Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph

Correct Answer

10

More Questions on Indian Railway

  • Q. When ISMD attached train is allowed to run through on PF line the speed must be
    A)10 kmph
    B)5 kmph
    C)8 kmph
    D)None of these
    Answer: 5 kmph
  • Q. When the engine is pushing a material train and BV is not leading, the speed shall not exceed.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)30 kmph
    Answer: 10 kmph
  • Q. Air pressure in the engine and brake van of a goods train with 58 N Boxes shall be 5.0 kg/cm2 and ________ respectively.
    A)4.5 kg/cm2
    B)4.1 kg/cm2
    C)4.2 kg/cm2
    D)4.7 kg/cm2
    Answer: 4.7 kg/cm2
  • Q. Number of the Nil caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 408
    D)None of these
    Answer: T/A 409
  • Q. The headquarters of Northern Railway is at
    A)Gorakhpur
    B)New Delhi
    C)Guwahati
    D)Mumbai (CST)
    Answer: New Delhi
  • Q. Colour of the semaphore distant signal is ________.
    A)Yellow
    B)Red
    C)White
    D)Green
    Answer: Yellow
  • Q. Interchange point of Central and Western railway is ________.
    A)Both
    B)Dadar
    C)Jalgaon
    D)None of these
    Answer: Both
  • Q. Where did Chapman form the committee?
    A)Edimbara
    B)Glassgo
    C)London
    D)Lords
    Answer: London
  • Q. Matheran Hill Railway is a narrow gauge heritage railway located in which state?
    A)Maharashtra
    B)Tamil Nadu
    C)Himachal Pradesh
    D)Meghalaya
    Answer: Maharashtra
  • Q. Block overlap in two aspect signalling system is ________ meters.
    A)400
    B)500
    C)600
    D)600
    Answer: 400
  • Q. In which Governor – General’s reign railway lines in India were established?
    A)Lord Kenning
    B)Lord William Bentick
    C)Lord Cornwallis
    D)Lord Dalhousie
    Answer: Lord Dalhousie
  • Q. Stop signal is to be passed in On position.
    A)T-806
    B)T-509
    C)T-369(3b)
    D)Simple memo
    Answer: T-369(3b)
  • Q. The maximum speed of the assistance train to be sent on T/A 602
    A)30 kmph
    B)10 kmph
    C)15 kmph
    D)40 kmph
    Answer: 15 kmph
  • Q. In the panel working for cancellation of route the number in the counter changes and white indication appears after
    A)50 seconds
    B)120 seconds
    C)90 seconds
    D)None of these
    Answer: 120 seconds
  • Q. Which of the following sectors are included as part of multi – modal logistics hubs in India? 1)Aviation 2)National Highways 3) Ports 4)Inland waterways 5)Railways Select the correct option from codes given below:
    A)1, 2, 3, 4 & 5
    B)Only 2, 3 & 4
    C)Only 2, 3, 4, 5
    D)Only 2, 3 & 5
    Answer: 1, 2, 3, 4 & 5
  • Q. Normally the train with hot axle is admitted on ________.
    A)Main Line
    B)Loop Line
    C)Siding Line
    D)None of these
    Answer: Main Line
  • Q. Reminder Caution Order is?
    A)T/B409
    B)T/409
    C)T/A409
    D)None of these
    Answer: T/B409
  • Q. No. of vehicles that can be attached to goods trains in rear of BV is
    A)2 bogie or its equivalent
    B)2 bogies
    C)1 bogies
    D)None of these
    Answer: 2 bogie or its equivalent
  • Q. If distant signal show green accepts, which indication is shown for loco pilot on single distant?
    A)Receive on loop line
    B)Run through from station
    C)Receive of Main line
    D)None of these
    Answer: Run through from station
  • Q. For work of long duration, the stop indicator must be erected at not less than
    A)40
    B)30
    C)50
    D)45
    Answer: 30

Leave a Comment