Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.
A
25
B
20
C
15
D
None of these
Correct Answer
25
More Questions on Indian Railway
Q. When four wheeler attached, speed of passenger train will be ________ km/h.
A)85 B)80 C)75 D)90
Answer: 75
Q. Departmental enquiry must be ordered by ________.
A)DRM B)Sr. DPO C)COM D)Sr. DOM
Answer: DRM
Q. Load table is mentioned in the ________.
A)SOR B)SWR C)WTT D)None of these
Answer: WTT
Q. In case of defective head light, ________ bell code is given on block instrument to the station in advance.
A)000000-000 B)00000-0 C)000000-0 D)0000-00
Answer: 000000-0
Q. In how many zones Indian Railway has been divided?
A)17 B)14 C)16 D)20
Answer: 17
Q. India’s first – ever railways disaster management centre will come up in which city?
A)Lucknow B)Kolkata C)Bengaluru D)Pune
Answer: Bengaluru
Q. When the water rises above ballast level, but below rail level in cause ways, train may be permitted to run by
A)2 gangman B)JE(Pway) C)One gangman D)None of these
Answer: JE(Pway)
Q. Which marker is available in repeating signal?
A)P-Marker B)G-Marker C)C-Marker D)R-Marker
Answer: R-Marker
Q. Hand shunting outside section in gradient ________ is prohibited except with DRM permission.
A)ST 1-800 B)ST 1-600 C)ST 1-700 D)None of these
Answer: ST 1-600
Q. Which of the following is / are eligible to receive Ways and Means Advances from RBI to handle their temporary mismatch in the cash flow? 1)State Governments 2)Central Government 3)Public Sector Companies 4)Indian Railways Select the correct option from the codes given below:
Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
A)30 kmph B)Normal speed C)15 kmph D)60 kmph
Answer: 60 kmph
Q. Block overlap in two aspect signalling system is ________ meters.
A)400 B)500 C)600 D)600
Answer: 400
Q. After passing an automatic stop signal at ON. If the Driver finds a train or obstruction he must stop his train at ________ away from the train or obstruction.
A)150 meters B)200 meters C)180 meters D)None of these
Answer: 150 meters
Q. On the electrified area in sections at 25 KV A.C., when the gross clearance is between 390 MM and 340 MM the speed must be
A)8 kmph B)10 kmph C)15 kmph D)None of these
Answer: 15 kmph
Q. In the panel working for cancellation of route the number in the counter changes and white indication appears after
A)50 seconds B)120 seconds C)90 seconds D)None of these
Answer: 120 seconds
Q. When the train catches fire, that carriage must be ________.
A)Both B)Isolated C)Non-isolated D)None of these
Answer: Isolated
Q. Consider the following steps in Budget Procedure in India: 1)The demands for grants of various ministries and departments including railways are considered by the concerned standing committees 2)Broad contours of the budget and the principles and policies underlying it are discussed. 3)A cut motion is moved in the Lok Sabha 4)Budget is presented in the House. Which among the following is the correct sequence of the above steps?
A)4 2 1 3 B)1 2 3 4 C)1 2 4 3 D)3 1 4 2
Answer: 4 2 1 3
Q. When a driver finds automatic stop signal at on he must stop for 01 minute during day and 02 minutes during night and proceed at ________ kmph
A)25 B)15 C)20 D)None of these
Answer: 15
Q. Loco pilot must have ________ sets of spectacles in his personal store.
A)Three B)Two C)One D)None of these
Answer: Two
Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.