Q. Diesel locomotives are built in?

Correct Answer

Varanasi

More Questions on Indian Railway

  • Q. For ‘B’ Class ISMD load, permission must be granted by
    A)CE
    B)DRM
    C)CRS
    D)None of these
    Answer: CE
  • Q. Competency certificate of the gateman of interlocked engineering gate is signed by
    A)Both
    B)SSE/P.way
    C)SSE/Sig.
    D)None of these
    Answer: Both
  • Q. D class station board is placed ________ meters from the end of the platform.
    A)600
    B)400
    C)500
    D)800
    Answer: 500
  • Q. When baking a train from one line to the other line, it is necessary to present the train guard.
    A)Break van
    B)Point
    C)Station
    D)Any Place
    Answer: Break van
  • Q. SM shall inspect the personal store of Guard once in ________ months.
    A)6
    B)2
    C)4
    D)3
    Answer: 3
  • Q. TSL is started between those two stations at which cross over facility are available and
    A)D Class/IBC
    B)A Class/IBS
    C)C Class/IBS
    D)None of these
    Answer: C Class/IBS
  • Q. At least how far will the final detonator be used to defend the train in broad gauge?
    A)820 meters
    B)180 meters
    C)600 meters
    D)1220 meters
    Answer: 1220 meters
  • Q. EMU train has ________ type of couplings.
    A)Shakuu
    B)Shakau
    C)Shakua
    D)None of these
    Answer: Shakau
  • Q. Hand shunting is performed at speed not exceeding
    A)05 kmph
    B)10 kmph
    C)08 kmph
    D)None of these
    Answer: 05 kmph
  • Q. Rake link book-let is prepared by COM and ________.
    A)DPO
    B)CPTM
    C)CPO
    D)None of these
    Answer: CPTM
  • Q. During prolonged failure of signals in automatic section, ________ authority is issued.
    A)T/C 912
    B)T/B 912
    C)T/D 912
    D)T/A 912
    Answer: T/D 912
  • Q. To send the assisting engine into obstructed block section T/A 602 authority is issued ________ and the speed of engine shall be ________.
    A)15/10 km/h
    B)25/10 km/h
    C)20/10 km/h
    D)None of these
    Answer: 15/10 km/h
  • Q. Apart from the regular store, Guard of material train must also possess ________.
    A)Third aid box
    B)First aid box
    C)Second aid box
    D)None of these
    Answer: First aid box
  • Q. Number of the Nil caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 408
    D)None of these
    Answer: T/A 409
  • Q. Time taken by train running at booked speed is called as ________.
    A)Normal running time
    B)Long time
    C)Minimum running time
    D)None of these
    Answer: Normal running time
  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. In which city is the Wheel and Axle Plant of the Indian Railways located?
    A)Bangalore
    B)Kapurthala
    C)Varanasi
    D)Rae Barelly
    Answer: Bangalore
  • Q. At the starting station, passenger train must have ________ % of brake power.
    A)90
    B)75
    C)50
    D)100
    Answer: 100
  • Q. In which class overlapping section is found?
    A)C-Class
    B)A-Class
    C)B-Class
    D)D-Class
    Answer: C-Class
  • Q. With reference to headquarters of the various Railway zones, consider the following matches: North Eastern → Guwahati Central → Bhopal Western → Mumbai Which of the above is / are correct matches:
    A)Only 2 & 3
    B)Only 1
    C)Only 1 & 2
    D)Only 3
    Answer: Only 3