More Questions on Indian Railway
- Q. Modified lower quadrant signaling may be introduced only with section of
A)GM
B)Railway Board
C)CRS
D)None of these
Answer: CRS
- Q. In the work of short duration the first flag man to the approaching train must started at not less than ________ Metres from the last detonator.
A)145
B)45
C)90
D)150
Answer: 45
- Q. The validity of BCC is for ________ years
A)01 years
B)03 years
C)02 years
D)None of these
Answer: 03 years
- Q. All the authorities related to TSL working are examined by TI and its report is submitted to DRM within ________ days of resumption of normal working.
A)10
B)7
C)9
D)15
Answer: 7
- Q. If distant signal show green accepts, which indication is shown for loco pilot on single distant?
A)Receive on loop line
B)Run through from station
C)Receive of Main line
D)None of these
Answer: Run through from station
- Q. The time taken for formation of a goods train in flat yard is
A)3 kmph
B)2 hrs
C)1 hr
D)None of these
Answer: 2 hrs
- Q. The additional Hours in the case of staff posted at way side stations who are provided with quarters within 0.5kkm will be ________ beyond.
A)24 Hours
B)12 Hours
C)08 Hours
D)16Hours
Answer: 24 Hours
- Q. What is the speed of second train on double line section running on T/A602?
A)10 kmph
B)20 kmph
C)15 kmph
D)8 kmph
Answer: 8 kmph
- Q. Permission of ________ is required to work the material train in the night.
A)DRM
B)AOM
C)DOM
D)None of these
Answer: DRM
- Q. There is insufficient vacuum/pressure in engine.
A)_____00
B)___0___
C)0___0
D)00-----
Answer: 00-----
- Q. When the points are set for main line, point indicator shows white target by day and ________ Light by night.
A)Yellow
B)Red
C)Green
D)White
Answer: White
- Q. While stabling box load, hand brakes of ________ wagons at both ends shall be pinned down.
A)7 - 7
B)8 - 8
C)6 - 6
D)8 - 8
Answer: 6 - 6
- Q. When a running line is occupied ________ entry must be made in TSR.
A)Yellow Ink
B)Red Ink
C)Green Ink
D)None of these
Answer: Red Ink
- Q. Block overlap in multiple aspect signalling system is ________ meters.
A)180
B)200
C)300
D)208
Answer: 180
- Q. In TALQ signalling system, ________ signal will be treated as defective if home signal becomes defective.
A)Hand
B)Outer
C)Call-On
D)Non eof these
Answer: Outer
- Q. Adequate distance kept beyond the starter signal to take off the home signal is called as ________.
A)Block instrument
B)Signal over lap
C)Over lap
D)None of these
Answer: Signal over lap
- Q. When a train is working on T/B 912 in automatic block in system the speed of train when the view ahead is clear with straight line is
A)15 kmph
B)25 kmph
C)20 kmph
D)None of these
Answer: 25 kmph
- Q. In case of ACP Guard shall proceed towards the front from ________ side.
A)Back
B)Left
C)Right
D)Noe of these
Answer: Left
- Q. When the rail failure is rectified by the train can pass at speed
A)30 kmph
B)20 kmph
C)25 kmph
D)None of these
Answer: 30 kmph
- Q. Interchange point of Central and Western railway is ________.
A)Both
B)Dadar
C)Jalgaon
D)None of these
Answer: Both
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State