Q. The wagon containing ISMD load shall be attached.

Correct Answer

Next to Engine

More Questions on Indian Railway

  • Q. Gorakhpur which has the longest railway platform in the world is located in which of the following states?
    A)Uttar Pradesh
    B)Odisha
    C)West Bengal
    D)Chhattisgarh
    Answer: Uttar Pradesh
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. Signal failure advised to the driver through the station in rear will be inform
    A)T/369(3b)
    B)T/369
    C)T/370
    D)None of these
    Answer: T/369
  • Q. Motor vehicle in closed wagon shall be attached ________ position from engine on a passenger train.
    A)Third
    B)First
    C)Second
    D)None of these
    Answer: Third
  • Q. What action shall be taken by loco pilot if Guard failed to exchange all right signal after passing engineering speed restriction zone?
    A)Stop his train and find the cause
    B)Proceed further with same speed up to next station
    C)Proceed further with normal speed
    D)None of these
    Answer: Stop his train and find the cause
  • Q. Distance between two automatic signals is called as ________.
    A)Signalling Section
    B)Block section
    C)Mid Section
    D)None of these
    Answer: Signalling Section
  • Q. The Ministry of Railways has recently launched which app for freight managers?
    A)SNOORTI app
    B)SFOORTI app
    C)SKOORTI app
    D)SMOORTI app
    Answer: SFOORTI app
  • Q. What will be the maximum speed if leading cab of electric engine is defective and assistant driver is operating the train from rear cab?
    A)40 kmph
    B)15 kmph
    C)30 kmph
    D)Normal
    Answer: 40 kmph
  • Q. Engineering allowance, loco gain and traffic gain are mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. Illuminated A marker of semi-automatic signal means ________.
    A)Outer signal
    B)Working as automatic signal
    C)Semi signal
    D)None of these
    Answer: Working as automatic signal
  • Q. What is the length of North – Eastern Frontier Railway (NEFR)?
    A)4290 km
    B)4300 Km
    C)3700 Km
    D)5298 km
    Answer: 3700 Km
  • Q. If the patrol man does not turn up within ________ minutes, he will be treated as delayed.
    A)15
    B)10
    C)20
    D)40
    Answer: 15
  • Q. Block competency certificate is given in the prescribed form ________.
    A)T/115A
    B)T/115B
    C)T/115C
    D)T/115D
    Answer: T/115B
  • Q. When a front portion of a parted train gives one long one short one long one short whistle, SM to wave ________ signal four times above head from side to side and acknowledge.
    A)Yellow
    B)RED
    C)Green
    D)None of these
    Answer: RED
  • Q. Yearly goods stock census is taken on ________.
    A)30st November
    B)31st December
    C)31st October
    D)31st March
    Answer: 30st November
  • Q. It is a Python Rake.
    A)15 kmph
    B)60 kmph
    C)25 kmph
    D)Normal speed
    Answer: 60 kmph
  • Q. Trolley caution order no is ________.
    A)600
    B)400
    C)500
    D)800
    Answer: 400
  • Q. Which state has the longest route (in kilometers) of railway line in India?
    A)Rajasthan
    B)Maharashtra
    C)Andhra Pradesh
    D)Uttar Pradesh
    Answer: Uttar Pradesh
  • Q. During TFC in single line section what authority to proceed will be served to driver of Dn train during return.
    A)TH-602
    B)T/A-602
    C)TG-602
    D)TB-602
    Answer: TH-602
  • Q. LV board will be of ________ colour and with LV.
    A)Yellow
    B)Red
    C)Green
    D)None of these
    Answer: Red

Leave a Comment