More Questions on Indian Railway
- Q. Point indicator is provided to indicate ________.
A)Both
B)Points
C)Bar
D)None of these
Answer: Points
- Q. Point indicator shows ________ light when the points are set for loop line.
A)S&T (T/350)
B)S&T (T/351)
C)S&T (T/352)
D)S&T (T/315)
Answer: S&T (T/351)
- Q. If the driver does not receive all right signal from the guard, he must call by giving.
A)On long
B)Two sharp whistles
C)One long one short
D)None of these
Answer: Two sharp whistles
- Q. Visibility test object is placed at a distance of ________ meters from the station building.
A)180
B)108
C)100M
D)200
Answer: 180
- Q. Motorman shall give ________ beat to release the hand brakes.
A)00-00-00
B)00-0-00
C)0-0-0
D)0-00-00
Answer: 00-0-00
- Q. Consider the following statements about the Bio Toilet Project in Indian Railways: 1)The bio – toilets are joint initiative of Indian Railways and DRDO 2)The human excreta in the bio – toilets is treated through anaerobic digestion process 3)The bio toilet reduces the solid human waste to biogas and pure water Which of the above statements is/are correct?
A)2 & 3 Only
B)1 & 3 Only
C)2 Only
D)1, 2 & 3
Answer: 1, 2 & 3
- Q. Presentation of the first ever railway budget in India held in
A)1925
B)1853
C)1888
D)1905
Answer: 1925
- Q. Where is the information about the Ruling Gradient of a section?
A)G & SR
B)SWR
C)WTT
D)Operating Manual
Answer: WTT
- Q. While cancelling ART/MRV, siren shall be sounded for ________ seconds.
A)85
B)60
C)75
D)90
Answer: 90
- Q. Shunting restrictions of station is written in ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: SWR
- Q. Caution and Termination indication Boards will be fixed from the bridge or vulnerable places at
A)1000 meters
B)400 meters
C)600 meters
D)None of these
Answer: 600 meters
- Q. Maximum height above rail level for a low passenger platform in BG is
A)840 mm
B)455 mm
C)760 mm
D)None of these
Answer: 455 mm
- Q. To start the train from a line with common starter, ________ authority is issued.
A)T/512
B)T/516
C)T/517
D)T/511
Answer: T/512
- Q. Accident drill is to be conducted once in ________ if no real accident occurs during this period.
A)01 month
B)04 month
C)02 month
D)03 Months
Answer: 02 month
- Q. Hand shunting speed is ________
A)8 kmph
B)5 kmph
C)10 kmph
D)None of these
Answer: 5 kmph
- Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5
B)10
C)20
D)None of these
Answer: 10
- Q. The length of sand hump is about ________ feet.
A)170
B)150
C)120
D)170
Answer: 170
- Q. Track maintenance machine is permitted to work during
A)Day clear weather
B)Day
C)Day and Night
D)None of these
Answer: Day and Night
- Q. IN the BD Spl, the water must be filled ________.
A)Three Week
B)Once a week
C)Two week
D)None of these
Answer: Once a week
- Q. W/L board will be provided at not less than ________ metres from the gate.
A)600
B)400
C)500
D)800
Answer: 600