Q. EMU train has ________ and automatic types of working brakes.

Correct Answer

EP Brakes

More Questions on Indian Railway

  • Q. Calling on signal shows ________ light in off position in two aspect signalling system.
    A)Green
    B)White
    C)RED
    D)Yellow
    Answer: Yellow
  • Q. Goods train without brake van shall not be run during ________.
    A)CCF
    B)BCF
    C)ACF
    D)None of these
    Answer: ACF
  • Q. The numbers of A, B and C coaches are 72, ________ and 76.
    A)71
    B)72
    C)70
    D)75
    Answer: 70
  • Q. Which authority shall be received to perform shunting beyond LSS at station of double line equipped with
    A)T/A 602
    B)T-806
    C)T/A 802
    D)T-806 A
    Answer: T-806
  • Q. It is the responsibility of SM to see that shunting is performed as per ________.
    A)G&R
    B)WTT
    C)SWR
    D)None of these
    Answer: SWR
  • Q. Maximum permissible speed is fixed by ________.
    A)MT
    B)CRS
    C)GM
    D)None of these
    Answer: CRS
  • Q. Isolation shall be provided at an interlocked station when the speed is
    A)Above 50 kmph
    B)50 kmph
    C)75 kmph
    D)None of these
    Answer: Above 50 kmph
  • Q. Speed of the last train during ACF on double line is ________ km/h.
    A)20/15/Walking
    B)25/10/Walking
    C)20/10/Walking
    D)None of these
    Answer: 25/10/Walking
  • Q. 400 meters beyond the home signal of a C’ class station is called as ________.
    A)Last stop signal
    B)Block section
    C)Overlapping block section
    D)None of these
    Answer: Overlapping block section
  • Q. In the enroute, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 90
  • Q. When was the nationalization of Indian Railways done?
    A)1951
    B)1952
    C)1950
    D)1954
    Answer: 1950
  • Q. New Humsafar Express, 3 – tier AC train was flagged off between which two locations on 2 June 2018?
    A)Agartala and Bengaluru
    B)Ajmer and Rameshwaram
    C)Gorakhpur and Anand Vihar
    D)Jodhpur and Bandra
    Answer: Jodhpur and Bandra
  • Q. Guard shall use ________ bell code to warn the motorman, if motorman violated the speed.
    A)0-00-00
    B)000-000
    C)00-00
    D)000-000-000
    Answer: 000-000
  • Q. Permission of ________ is required to work the material train in the night.
    A)DRM
    B)AOM
    C)DOM
    D)None of these
    Answer: DRM
  • Q. If the train passes through without headlight, SM shall give ________ bell code and advise the reason.
    A)0000-0
    B)000000-0
    C)00000-0
    D)0000-00
    Answer: 000000-0
  • Q. When the train has not cleared the fouling marks. Driver to give ________ whistle
    A)01 long
    B)03 long
    C)02 long
    D)None of these
    Answer: 03 long
  • Q. In TALQ signalling system, ________ signal will be treated as defective if home signal becomes defective.
    A)Hand
    B)Outer
    C)Call-On
    D)Non eof these
    Answer: Outer
  • Q. To admit the train on loop line, generally the far end points are to be ser for ________.
    A)Both
    B)Loop line
    C)Main line
    D)None of these
    Answer: Main line
  • Q. Which of the following is the largest zone in terms of route kilometers?
    A)Northern Railways
    B)Western Railways
    C)Eastern Railways
    D)Southern Railways
    Answer: Northern Railways
  • Q. Between which place station section is situated at double class B station, equipped with MACLS?
    A)FP to LSS
    B)Home signal to Ad starter
    C)BSLB to Ad. Starter
    D)A or B any one
    Answer: BSLB to Ad. Starter