- Q. Caution indication board will be provided at ________ meters from the bridge or vulnerable places.
A)600
B)500
C)400
D)800
Answer: 600
- Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
A)T/407
B)T/409
C)T/408
D)T/406
Answer: T/409
- Q. When a trolley is working on T/1518 during thick or foggy weather, the speed is
A)10 kmph
B)5 kmph
C)8 kmph
D)None of these
Answer: 5 kmph
- Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
A)Block sectiond
B)Next whole block section
C)Back whole block section
D)None of these
Answer: Next whole block section
- Q. Guard shall use ________ bell code to warn the motorman, if motorman violated the speed.
A)0-00-00
B)000-000
C)00-00
D)000-000-000
Answer: 000-000
- Q. “Act” means the Railway Act is ________.
A)1989 (22 of 1989)
B)1989 (24 of 1989)
C)1989 (23 of 1989)
D)None of these
Answer: 1989 (24 of 1989)
- Q. What will be the maximum speed in Loop Line at B-Class standard-III interlocked station?
A)50 kmph
B)15 kmph
C)25 kmph
D)75 kmph
Answer: 15 kmph
- Q. When a train is received at a station during signal failure on signal post telephone, the speed of train is
A)8 kmph
B)15 kmph
C)25 kmph
D)None of these
Answer: 15 kmph
- Q. Which of the following is the easternmost division of the Indian Railways?
A)Rangiya
B)Tinsukia
C)Lumding
D)Katihar
Answer: Tinsukia
- Q. When a driver passing an automatic gate stop signal at ‘ON’ he must stop short of the gate of
A)25 meters
B)30 meters
C)45 meters
D)None of these
Answer: None of these
- Q. Which city is hosting the International Conference on Green Initiatives & Railway Electrification?
A)Guwahati
B)Kochi
C)Chennai
D)New Delhi
Answer: New Delhi
- Q. To apply for Line block, the notice shall be given to DRM not less than
A)12 hours
B)48 hours
C)24 hours
D)None of these
Answer: 24 hours
- Q. Competency certificate of the gateman of interlocked engineering gate is issued by
A)SSE/C & W
B)SSE/P.way
C)SSE/Sig.
D)None of these
Answer: SSE/P.way
- Q. The number of private number sheet is ________.
A)T/99 D
B)T/99 F
C)T/99 A
D)T/99 E
Answer: T/99 F
- Q. During total interruption of communication on signal line. The speed of LE to establish communication is ________ kmph during day and clear weather.
A)20
B)10
C)15
D)None of these
Answer: 15
- Q. Calling on signal shows ________ light in off position in two aspect signalling system.
A)Green
B)White
C)RED
D)Yellow
Answer: Yellow
- Q. When the points are set for main line, point indicator shows white target by day and ________ Light by night.
A)Yellow
B)Red
C)Green
D)White
Answer: White
- Q. A vehicle which can be bodily lifted off the line by ________ is a trolley
A)3 man
B)02 man
C)04 man
D)None of these
Answer: 04 man
- Q. Distant signal is a ________ signal.
A)Subsidiary
B)Permissive
C)Home
D)None of these
Answer: Permissive
- Q. If the IBS is defective and advanced starter is working, SM shall issue ________ authority with private number of next station to pass IBS.
A)T/369(4b)
B)T/369(3b)
C)T/369(2B)
D)T/369(5b)
Answer: T/369(3b)