Q. Competency certificate of the gateman of non- interlocked engineering gate is signed by ________.

Correct Answer

PWI

More Questions on Indian Railway

  • Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?
    A)30 kmph
    B)Normal speed
    C)15 kmph
    D)60 kmph
    Answer: 60 kmph
  • Q. During single line working on double line in automatic area the speed of all train running in wrong direction shall not exceed
    A)10 kmph
    B)25 kmph
    C)15 kmph
    D)None of these
    Answer: 25 kmph
  • Q. The speed of shunting is ________.
    A)10 kmph
    B)15 kmph
    C)20 kmph
    D)None of these
    Answer: 15 kmph
  • Q. What is the name of the first train of Indian Railways handed over to private players for operation?
    A)Karnataka Express
    B)Tejas Express
    C)Shatabdi Express
    D)Duronto Express
    Answer: Tejas Express
  • Q. Mission PACE deals with
    A)Fast Ticketing System
    B)Protection of nature
    C)Help Customers
    D)Quality of Goods and Services
    Answer: Quality of Goods and Services
  • Q. The Ministry of Railways has signed MoU with which Union Ministry to augment services in Railway hospitals?
    A)Ministry of Social Justice and Empowerment
    B)Ministry of Women and Child Development
    C)Ministry of Drinking Water and Sanitation
    D)Ministry of AYUSH
    Answer: Ministry of AYUSH
  • Q. How many training institutions of Railways are in India?
    A)Five
    B)Three
    C)Four
    D)Six
    Answer: Five
  • Q. Maximum number of explosive unit wagons in a mixed train is
    A)3
    B)5
    C)7
    D)None of these
    Answer: 3
  • Q. Loss of railway property of Rs. more than 2 Crores is treaed as ________ accident.
    A)Both
    B)Minor
    C)Serious
    D)None of these
    Answer: Serious
  • Q. There is insufficient vacuum/pressure in engine.
    A)_____00
    B)___0___
    C)0___0
    D)00-----
    Answer: 00-----
  • Q. In Automatic areas when there are no signals and communication, the speed of the train is ________ kmph while working on T/B 912 during day.
    A)15
    B)25
    C)20
    D)10
    Answer: 25
  • Q. Where is the information about the Ruling Gradient of a section?
    A)G & SR
    B)SWR
    C)WTT
    D)Operating Manual
    Answer: WTT
  • Q. At station which signal will be taken off for block line?
    A)Shut
    B)Repeating
    C)Calling on
    D)No Signal
    Answer: No Signal
  • Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 15 kmph
  • Q. Number of the Reminder caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 409
    D)None of these
    Answer: T/B 409
  • Q. Indian railways has installed Asia’s largest Solid State Interlocking (SSI) system in which state?
    A)Madhya Pradesh
    B)Tamil Nadu
    C)West Bengal
    D)Punjab
    Answer: West Bengal
  • Q. ________ number of Guard wagons shall be attached in either direction of explosive wagons.
    A)3 - 3
    B)1 - 1
    C)2 - 2
    D)4 - 4
    Answer: 2 - 2
  • Q. A lorry shall be protected by banner flags and detonators if it remains stationary within the station yard for more than
    A)20 meters
    B)15 meters
    C)10 meters
    D)None of these
    Answer: 15 meters
  • Q. Hand shunting of vehicles is prohibited in gradient
    A)1 - 400 or steeper
    B)1 - 260
    C)1 - 400
    D)None of these
    Answer: 1 - 400 or steeper
  • Q. Water over track is 90 mm.
    A)15 kmph
    B)8 kmph
    C)10 kmph
    D)25 kmph
    Answer: 10 kmph