- Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
A)Sectional
B)Corner
C)Warner
D)None of these
Answer: Warner
- Q. TSL is started between those two stations at which cross over facility are available and
A)D Class/IBC
B)A Class/IBS
C)C Class/IBS
D)None of these
Answer: C Class/IBS
- Q. Under approved special instructions, Distant signal can be placed along with the
A)Both
B)Last Stop
C)First Stop
D)None of these
Answer: Last Stop
- Q. If the IBS is defective and advanced starter is working, SM shall issue ________ authority with private number of next station to pass IBS.
A)T/369(4b)
B)T/369(3b)
C)T/369(2B)
D)T/369(5b)
Answer: T/369(3b)
- Q. How many officers may be attached with light engine?
A)1
B)2
C)3
D)None of these
Answer: 3
- Q. Reference of ________ is written by the side of the Rule if the Rule is corrected.
A)No. and Item No. Correction Slip
B)Number Slip
C)Item Number
D)None of these
Answer: No. and Item No. Correction Slip
- Q. During single line working on double line in automatic area the speed of all train running in wrong direction shall not exceed
A)10 kmph
B)25 kmph
C)15 kmph
D)None of these
Answer: 25 kmph
- Q. When an incomplete parted portion arrives at a station the Driver to stop his train at ________ and give one long one short one long one short whistle.
A)Both
B)Outer Most facing Points
C)Inner Most facing signal
D)None of these
Answer: Outer Most facing Points
- Q. Railway staff collage is situated at ________.
A)Chennai
B)Vadodara
C)Kanyakumari
D)New Delhi
Answer: Vadodara
- Q. In automatic area, when all signals and communications have failed, the driver is issued ________ as authority to proceed.
A)T/A-912
B)T/B-912
C)T/C-912
D)None of these
Answer: T/B-912
- Q. BSLB determines the limits of Station section and ________.
A)Station Limit
B)Block Section
C)Station Section
D)None of these
Answer: Block Section
- Q. The speed of shunting is ________.
A)10 kmph
B)15 kmph
C)20 kmph
D)None of these
Answer: 15 kmph
- Q. Number of train signal register of double line is ________.
A)T/66 B
B)T/66 A
C)T/66 C
D)T/66
Answer: T/66 B
- Q. How many minimum BP pressure is require in engine to charge Goods train?
A)5.8 kg/cm2 D. 5.00 kg/cm2
B)4.8 kg/cm2 B. 6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
C)6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
D)5.00 kg/cm2
Answer: 5.00 kg/cm2
- Q. Departmental enquiry must be ordered by ________.
A)DRM
B)Sr. DPO
C)COM
D)Sr. DOM
Answer: DRM
- Q. If leakage in LPG Tank, how long area is prohibited to carry to burn the burning fire ?
A)100 meters
B)45 meters
C)50 meters
D)1000 meters
Answer: 45 meters
- Q. Which marker is available in repeating signal?
A)P-Marker
B)G-Marker
C)C-Marker
D)R-Marker
Answer: R-Marker
- Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5
B)10
C)20
D)None of these
Answer: 10
- Q. Speed of train when whistle becomes defective is ________ km/h.
A)45/8
B)30/8
C)25/8
D)40/8
Answer: 25/8
- Q. During shunting, outer, home and ________ signals are not taken off.
A)Both
B)Last stop signal
C)First stop signal
D)None of these
Answer: First stop signal