Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.

Correct Answer

TI

More Questions on Indian Railway

  • Q. Time taken by train running at MPS is called as ________.
    A)Normal running time
    B)Long time
    C)Minimum running time
    D)None of these
    Answer: Minimum running time
  • Q. Caution indication board will be provided at ________ meters from the bridge or vulnerable places.
    A)600
    B)500
    C)400
    D)800
    Answer: 600
  • Q. During single line working of DL the speed of the first train is ________ kmph
    A)15
    B)25
    C)20
    D)None of these
    Answer: 25
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. Which type Authority to proceed shall be used at without starter signal station on single line?
    A)Any one
    B)Non Tangible
    C)Tangible
    D)None of these
    Answer: Tangible
  • Q. On which authority advance starter may be passed during shunting operation in its on position?
    A)On hand signal
    B)T-369(3b)
    C)Written memo
    D)T-806
    Answer: T-806
  • Q. If the driver does not received all right signal from the guard, he must call for is by giving.
    A)On long
    B)Two sharp whistles
    C)One long one short.
    D)None of these
    Answer: Two sharp whistles
  • Q. Fog signal man must be on ________ Hrs duty.
    A)5
    B)3
    C)4
    D)None of these
    Answer: 3
  • Q. The monies in the National Investment Fund can be used for ________: 1. Recapitalization of public sector banks 2. Purchasing the shares of CPSEs 3. Towards operating expenses of Indian Railways 4. Social Overheads such as building schools, toilets etc. Select the correct option from the codes given below:
    A)Only 1, 2 & 4
    B)Only 1, 2 & 3
    C)Only 2, 3 & 4
    D)Only 1 & 2
    Answer: Only 1 & 2
  • Q. Speed of second train during temporary single line working is ________.
    A)Both
    B)Normal
    C)Abnormal
    D)None of these
    Answer: Normal
  • Q. The speed of Engine on Baharline is ________ kmph
    A)16
    B)10
    C)15
    D)None of these
    Answer: 10
  • Q. On which speed BG engine shall be run while speedometer is defective during run?
    A)25 kmph
    B)50 kmph
    C)40 kmph
    D)Maximum 10% less of MPS
    Answer: Maximum 10% less of MPS
  • Q. Consider the following statements with regard to ‘Ad Hoc’ Committees of the parliament: 1)They are temporary in nature and appointed for a specific purpose 2)Railway Convention Committee is an ad hoc committee Which among the above statements is / are correct?
    A)Both 1 & 2 are correct
    B)Only 1 is correct
    C)Only 2 is correct
    D)Neither 1 nor 2 is correct
    Answer: Both 1 & 2 are correct
  • Q. Track maintenance machine is permitted to work during
    A)Day clear weather
    B)Day
    C)Day and Night
    D)None of these
    Answer: Day and Night
  • Q. What is the means of EA in WTT?
    A)Extra recovery time
    B)Extra allowances
    C)Engineering allowances
    D)None of these
    Answer: Engineering allowances
  • Q. The driver shall sound the following whistle to indicate that the fouling marks is not clear
    A)One long
    B)Three long
    C)Short one long
    D)None of these
    Answer: Three long
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. When the rail failure is rectified by the train can pass at speed
    A)30 kmph
    B)20 kmph
    C)25 kmph
    D)None of these
    Answer: 30 kmph
  • Q. The distance between two automatic signals is normally
    A)3 km
    B)2 km
    C)1 km
    D)None of these
    Answer: 1 km
  • Q. Point indicator is provided to indicate ________.
    A)Both
    B)Points
    C)Bar
    D)None of these
    Answer: Points

Leave a Comment