T/406
Answer: T/409
- Q. Flasher lights will be provided in all ________ engines working on DL and Automatic areas.
A)Power
B)Electrical & Diesel
C)Diesel
D)None of these
Answer: Electrical & Diesel
- Q. Indian railways has installed Asia’s largest Solid State Interlocking (SSI) system in which state?
A)Madhya Pradesh
B)Tamil Nadu
C)West Bengal
D)Punjab
Answer: West Bengal
- Q. The speed of Motor Trolly over points and crossings is
A)15 kmph
B)10 kmph
C)8 kmph
D)None of these
Answer: 15 kmph
- Q. No passenger train shall be started from a station before the ________ time
A)Both
B)Advertised
C)Non-advertised
D)None of these
Answer: Advertised
- Q. In which of the following cities are located 3 zonal headquarters of Indian Railways?
A)New Delhi
B)Guwahati
C)Mumbai
D)Kolkata
Answer: Kolkata
- Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
A)8 kmph
B)15 kmph
C)10 kmph
D)Normal
Answer: 10 kmph
- Q. Load table is mentioned in the ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: WTT
- Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
A)LI
B)TI
C)CI
D)None of these
Answer: TI
- Q. What will be maximum speed during shunting of goods train?
A)25 kmph
B)8 kmph
C)15 kmph
D)30 kmph
Answer: 15 kmph
- Q. During prolonged failure of signals in automatic section, ________ authority is issued.
A)T/C 912
B)T/B 912
C)T/D 912
D)T/A 912
Answer: T/D 912
- Q. In the panel working for cancellation of route the number in the counter changes and white indication appears after
A)50 seconds
B)120 seconds
C)90 seconds
D)None of these
Answer: 120 seconds
- Q. Which Zone is the largest railway zone in India?
A)Eastern Railway
B)Central Railway
C)Northern Railway
D)Western Railway
Answer: Northern Railway
- Q. Slip siding protects
A)Station section
B)Station limit
C)Block section
D)None of these
Answer: Block section
- Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of BP pressure in the engine.
A)5
B)4
C)2
D)8
Answer: 5
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State