Q. The wagon containing ISMD load shall be attached.

Correct Answer

Next to Engine

More Questions on Indian Railway

  • Q. Point indicator shows ________ light when the points are set for loop line.
    A)S&T (T/350)
    B)S&T (T/351)
    C)S&T (T/352)
    D)S&T (T/315)
    Answer: S&T (T/351)
  • Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the engine.
    A)3
    B)5
    C)2
    D)4
    Answer: 5
  • Q. Except ________ signal, cabin master shall not show any other signal from his cabin during shunting.
    A)Red hand signal
    B)Yellow signal
    C)Green signal
    D)None of these
    Answer: Red hand signal
  • Q. The speed of a Trolley is
    A)15 kmph
    B)20 kmph
    C)8 kmph
    D)None of these
    Answer: 15 kmph
  • Q. When an accident occurs the GDR must their report to next SM in form.
    A)ACC5
    B)ACC1
    C)ACC2
    D)ACC3
    Answer: ACC3
  • Q. To apply for Line block, the notice shall be given to DRM not less than
    A)12 hours
    B)48 hours
    C)24 hours
    D)None of these
    Answer: 24 hours
  • Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
    A)30 kmph
    B)Normal speed
    C)15 kmph
    D)60 kmph
    Answer: 60 kmph
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. Track maintenance machine is permitted to work during
    A)Day clear weather
    B)Day
    C)Day and Night
    D)None of these
    Answer: Day and Night
  • Q. What is the maximum speed in block section during thick & foggy weather?
    A)15 kmph
    B)30 kmph
    C)60 kmph
    D)Not to move
    Answer: 60 kmph
  • Q. Maximum No. of ________ coaches can be attached in rear of SLR of passenger train.
    A)4
    B)2
    C)3
    D)6
    Answer: 2
  • Q. When the engine is pushing a material train and BV is not leading, the speed shall not exceed.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)30 kmph
    Answer: 10 kmph
  • Q. The driver shall sound the following whistle to indicate that the fouling marks is not clear
    A)One long
    B)Three long
    C)Short one long
    D)None of these
    Answer: Three long
  • Q. Block overlap in two aspect signalling system is ________ meters.
    A)400
    B)500
    C)600
    D)600
    Answer: 400
  • Q. If the Advanced starter is defective and IBS is working, SM shall issue ________ authority with private number of same station to pass the advanced starter.
    A)T/369(4b)
    B)T/369(3b)
    C)T/369(2B)
    D)T/369(5b)
    Answer: T/369(3b)
  • Q. When the train enters the block section without ATP, to permit to start the Train, SM to issue restarting memo with ________.
    A)Both
    B)PN
    C)Without PN
    D)None of these
    Answer: PN
  • Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of BP pressure in the brake van.
    A)6.8
    B)7.8
    C)5.8
    D)4.8
    Answer: 4.8
  • Q. What is the maximum speed of a goods train pushed backed from block section ?
    A)15/8 kmph
    B)15 kmph
    C)8 kmph
    D)None of these
    Answer: 8 kmph
  • Q. For ‘B’ Class ISMD load, permission must be granted by
    A)CE
    B)DRM
    C)CRS
    D)None of these
    Answer: CE
  • Q. In automatic block system SL, the minimum equipment of signal shall be
    A)Home, Starter, Advance Starter
    B)Home, Starter
    C)Distance Home Starter
    D)None of these
    Answer: Home, Starter