Q. Colour of the semaphore shunt signal is ________.

Correct Answer

Red

More Questions on Indian Railway

  • Q. Maximum speed of B’ class ODC is ________ km/h.
    A)60
    B)50
    C)40
    D)75
    Answer: 40
  • Q. Hand shunting speed is ________
    A)8 kmph
    B)5 kmph
    C)10 kmph
    D)None of these
    Answer: 5 kmph
  • Q. All automatic stop signals will have ________ marker plate.
    A)G
    B)B
    C)A
    D)None of these
    Answer: A
  • Q. Competency certificate of the gateman of interlocked engineering gate is signed by
    A)Both
    B)SSE/P.way
    C)SSE/Sig.
    D)None of these
    Answer: Both
  • Q. If the Distant signal of a Gate becomes defective in off condition, ________ is issued to Loco Pilot from the station in rear.
    A)Nil caution order
    B)Caution order
    C)Reminder order
    D)None of these
    Answer: Caution order
  • Q. To receive a train on unsignalled line, ________ authority is issued.
    A)T/369(4b) Pilot in MEMU
    B)T/369(3b) Pilot in MEMO
    C)T/369(2B) Pilot in MEMO
    D)T/369(5b) Pilot in MEMU
    Answer: T/369(3b) Pilot in MEMO
  • Q. Percentage of in operative cylinders that can be attached in goods train is
    A)5%
    B)15%
    C)10%
    D)None of these
    Answer: 15%
  • Q. Block overlap in two aspect signalling system is ________ meters.
    A)400
    B)500
    C)600
    D)600
    Answer: 400
  • Q. To attach the 12 coach EMU rake, ________ units are to be attached.
    A)8
    B)5
    C)6
    D)4
    Answer: 4
  • Q. The headquarters of South Railways is situated at
    A)Delhi
    B)Kolkata
    C)Chennai
    D)Mumbai
    Answer: Chennai
  • Q. Flasher light is of ________ colour.
    A)Green
    B)Red
    C)Amber
    D)None of these
    Answer: Amber
  • Q. What is the maximum speed over facing point in non-interlocked station?
    A)15 kmph
    B)50 kmph
    C)75 kmph
    D)25 kmph
    Answer: 15 kmph
  • Q. Track maintenance machine is permitted to work during
    A)Day clear weather
    B)Day
    C)Day and Night
    D)None of these
    Answer: Day and Night
  • Q. During thick & foggy weather, line must be clear upto ________ for granting line clear at a B’ class station in TALQ signalling system on Double line.
    A)Shunt signal
    B)Calling-on Signal
    C)Home Signal
    D)None of these
    Answer: Home Signal
  • Q. Night duty should not normally be performed by the running staff for more than ________ nights at a stretch.
    A)6
    B)10
    C)12
    D)None of these
    Answer: 6
  • Q. Minimum distance apart of refuges in Tunnels in BG is (at present)
    A)200 meters
    B)100 meters
    C)150 meters
    D)None of these
    Answer: 100 meters
  • Q. Where is RDSO Situated.
    A)Chennai
    B)Vadodara
    C)Lucknow
    D)New Delhi
    Answer: Lucknow
  • Q. It is a Python Rake.
    A)15 kmph
    B)60 kmph
    C)25 kmph
    D)Normal speed
    Answer: 60 kmph
  • Q. Consider the following steps in Budget Procedure in India: 1)The demands for grants of various ministries and departments including railways are considered by the concerned standing committees 2)Broad contours of the budget and the principles and policies underlying it are discussed. 3)A cut motion is moved in the Lok Sabha 4)Budget is presented in the House. Which among the following is the correct sequence of the above steps?
    A)4 2 1 3
    B)1 2 3 4
    C)1 2 4 3
    D)3 1 4 2
    Answer: 4 2 1 3
  • Q. How much overlap is required to be off an Automatic stop signal on double line Automatic block system?
    A)90 meters
    B)180 meters
    C)120 meters
    D)Zero
    Answer: Zero