Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
A)Both 1 & 2 B)1 Only C)2 Only D)Neither 1 nor 2
Answer: 2 Only
Q. ndian Railway’s Jamalpur Workshop is located at?
A)Bihar B)West Bengal C)Orissa D)Uttar Pradesh
Answer: Bihar
Q. Max. Speed of special train with 132 tonne bogie well wagon shall be ________ km/h.
A)35 B)20 C)25 D)30
Answer: 30
Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of FP pressure in the brake van.
A)6.8 B)7.8 C)5.8 D)4.7
Answer: 4.7
Q. Yearly coaching stock census is taken on ________.
A)31st January B)31st December C)31st October D)31st March
Answer: 31st October
Q. The turning out time of an MRV Spl. When in is kept in one exit siding is ________ minutes.
A)20 B)25 C)15 D)None of these
Answer: 25
Q. What is the speed of A class ODC in BG?
A)40 kmph B)15 kmph C)25 kmph D)Normal speed
Answer: Normal speed
Q. There is insufficient vacuum/pressure in engine.
A)_____00 B)___0___ C)0___0 D)00-----
Answer: 00-----
Q. Loco Pilot shall sound ________ whistle if SM do not exchange hand signals.
A)One short B)Two short C)Three short D)Noen of these
Answer: Two short
Q. Rake link book-let is prepared by COM and ________.
A)DPO B)CPTM C)CPO D)None of these
Answer: CPTM
Q. Which is the least signalto be installed on C class stations in multiple aspect signalling?
A)Warner, Home B)Outer, Home C)Distant, Home D)Distant, Home, Starter
Answer: Distant, Home
Q. Caution and Termination indication Boards will be fixed from the bridge or vulnerable places at
A)1000 meters B)400 meters C)600 meters D)None of these
Answer: 600 meters
Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.
A)25 B)20 C)15 D)None of these
Answer: 25
Q. The world’s highest railway bridge will come up over which Indian River?
A)Ganga B)Narmada C)Godavari D)Chenab
Answer: Chenab
Q. Over which of the following rivers is the world’s highest railway bridge in Kashmir being constructed?
A)Sutlej B)Chenab C)Jhelum D)Indus
Answer: Chenab
Q. Number of the caution order is ________
A)T/410 B)T/409 C)T/408 D)None of these
Answer: T/409
Q. Guard shall exchange alright hand signal from ________ side while the train is started from the station.
A)Both B)Path C)Platform D)None of these
Answer: Platform
Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5 B)10 C)20 D)None of these
Answer: 10
Q. Tower wagon shall run as per the rules of working of ________.
A)Passengers B)Wagon C)Train D)None of these
Answer: Train
Q. Danger zone in 25 KV AC traction is ________ meters from OHE.