Q. Upto how many track machine shall be allowed for working within the block section?

Correct Answer

5

More Questions on Indian Railway

  • Q. The numbers of A, B and C coaches are 72, ________ and 76.
    A)71
    B)72
    C)70
    D)75
    Answer: 70
  • Q. What is the speed of second train on double line section running on T/A602?
    A)10 kmph
    B)20 kmph
    C)15 kmph
    D)8 kmph
    Answer: 8 kmph
  • Q. Written authority received to pass approach stop signal.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: 15 kmph
  • Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
    A)30 kmph
    B)Normal speed
    C)15 kmph
    D)60 kmph
    Answer: 60 kmph
  • Q. The turning out time of an MRV Spl. When in is kept in one exit siding is ________ minutes.
    A)20
    B)25
    C)15
    D)None of these
    Answer: 25
  • Q. By whom the rear portion of train left behind in block section protected?
    A)By engineearing official
    B)By Guard
    C)By LP
    D)No need to protect the load
    Answer: By Guard
  • Q. When four wheeler attached, speed of passenger train will be ________ km/h.
    A)85
    B)80
    C)75
    D)90
    Answer: 75
  • Q. Launched three Trains to improve Quality of Travel (for reserved passengers), these are:
    A)Dirubhargh, Sahayak and Humsafar
    B)Humsafar, Tejas and Uday
    C)Tejas, Antyodaya and Gatiman
    D)Sahayak,Antyodaya and Gatiman
    Answer: Humsafar, Tejas and Uday
  • Q. During total interruption of communication on signal line. The speed of LE to establish communication is ________ kmph during day and clear weather.
    A)20
    B)10
    C)15
    D)None of these
    Answer: 15
  • Q. Railway staff collage is situated at ________.
    A)Chennai
    B)Vadodara
    C)Kanyakumari
    D)New Delhi
    Answer: Vadodara
  • Q. How much block overlap is required at the station equipped with single line MACLS?
    A)120 meters
    B)400 meters
    C)180 meters
    D)Zero meters
    Answer: 180 meters
  • Q. Validity of the competency certificate of the gateman is for ________ years.
    A)9
    B)10
    C)3
    D)4
    Answer: 3
  • Q. In case of goods train without brake van, Guard is exempted from ________.
    A)Whistling
    B)ARS
    C)Tail Lamp
    D)None of these
    Answer: ARS
  • Q. In Automatic areas when there are no signals and communication, the speed of the train is ________ kmph while working on T/B 912 during day.
    A)15
    B)25
    C)20
    D)10
    Answer: 25
  • Q. Distance between outer and home signals on a single line is ________ meters when there is no advanced starter or SLB in the opposite direction.
    A)400
    B)900
    C)800
    D)700
    Answer: 400
  • Q. After proceeding 1200 meters from the obstruction Guard to place ________ detonator 10 meters apart in absolute Block system in BG
    A)3
    B)1
    C)2
    D)None of these
    Answer: 3
  • Q. The senior most ________ officer is personally responsible for ensuring and efficient handing of cranes and removal of wreckage after accident.
    A)C & W
    B)Engineering
    C)Mechanical
    D)None of these
    Answer: Mechanical
  • Q. Number of the Reminder caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 409
    D)None of these
    Answer: T/B 409
  • Q. Permissible limit of flat tyre in goods and coaching vehicles is 60mm and ________ respectively.
    A)80 mm
    B)60 mm
    C)70 mm
    D)50 mm
    Answer: 50 mm
  • Q. Is general manager responsible for?
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board