Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.

Correct Answer

25

More Questions on Indian Railway

  • Q. What will be the distance between banner flag and stop indicator if engineering work continue for more than one day ?
    A)27 meters
    B)30 meters
    C)3 meters
    D)100 meters
    Answer: 30 meters
  • Q. General Manger is responsible for
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board
  • Q. Indian Railway will be provided a device to their Gang Men which would be wireless enabled and will intimate them about approaching trains. The Device will be called:
    A)Shaktimaan
    B)Surakhsha
    C)Rail Rakshak
    D)Rakshak
    Answer: Rakshak
  • Q. The speed of the train over neutral section shall not be less than ________ kmph
    A)40
    B)20
    C)30
    D)None of these
    Answer: 30
  • Q. Track maintenance machine is permitted to work during
    A)Day clear weather
    B)Day
    C)Day and Night
    D)None of these
    Answer: Day and Night
  • Q. Maximum speed of tower wagon is ________ km/h.
    A)40
    B)25
    C)20
    D)50
    Answer: 40
  • Q. Where is the information about the Ruling Gradient of a section?
    A)G & SR
    B)SWR
    C)WTT
    D)Operating Manual
    Answer: WTT
  • Q. In recent times, the “dynamic brake system” is becoming popular in modern railways. The dynamic brake system coverts Kinetic energy to________:
    A)Sound energy
    B)Potential energy
    C)Electricity
    D)Magnetic energy
    Answer: Electricity
  • Q. What will be the code of engine whistle during signal passing at ON or in defective condition on proper authority information by the Loco Pilot to Guard ?
    A)--0
    B)0-0
    C)-0-
    D)---
    Answer: 0-0
  • Q. In the classification of A to R accidents, ________ and ‘o’ classes are not included.
    A)Both
    B)Minor
    C)Serious
    D)None of these
    Answer: Serious
  • Q. Where is the Railway Staff College located?
    A)Vadodara
    B)Pune
    C)Delhi
    D)Allahabad
    Answer: Vadodara
  • Q. Warning boards for neutral section shall be fixed at a distance of
    A)300 and 600 meters
    B)400 and 600 meters
    C)500 and 250 meters
    D)None of these
    Answer: 500 and 250 meters
  • Q. Danger zone in 1500 DC traction is ________ meters from OHE.
    A)3
    B)1
    C)2
    D)4
    Answer: 1
  • Q. Signal overlap at a terminal station with multi aspect colour light signalling is ________.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. If any Loco pilot leave from his duty place without to informed to his supervisor, it is treated as?
    A)A & B both
    B)Absent from his duty
    C)Indiscipline
    D)None of these
    Answer: Absent from his duty
  • Q. In double Distant signalling, outermost signal is called as ________.
    A)Stop
    B)Distant
    C)Call-on
    D)None of these
    Answer: Distant
  • Q. Gorakhpur which has the longest railway platform in the world is located in which of the following states?
    A)Uttar Pradesh
    B)Odisha
    C)West Bengal
    D)Chhattisgarh
    Answer: Uttar Pradesh
  • Q. Max. Speed of special train with 132 tonne bogie well wagon shall be ________ km/h.
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. If loco pilot do not work in any section for more than 6 months, road learning for 2 trips by day and ________ trip by night is given.
    A)3
    B)1
    C)2
    D)4
    Answer: 1
  • Q. When was the first train steamed off in India?
    A)1875
    B)1848
    C)1853
    D)1880
    Answer: 1853