- Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.
A)15 km
B)8 km
C)10 km
D)25 km
Answer: 25 km
- Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
A)25/10 kmph
B)15/8 kmph
C)25/8 kmph
D)25/12 kmph
Answer: 25/8 kmph
- Q. What is the maximum speed of 140 ton diesel hydraulic crane?
A)140 kmph
B)75 kmph
C)100 kmph
D)160 kmph
Answer: 75 kmph
- Q. Maximum of ________ cranes can be attached in a passenger train.
A)3
B)1
C)2
D)4
Answer: 1
- Q. In which city is the Wheel and Axle Plant of the Indian Railways located?
A)Bangalore
B)Kapurthala
C)Varanasi
D)Rae Barelly
Answer: Bangalore
- Q. In case of defective head light, ________ bell code is given on block instrument to the station in advance.
A)000000-000
B)00000-0
C)000000-0
D)0000-00
Answer: 000000-0
- Q. Where is RDSO Situated.
A)Chennai
B)Vadodara
C)Lucknow
D)New Delhi
Answer: Lucknow
- Q. At the starting station, CC rake goods train must have ________ % of brake power.
A)90
B)75
C)50
D)100
Answer: 100
- Q. Tower wagon shall run as per the rules of working of ________.
A)Passengers
B)Wagon
C)Train
D)None of these
Answer: Train
- Q. The Ministry of Railways has recently launched which app for freight managers?
A)SNOORTI app
B)SFOORTI app
C)SKOORTI app
D)SMOORTI app
Answer: SFOORTI app
- Q. Stop signal is to be passed in On position.
A)T-806
B)T-509
C)T-369(3b)
D)Simple memo
Answer: T-369(3b)
- Q. Block section limit board provided at station?
A)B class Single line TA
B)B class Single line MAUQ
C)B class Double line TA
D)B class Double line MA
Answer: B class Double line MA
- Q. While passing through the non-interlocked points, maximum speed of the train shall be ________ km/h.
A)15 km
B)8 km
C)10 km
D)20 km
Answer: 15 km
- Q. In case of accident, siren is repeated at an interval of ________ minutes.
A)20
B)10
C)15
D)5
Answer: 5
- Q. The senior most ________ officer is personally responsible for ensuring and efficient handing of cranes and removal of wreckage after accident.
A)C & W
B)Engineering
C)Mechanical
D)None of these
Answer: Mechanical
- Q. Which of the following is the largest zone in terms of route kilometers?
A)Northern Railways
B)Western Railways
C)Eastern Railways
D)Southern Railways
Answer: Northern Railways
- Q. If a military personnel is injured or killed in railway premises the DRM shall advise ________ New Delhi.
A)Army Head Quarter
B)Railway Board
C)Zonal HQ
D)None of these
Answer: Army Head Quarter
- Q. Which of the following stations was formerly known as Victoria Terminus?
A)Lokmanya Tilak Terminus
B)Churchgate Railway Station
C)Mumbai Central
D)Chhatrapati Shivaji Terminus
Answer: Chhatrapati Shivaji Terminus
- Q. During shunting, outer, home and ________ signals are not taken off.
A)Both
B)Last stop signal
C)First stop signal
D)None of these
Answer: First stop signal
- Q. Time taken by train running at MPS is called as ________.
A)Normal running time
B)Long time
C)Minimum running time
D)None of these
Answer: Minimum running time