Q. Competency certificate of the gateman of non- interlocked engineering gate is signed by ________.

Correct Answer

PWI

More Questions on Indian Railway

  • Q. Joint sighting committee shall inspect the visibility of signals once in
    A)6 months
    B)A month
    C)3 months
    D)None of these
    Answer: 3 months
  • Q. During shunting, outer, home and ________ signals are not taken off.
    A)Both
    B)Last stop signal
    C)First stop signal
    D)None of these
    Answer: First stop signal
  • Q. For disconnection of points S&T official must issue form ________
    A)T/B 351
    B)T/351
    C)T/A 351
    D)None of these
    Answer: T/351
  • Q. Shatabdi Express train was started in ________.
    A)1990
    B)1984
    C)1988
    D)1985
    Answer: 1988
  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. When water level is just above top of rail speed of electric locomotive shall apply ?
    A)15 kmph
    B)5 kmph
    C)10 kmph
    D)20 kmph
    Answer: 10 kmph
  • Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
    A)Sectional
    B)Corner
    C)Warner
    D)None of these
    Answer: Warner
  • Q. When did the first ignition engine develop?
    A)1900
    B)1890
    C)1892
    D)1904
    Answer: 1892
  • Q. While passing through the non-interlocked points, maximum speed of the train shall be ________ km/h.
    A)15 km
    B)8 km
    C)10 km
    D)20 km
    Answer: 15 km
  • Q. Track maintenance machine is permitted to work during
    A)Day clear weather
    B)Day
    C)Day and Night
    D)None of these
    Answer: Day and Night
  • Q. On double line, when a running line is blocked by stabled load , the point to be set against are
    A)Advance point
    B)Either side points
    C)Rear points
    D)None of these
    Answer: Rear points
  • Q. Mixed and Goods trains worked with vacuum throughout, the following number of vehicles can be attached in rear of BV.
    A)Not more than two bogies or their equivalent
    B)Two Bogies
    C)04 four wheelers only
    D)None of these
    Answer: Not more than two bogies or their equivalent
  • Q. Which of the following stations has all the three gauges viz. broad, metre and narrow?
    A)Shimla
    B)Lucknow
    C)Chandigarh
    D)Siliguri
    Answer: Siliguri
  • Q. Train is to be passed through loop line.
    A)30 kmph
    B)15 kmph
    C)25 kmph
    D)Normal speed
    Answer: 15 kmph
  • Q. Interchange point of Central and Western railway is ________.
    A)Both
    B)Dadar
    C)Jalgaon
    D)None of these
    Answer: Both
  • Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
    A)30 kmph
    B)Normal speed
    C)15 kmph
    D)60 kmph
    Answer: 60 kmph
  • Q. Authority to pass IBS has been issued from station in rear.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: 15 kmph
  • Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
    A)Walkie-Talkie
    B)Walkie
    C)VHF
    D)None of these
    Answer: Walkie-Talkie
  • Q. Loss of Railway property of ________ is treated as serious accident.
    A)75 Lakhs
    B)More than 50 lakhs
    C)01 crore
    D)More than 02 crore
    Answer: More than 02 crore
  • Q. Maximum speed of trains during thick & foggy weather in absolute block system is ________ when signal is showing green.
    A)50
    B)50
    C)40
    D)60
    Answer: 60