Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.

Correct Answer

25

More Questions on Indian Railway

  • Q. For Block Back form ________ To be issued on DL.
    A)T/B-806+PN
    B)T/806+PN
    C)T/A806+PN
    D)None of these
    Answer: T/806+PN
  • Q. Target time for dispatch of ARME from single exit siding at night is ________ minutes.
    A)8
    B)10
    C)5
    D)25
    Answer: 25
  • Q. Adequate distance means the distance sufficient to ensure ________.
    A)Station Limit
    B)Safety
    C)Non-Safety
    D)None of these
    Answer: Safety
  • Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
    A)Walkie-Talkie
    B)Walkie
    C)VHF
    D)None of these
    Answer: Walkie-Talkie
  • Q. Any person aggrieved by a decision if labour commissioner may prefer an appeal to the central government within ________ days from the Regional Labour Commissioner
    A)30
    B)10
    C)20
    D)None of these
    Answer: 30
  • Q. Number of train signal register of single line is ________.
    A)T/166 B
    B)T/136 A
    C)T/137 B
    D)T/135
    Answer: T/137 B
  • Q. Maximum speed of pushing back is ________ km/h.
    A)45
    B)30
    C)25
    D)40
    Answer: 25
  • Q. Diesel locomotives are built in?
    A)Perambur
    B)Banglore
    C)Varanasi
    D)Hubli
    Answer: Varanasi
  • Q. Caution indication board will be provided at ________ meters from the bridge or vulnerable places.
    A)600
    B)500
    C)400
    D)800
    Answer: 600
  • Q. Clocks of control office shall be synchronized with All India Radio at 08:00 hours,
    A)15:30
    B)14:30
    C)12:30
    D)13:30
    Answer: 13:30
  • Q. Dead engine is attached at ________ position on a Mail / Express train.
    A)Both
    B)Engine to engine
    C)Next to engine
    D)None of these
    Answer: Next to engine
  • Q. On which speed BG train should be run while speedometer failed in block section?
    A)No need to reduced speed
    B)10% less of sectional speed
    C)10% less of booked speed
    D)40 kmph
    Answer: 10% less of sectional speed
  • Q. Not more than ________ persons including trollyman shall go on a trolly.
    A)9
    B)10
    C)3
    D)4
    Answer: 10
  • Q. A lorry shall be protected by banner flags and detonators if it remains stationary within the station yard for more than
    A)20 meters
    B)15 meters
    C)10 meters
    D)None of these
    Answer: 15 meters
  • Q. If warner signal of any station becomes defective in off condition, ________ is issued to Loco Pilot from the station in rear.
    A)Verbally
    B)Walkie-Talkie
    C)Written Memo
    D)None of these
    Answer: Written Memo
  • Q. The turning out time off BD SPL. During day is ________ minutes
    A)50
    B)30
    C)20
    D)None of these
    Answer: 30
  • Q. Yearly coaching stock census is taken on ________.
    A)31st January
    B)31st December
    C)31st October
    D)31st March
    Answer: 31st October
  • Q. Ruling gradient of the division is mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. Which whistle code shall be used by loco pilot while Approach on W board.
    A)Three short
    B)Long continue
    C)Intermittent
    D)Three long
    Answer: Intermittent
  • Q. In the enroute, M/E train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 90