Q. How much block overlap is required at the station equipped with MACLS?

Correct Answer

180 meters

More Questions on Indian Railway

  • Q. Which railway zone has become the first Rail Zone in India with 100% LED Lighting at railway stations?
    A)South Western Railway
    B)North Eastern Railway
    C)South Central Railway
    D)North Central Railway
    Answer: South Central Railway
  • Q. During hand shunting only ________ Bogies can be hand shunted.
    A)3
    B)1
    C)2
    D)None of these
    Answer: 1
  • Q. In case of home signal defective the speed of the train while passing over the points shall not be more than ________ km/h.
    A)15 km
    B)18 km
    C)10 km
    D)20 km
    Answer: 15 km
  • Q. To admit the train on loop line, generally the far end points are to be ser for ________.
    A)Both
    B)Loop line
    C)Main line
    D)None of these
    Answer: Main line
  • Q. Night duty should not normally be performed by the running staff for more than ________ nights at a stretch.
    A)6
    B)10
    C)12
    D)None of these
    Answer: 6
  • Q. Over which of the following rivers is the world’s highest railway bridge in Kashmir being constructed?
    A)Sutlej
    B)Chenab
    C)Jhelum
    D)Indus
    Answer: Chenab
  • Q. Maximum speed of trains during thick & foggy weather in absolute block system is ________ when signal is showing green.
    A)50
    B)50
    C)40
    D)60
    Answer: 60
  • Q. Headquarters of which one among the following Railway Zones in India is situated at the highest elevation from the mean sea level?
    A)South Western Railway
    B)East Central Railway
    C)South Eastern Railway
    D)West Central Railway
    Answer: South Western Railway
  • Q. Booked speed of a train is ________ percent less than maximum permissible speed
    A)15
    B)5
    C)10
    D)20
    Answer: 10
  • Q. During TFC in single line section what authority to proceed will be served to driver of Dn train during return.
    A)TH-602
    B)T/A-602
    C)TG-602
    D)TB-602
    Answer: TH-602
  • Q. When a trolley is working on T/1518 during thick or foggy weather, the speed is
    A)10 kmph
    B)5 kmph
    C)8 kmph
    D)None of these
    Answer: 5 kmph
  • Q. In which of the following cities are located 3 zonal headquarters of Indian Railways?
    A)New Delhi
    B)Guwahati
    C)Mumbai
    D)Kolkata
    Answer: Kolkata
  • Q. In the event of an accident falling in more than one class it should be treated as an accident in the ________ class.
    A)Both
    B)Lowest
    C)Highest
    D)None of these
    Answer: Highest
  • Q. Isolation shall be provided at an interlocked station when the speed is
    A)Above 50 kmph
    B)50 kmph
    C)75 kmph
    D)None of these
    Answer: Above 50 kmph
  • Q. Normal condition of automatic stop signal is ________.
    A)Yellow
    B)Red
    C)Green
    D)None of these
    Answer: Green
  • Q. With respect to ‘Operating ratio’ in Railways, which of the following statement is/are correct? 1)The higher is the ‘Operating Ratio’; the better is the economic condition of railways. 2) ‘Operating ratio’ of Indian Railways is high on account of social service obligation imposed in Budget. Select the correct option from the codes given below
    A)Both 1 & 2
    B)Only 1
    C)Only 2
    D)Neither 1 nor 2
    Answer: Only 2
  • Q. Distance between outer and home signals on a double line is ________ meters.
    A)400
    B)900
    C)800
    D)700
    Answer: 400
  • Q. How many training institutions of Railways are in India?
    A)Five
    B)Three
    C)Four
    D)Six
    Answer: Five
  • Q. While protecting the material train, banner flag is placed at a distance of
    A)600
    B)400
    C)500
    D)800
    Answer: 600
  • Q. When the signal is blank in MACLS system, it is treated as showing ________ aspect.
    A)Defective
    B)Restricted
    C)Most restricted
    D)Noe of these
    Answer: Most restricted

Leave a Comment