Q. Maximum speed of trains during thick & foggy weather in absolute block system is ________ when signal is showing green.

Correct Answer

60

More Questions on Indian Railway

  • Q. When the Loco pilot should contact with SM on telephone while IBS in “ON” position?
    A)Immediate
    B)After 5 minutes
    C)After 2 minutes
    D)After 1 miutes in day and 2 minutes in night
    Answer: After 1 miutes in day and 2 minutes in night
  • Q. In the classification of A to R accidents, ________ and ‘o’ classes are not included.
    A)Both
    B)Minor
    C)Serious
    D)None of these
    Answer: Serious
  • Q. Consider the following statements with respect to the Railway Convention Committee: 1)The committee consists of members only from Lok Sabha 2)Railway Minister is the ex – officio chairman of Railway Convention Committee Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: Neither 1 nor 2
  • Q. Corridor block is mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. Station manager of a big station shall inspect the cabins at least once in ________.
    A)Thrice in a week.
    B)Once in a week
    C)Twice in a week
    D)None of these
    Answer: Once in a week
  • Q. Which is the India’s first double Decker train?
    A)Guwahati Thiruvananthapuram Express
    B)Ahmedabad - Mumbai Central Double Decker Express
    C)Samjhauta Express
    D)Howrah – Dhanbad Double Decker Express
    Answer: Howrah – Dhanbad Double Decker Express
  • Q. Duplicate signal is ________.
    A)Co-acting signal
    B)Home Signal
    C)Warner Signal
    D)None of these
    Answer: Co-acting signal
  • Q. Consider the following initiative with Ministries associated to them: 1)Project Swarna – Ministry of Railways 2)Project CHAMAN – Ministry of Agriculture 3)Project DARPAN – Ministry of Communications Which of the above is/are correct?
    A)Only 1 & 3
    B)Only 1 & 2
    C)Only 2 & 3
    D)1, 2 & 3
    Answer: 1, 2 & 3
  • Q. Max. Speed of special train with 132 tonne bogie well wagon shall be ________ km/h.
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. The banner flag is a ________
    A)Both of these
    B)Temporary stop signal
    C)Permanent stop signal
    D)None of these
    Answer: Temporary stop signal
  • Q. Shunting speed of 5 box wagons is ________ km/h.
    A)6
    B)2
    C)5
    D)8
    Answer: 2
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. During TFC in double line which authority to serve the driver for train operation?
    A)TC-602
    B)TC-1425
    C)TA-602
    D)TD-1425
    Answer: TC-602
  • Q. Engineering allowance, loco gain and traffic gain are mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. In case of ACP Guard shall proceed towards the front from ________ side.
    A)Back
    B)Left
    C)Right
    D)Noe of these
    Answer: Left
  • Q. Is general manager responsible for?
    A)Both railway Board and Railway Ministry
    B)Railway Board
    C)Railway Ministry
    D)None of these
    Answer: Railway Board
  • Q. In automatic block system SL, the signal that can be dispensed with is
    A)Automatic Stop signal
    B)Home
    C)Starter
    D)None of these
    Answer: Automatic Stop signal
  • Q. Matheran Hill Railway is located in which state of India?
    A)Odisha
    B)Himachal Pradesh
    C)Maharashtra
    D)Meghalaya
    Answer: Maharashtra
  • Q. Block overlap in multiple aspect signalling system is ________ meters.
    A)180
    B)200
    C)300
    D)208
    Answer: 180
  • Q. Record of caution order is kept for ________ months.
    A)9
    B)10
    C)5
    D)12
    Answer: 12