Q. The wagon containing ISMD load shall be attached.

Correct Answer

Next to Engine

More Questions on Indian Railway

  • Q. Number of the caution order is ________
    A)T/410
    B)T/409
    C)T/408
    D)None of these
    Answer: T/409
  • Q. Maximum speed of shunting of wagons with explosives is ________ km/h.
    A)15
    B)8
    C)10
    D)20
    Answer: 8
  • Q. Time taken by train running at booked speed is called as ________.
    A)Normal running time
    B)Long time
    C)Minimum running time
    D)None of these
    Answer: Normal running time
  • Q. DRM nominates ________ for each section to issue caution orders to train crew.
    A)Nil notice
    B)Caution notice station
    C)Notice
    D)None of these
    Answer: Caution notice station
  • Q. Which of the following stations has all the three gauges viz. broad, metre and narrow?
    A)Shimla
    B)Lucknow
    C)Chandigarh
    D)Siliguri
    Answer: Siliguri
  • Q. Motor Trolly can follow another motor trolly during
    A)Day and Night clear weather
    B)Day and Night
    C)Day only
    D)None of these
    Answer: Day and Night clear weather
  • Q. When a passenger carrying train is working with engine running tender foremost the speed is ________ if cow catcher and head light is not provided.
    A)15 kmph
    B)25 kmph
    C)20 kmph
    D)None of these
    Answer: 20 kmph
  • Q. To receive a train on unsignalled line, ________ authority is issued.
    A)T/369(4b) Pilot in MEMU
    B)T/369(3b) Pilot in MEMO
    C)T/369(2B) Pilot in MEMO
    D)T/369(5b) Pilot in MEMU
    Answer: T/369(3b) Pilot in MEMO
  • Q. In the event of an accident falling in more than one class it should be treated as an accident in the ________ class.
    A)Both
    B)Lowest
    C)Highest
    D)None of these
    Answer: Highest
  • Q. When baking a train from one line to the other line, it is necessary to present the train guard.
    A)Break van
    B)Point
    C)Station
    D)Any Place
    Answer: Break van
  • Q. In diesel engine, ignition is caused by
    A)Compression
    B)Spark
    C)Automatic starter
    D)Friction
    Answer: Compression
  • Q. For Block Back form ________ To be issued on DL.
    A)T/B-806+PN
    B)T/806+PN
    C)T/A806+PN
    D)None of these
    Answer: T/806+PN
  • Q. At Terminal yards where the signal overlap is zero, the speed over facing points is ________ kmph
    A)10
    B)20
    C)30
    D)None of these
    Answer: 10
  • Q. Which year is declared as “Year of Rail Users” by the Indian Railways?
    A)1996
    B)2000
    C)1995
    D)1997
    Answer: 1995
  • Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
    A)LI
    B)TI
    C)CI
    D)None of these
    Answer: TI
  • Q. Which authority shall be received to proceed for obstructed block section due to an Accident?
    A)T/A 602
    B)T-1425
    C)T-369(3b)+P.No.
    D)Simple memo
    Answer: T/A 602
  • Q. When a goods train is working without brake can the speed is
    A)25 kmph by day and 15 kmph by night
    B)15 kmph
    C)25 kmph
    D)None of these
    Answer: None of these
  • Q. A jumper is remote control and is used for ________.
    A)Control on Light, Fan etc.
    B)Light
    C)Fans
    D)None of these
    Answer: Control on Light, Fan etc.
  • Q. Shutting signal in the color light signal system under the starter of which light is visible in the on-condition?
    A)Single white
    B)Yellow
    C)Two White parallel
    D)No light
    Answer: No light
  • Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?
    A)27 meters
    B)30 meters
    C)3 meters
    D)100 meters
    Answer: 30 meters