Q. Upto how many track machine shall be allowed for working within the block section?

Correct Answer

5

More Questions on Indian Railway

  • Q. Which of the gauges is used in the hilly areas?
    A)Narrow gauge
    B)Broad gauge
    C)Meter gauge
    D)Special gauge
    Answer: Narrow gauge
  • Q. What is the target time for ART during night hours?
    A)60 minutes
    B)30 minutes
    C)45 minutes
    D)20 minutes
    Answer: 45 minutes
  • Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
    A)5
    B)10
    C)20
    D)None of these
    Answer: 10
  • Q. Where is the Indian Railways Institute of Mechanical and Electrical Engineering institute situated?
    A)Jamalpur
    B)Nasik
    C)Baroda
    D)Pune
    Answer: Jamalpur
  • Q. LV board will be of ________ colour and with LV.
    A)Yellow
    B)Red
    C)Green
    D)None of these
    Answer: Red
  • Q. A platform surrounded by rail lines from all the four sides, is called
    A)Island platform
    B)Dock platform
    C)Passenger platform
    D)Goods platform
    Answer: Island platform
  • Q. Loco and traffic running staff are entitled for ________ hours rest at head quarters after running duty of 08 hours or more
    A)12 hours
    B)04 hours
    C)08 hours
    D)16 hours
    Answer: 16 hours
  • Q. First Train started in India?
    A)1853
    B)1851
    C)1852
    D)1854
    Answer: 1853
  • Q. Consider the following: Road and Railways Schools Sanitary Facilities Hospitals Which among the above are considered to be the Economic Overheads?
    A)1, 2 & 3
    B)Only 1
    C)1 & 2
    D)1, 2 , 3 & 4
    Answer: Only 1
  • Q. To start the train from a line with common starter, ________ authority is issued.
    A)T/512
    B)T/516
    C)T/517
    D)T/511
    Answer: T/512
  • Q. Signal failure advised to the driver through the station in rear will be inform
    A)T/369(3b)
    B)T/369
    C)T/370
    D)None of these
    Answer: T/369
  • Q. Each motor coach shall consist of ________ Traction motors.
    A)4
    B)2
    C)3
    D)5
    Answer: 4
  • Q. Dead engine is attached at ________ position on a Mail / Express train.
    A)Both
    B)Engine to engine
    C)Next to engine
    D)None of these
    Answer: Next to engine
  • Q. Illuminated A marker of semi-automatic signal means ________.
    A)Outer signal
    B)Working as automatic signal
    C)Semi signal
    D)None of these
    Answer: Working as automatic signal
  • Q. In double Distant signalling, outermost signal is called as ________.
    A)Stop
    B)Distant
    C)Call-on
    D)None of these
    Answer: Distant
  • Q. Stop signal is to be passed in On position.
    A)T-806
    B)T-509
    C)T-369(3b)
    D)Simple memo
    Answer: T-369(3b)
  • Q. What is the maximum speed of a goods train pushed backed from block section ?
    A)15/8 kmph
    B)15 kmph
    C)8 kmph
    D)None of these
    Answer: 8 kmph
  • Q. Between which of the destinations the first Indian train was started?
    A)From Mumbai to Surat
    B)From Kolkata to Delhi
    C)From Mumbai to Thane
    D)From Mumbai to Madras
    Answer: From Mumbai to Thane
  • Q. In which Governor – General’s reign railway lines in India were established?
    A)Lord Kenning
    B)Lord William Bentick
    C)Lord Cornwallis
    D)Lord Dalhousie
    Answer: Lord Dalhousie
  • Q. Accident drill is to be conducted once in ________ if no real accident occurs during this period.
    A)01 month
    B)04 month
    C)02 month
    D)03 Months
    Answer: 02 month

Leave a Comment