More Questions on Indian Railway
- Q. The first Shatabdi express was introduced between which of the following locations?
A)New Delhi and Jhansi
B)Bombay and Thane
C)Bombay and Kolkata
D)New Delhi and Chennai
Answer: New Delhi and Jhansi
- Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the brake van.
A)6.8
B)7.8
C)5.8
D)4.7
Answer: 4.7
- Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
A)30
B)20
C)25
D)15
Answer: 15
- Q. Time taken by train running at MPS is called as ________.
A)Normal running time
B)Long time
C)Minimum running time
D)None of these
Answer: Minimum running time
- Q. The headquarters of North – East Frontier Railway (NFR) is
A)Chennai
B)Kolkata
C)Maligaon (Guwahati)
D)Gorakhpur
Answer: Maligaon (Guwahati)
- Q. Shunting restrictions of station is written in ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: SWR
- Q. Interchange point of Central and Western railway is ________.
A)Both
B)Dadar
C)Jalgaon
D)None of these
Answer: Both
- Q. To admit the train on loop line, generally the far end points are to be ser for ________.
A)Both
B)Loop line
C)Main line
D)None of these
Answer: Main line
- Q. In automatic block area SL. The LSS shall not be taken off unless the line is clear upto
A)Automatic stop signal+180 Meters
B)Next automatic stop signal
C)Automatic stop signal+120 Meters
D)None of these
Answer: Next automatic stop signal
- Q. During prolonged failure of signals in automatic section, ________ authority is issued.
A)T/C 912
B)T/B 912
C)T/D 912
D)T/A 912
Answer: T/D 912
- Q. How many institutions do give suggestions for railways technology?
A)Three
B)One
C)Two
D)Four
Answer: Two
- Q. Train is to be passed through loop line.
A)30 kmph
B)15 kmph
C)25 kmph
D)Normal speed
Answer: 15 kmph
- Q. Knowledge of subsidiary rules is examined by ________ if train working staff of another Railway is required to work on our Railway.
A)LI
B)TI
C)CI
D)None of these
Answer: TI
- Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A)30
B)20
C)10
D)None of these
Answer: 30
- Q. On double line, when a running line is blocked by stabled load , the point to be set against are
A)Advance point
B)Either side points
C)Rear points
D)None of these
Answer: Rear points
- Q. When the train is stopped at FSS for more than ________ minutes, the Driver must send his assistant to station after consulting with guard.
A)10
B)5
C)7
D)None of these
Answer: 5
- Q. Signal has extinguished.
A)------00
B)___0___
C)0___0
D)00___
Answer: ------00
- Q. Distance between two automatic signals is called as ________.
A)Signalling Section
B)Block section
C)Mid Section
D)None of these
Answer: Signalling Section
- Q. Not more than ________ persons including trollyman shall go on a trolly.
A)9
B)10
C)3
D)4
Answer: 10
- Q. How many hooters shall be used for ART at the time of accident of a goods train outside the HQ.
A)4
B)2
C)3
D)5
Answer: 3