Q. Colour of the semaphore shunt signal is ________.

Correct Answer

Red

More Questions on Indian Railway

  • Q. Gateman competency certificate of interlocked traffic gate is signed by TI and SE (Sig) and counter signed by ________.
    A)DOM
    B)AOM(G)
    C)AOM(Chg)
    D)None of these
    Answer: AOM(G)
  • Q. When the platform level is ________ MM and more second arriving train shall not be received and berthed on non platform line directly.
    A)650
    B)700
    C)725
    D)760
    Answer: 760
  • Q. Which whistle code shall be used by loco pilot while Guard’s assistance is required?
    A)Three short
    B)Long continue
    C)Intermediate long continue
    D)Three long
    Answer: Three short
  • Q. Yearly goods stock census is taken on ________.
    A)30st November
    B)31st December
    C)31st October
    D)31st March
    Answer: 30st November
  • Q. While receiving train on an obstructed line and danger signal must be shown to LP at
    A)40 meters from obstruction
    B)45 meters
    C)30 meters
    D)None of these
    Answer: 45 meters
  • Q. When was the first train steamed off in India?
    A)1875
    B)1848
    C)1853
    D)1880
    Answer: 1853
  • Q. In case of ACP, Assistant Loco Pilot shall proceed towards the rear from ________ side.
    A)Back
    B)Left
    C)Right
    D)Noe of these
    Answer: Right
  • Q. Target time for departing ART during day is 30 minutes and during night is ________ minutes.
    A)60
    B)40
    C)50
    D)45
    Answer: 45
  • Q. On which speed BG engine shall be run while speedometer is defective during run?
    A)25 kmph
    B)50 kmph
    C)40 kmph
    D)Maximum 10% less of MPS
    Answer: Maximum 10% less of MPS
  • Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: 2 Only
  • Q. In the work of short duration the first flag man to the approaching train must started at not less than ________ Metres from the last detonator.
    A)145
    B)45
    C)90
    D)150
    Answer: 45
  • Q. Signal overlap at a terminal station with multi aspect colour light signalling is ________.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. What is the normal aspect of an Automatic stop signal on double line Automatic section?
    A)DOUBLE YELLOW
    B)RED
    C)GREEN
    D)YELLOW
    Answer: GREEN
  • Q. When a Goods train is working without guard or BV or Guard and BV the speed is
    A)10
    B)25
    C)20
    D)None of these
    Answer: 25
  • Q. Where is the Research, Design and Standard Organization situated?
    A)Pune
    B)Lucknow
    C)Bangalore
    D)New Delhi
    Answer: Lucknow
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. The largest national enterprise of India is
    A)Airways
    B)Indian Railway
    C)Indian Shipyard
    D)Waterways
    Answer: Indian Railway
  • Q. If outside the station limits the distance between two trains is ________ in averted collusion, such occurrence may not be treated as an averted collision.
    A)100 meter
    B)200 meter
    C)250 meter
    D)400 meters and more
    Answer: 400 meters and more
  • Q. Loco pilot must have ________ sets of spectacles in his personal store.
    A)Three
    B)Two
    C)One
    D)None of these
    Answer: Two
  • Q. On which time the departure signal shall be taken off for run through train passing via loop line?
    A)After entering in loop line
    B)Before entering at station
    C)After stopped at station
    D)Before 10 minutes from expected arrival
    Answer: Before 10 minutes from expected arrival