Q. The wagon containing ISMD load shall be attached.

Correct Answer

Next to Engine

More Questions on Indian Railway

  • Q. Distance between two automatic signals is called as ________.
    A)Signalling Section
    B)Block section
    C)Mid Section
    D)None of these
    Answer: Signalling Section
  • Q. Modified lower quadrant signaling may be introduced only with section of
    A)GM
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS
  • Q. The speed of engine movement from traffic yard to loco and loco to traffic yard is
    A)15 kmph
    B)8 kmph
    C)10 kmph
    D)None of these
    Answer: 10 kmph
  • Q. Shunting restrictions of station is written in ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: SWR
  • Q. Guard shall exchange alright hand signal from ________ side while the train is started from the station.
    A)Both
    B)Path
    C)Platform
    D)None of these
    Answer: Platform
  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. In automatic areas when all signals have failed and communication is available, the driver is issued ________ as authority to proceed.
    A)T/C-912
    B)T/B-912
    C)T/D-912
    D)None of these
    Answer: T/D-912
  • Q. ________ is measured with the help of anemometer.
    A)Both
    B)Wind
    C)Velocity
    D)None of these
    Answer: Both
  • Q. Target time for departing ART during day is 30 minutes and during night is ________ minutes.
    A)60
    B)40
    C)50
    D)45
    Answer: 45
  • Q. EMU trains of harbour line has ________ number of wooden wedges.
    A)6
    B)2
    C)4
    D)8
    Answer: 4
  • Q. Second train during all communication failure shall be dispatched after an interval of
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. Calling on signal shows ________ light in off position in two aspect signalling system.
    A)Green
    B)White
    C)RED
    D)Yellow
    Answer: Yellow
  • Q. While ordering ART/MRV each siren shall be sounded for ________ seconds.
    A)43
    B)41
    C)42
    D)45
    Answer: 45
  • Q. ________ brake is not provided in the coach of passenger train.
    A)Minor
    B)Hand
    C)Non-hand
    D)None of these
    Answer: Hand
  • Q. For extinguished home signal, Loco Pilot will be issued ________ authority form the station in rear in MACLS system.
    A)16
    B)20
    C)12
    D)10
    Answer: 16
  • Q. How many systems of working in Indian Railways for train operation?
    A)8
    B)6
    C)7
    D)9
    Answer: 6
  • Q. In the enroute, M/E train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 90
  • Q. Consider the following statements about the Bio Toilet Project in Indian Railways: 1)The bio – toilets are joint initiative of Indian Railways and DRDO 2)The human excreta in the bio – toilets is treated through anaerobic digestion process 3)The bio toilet reduces the solid human waste to biogas and pure water Which of the above statements is/are correct?
    A)2 & 3 Only
    B)1 & 3 Only
    C)2 Only
    D)1, 2 & 3
    Answer: 1, 2 & 3
  • Q. When baking a train from one line to the other line, it is necessary to present the train guard.
    A)Break van
    B)Point
    C)Station
    D)Any Place
    Answer: Break van
  • Q. BSLB determines the limits of Station section and ________.
    A)Station Limit
    B)Block Section
    C)Station Section
    D)None of these
    Answer: Block Section