Q. Normal condition of automatic stop signal is ________.

Correct Answer

Green

More Questions on Indian Railway

  • Q. Depot in-charge is responsible to test the detonators once in ________.
    A)Year
    B)Monthly
    C)Weekly
    D)None of these
    Answer: Year
  • Q. Nil Caution order number is ________
    A)T/C409
    B)T/A-409
    C)T/B-409
    D)None of these
    Answer: T/A-409
  • Q. Which is the longest station name in Indian Railways?
    A)Kharagpur
    B)Kanyakumari
    C)Venkatanarasimharajuvaripeta
    D)Chhatrapati Shivaji Terminus
    Answer: Venkatanarasimharajuvaripeta
  • Q. What will be the minimum distance of 2 Towar Wagons in the same block section ?
    A)130 meters
    B)100 meters
    C)120 meters
    D)140 meters
    Answer: 120 meters
  • Q. Modified lower quadrant signaling may be introduced only with section of
    A)GM
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS
  • Q. Point indicator is provided to indicate ________.
    A)Both
    B)Points
    C)Bar
    D)None of these
    Answer: Points
  • Q. Station manager of a big station shall inspect the cabins at least once in ________.
    A)Thrice in a week.
    B)Once in a week
    C)Twice in a week
    D)None of these
    Answer: Once in a week
  • Q. While receiving train on an obstructed line and danger signal must be shown to LP at
    A)40 meters from obstruction
    B)45 meters
    C)30 meters
    D)None of these
    Answer: 45 meters
  • Q. Signals are normally located to the ________ side of the line.
    A)Both
    B)Right
    C)Left
    D)None of these
    Answer: Left
  • Q. Where is the information about the Ruling Gradient of a section?
    A)G & SR
    B)SWR
    C)WTT
    D)Operating Manual
    Answer: WTT
  • Q. Hand shunting is performed at speed not exceeding
    A)05 kmph
    B)10 kmph
    C)08 kmph
    D)None of these
    Answer: 05 kmph
  • Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
    A)Block sectiond
    B)Next whole block section
    C)Back whole block section
    D)None of these
    Answer: Next whole block section
  • Q. Block competency certificate is issued by ________.
    A)AOM
    B)Principal ZRTI
    C)SM
    D)None of these
    Answer: Principal ZRTI
  • Q. Where the caution indicator placed in BG if the engineering work is more than one days and train not to be require to stop at site?
    A)800 Meter
    B)1200 Meter
    C)1000 Meter
    D)500 Meter
    Answer: 800 Meter
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. During hand shunting only ________ Bogies can be hand shunted.
    A)3
    B)1
    C)2
    D)None of these
    Answer: 1
  • Q. In context with the Indian railways what is TPWS?
    A)Train Protection Warning Stopper
    B)Train Passenger Warning System
    C)Train Protection Warning System
    D)Transmission Protection warning Stopper
    Answer: Train Protection Warning System
  • Q. When was the first train in India started?
    A)1853
    B)1851
    C)1852
    D)1854
    Answer: 1853
  • Q. When was the construction work for the first Railway line Started?
    A)1823
    B)1821
    C)1828
    D)1830
    Answer: 1821
  • Q. During total interruption of communication on signal line. The speed of LE to establish communication is ________ kmph during day and clear weather.
    A)20
    B)10
    C)15
    D)None of these
    Answer: 15