Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.

Correct Answer

25

More Questions on Indian Railway

  • Q. Which of the following zonal headquarters – city combination is incorrect?
    A)East Central - Hajipur
    B)South East Central - Bilaspur
    C)North Western - Jodhpur
    D)West Central - Jabalpur
    Answer: North Western - Jodhpur
  • Q. After passing an automatic stop signal at ON. If the Driver finds a train or obstruction he must stop his train at ________ away from the train or obstruction.
    A)150 meters
    B)200 meters
    C)180 meters
    D)None of these
    Answer: 150 meters
  • Q. After how much time Any goods train shall be treated as overdue train?
    A)After 20 minutes
    B)After 10 minutes
    C)After 15 minutes
    D)After 25 minutes
    Answer: After 20 minutes
  • Q. Section controller shall transmit the correct time at ________ hours daily to all the stations.
    A)16
    B)20
    C)12
    D)10
    Answer: 16
  • Q. After the detonator explodes if Driver does not find any signal he can proceed upto ________ Km cautiously
    A)2
    B)1.5
    C)1
    D)None of these
    Answer: 1.5
  • Q. Special instructions are issued by ________.
    A)Both
    B)COM
    C)Sr. DOM
    D)None of these
    Answer: COM
  • Q. How many surrounding area may be sealed from fire in case of leakage in LPG tank wagon?
    A)1500 meters
    B)200 meters
    C)1000 meters
    D)2000 meters
    Answer: 1000 meters
  • Q. Wagon with livestock shall be attached ________ position from engine on a goods train.
    A)Third
    B)First
    C)Second
    D)None of these
    Answer: Second
  • Q. Reference of ________ is written by the side of the Rule if the Rule is corrected.
    A)No. and Item No. Correction Slip
    B)Number Slip
    C)Item Number
    D)None of these
    Answer: No. and Item No. Correction Slip
  • Q. On which speed BG engine shall be run while speedometer is defective during run?
    A)25 kmph
    B)50 kmph
    C)40 kmph
    D)Maximum 10% less of MPS
    Answer: Maximum 10% less of MPS
  • Q. In recent times, the “dynamic brake system” is becoming popular in modern railways. The dynamic brake system coverts Kinetic energy to________:
    A)Sound energy
    B)Potential energy
    C)Electricity
    D)Magnetic energy
    Answer: Electricity
  • Q. In push button token less territory, before starting the train with for T/369(1) during signal failure at station in advance, SM to get ________ from that station.
    A)Both
    B)PN
    C)Non-PN
    D)None of these
    Answer: PN
  • Q. What is the target time for ART during night hours?
    A)60 minutes
    B)30 minutes
    C)45 minutes
    D)20 minutes
    Answer: 45 minutes
  • Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
    A)Sectional
    B)Corner
    C)Warner
    D)None of these
    Answer: Warner
  • Q. New Humsafar Express, 3 – tier AC train was flagged off between which two locations on 2 June 2018?
    A)Agartala and Bengaluru
    B)Ajmer and Rameshwaram
    C)Gorakhpur and Anand Vihar
    D)Jodhpur and Bandra
    Answer: Jodhpur and Bandra
  • Q. The additional Hours in the case of Gate man C saloon attendant, care takers will be ________
    A)24 Hours
    B)12 Hours
    C)08 Hours
    D)16 Hours
    Answer: 24 Hours
  • Q. Number of the caution order is ________
    A)T/410
    B)T/409
    C)T/408
    D)None of these
    Answer: T/409
  • Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
    A)Block sectiond
    B)Next whole block section
    C)Back whole block section
    D)None of these
    Answer: Next whole block section
  • Q. Notice station caution order No. is ________
    A)T/C-409
    B)T/409
    C)T/B-409
    D)None of these
    Answer: T/409
  • Q. Motorman of EMU shall give ________ bell code while passing A marker lit gate signal in ON position.
    A)0-00
    B)00-00
    C)000-000
    D)None of these
    Answer: 00-00

Leave a Comment