Q. ________ must be issued during thick or foggy weather.

Correct Answer

Caution Order

More Questions on Indian Railway

  • Q. When was the Jammu City appeared on the map of Indian Railway?
    A)1967
    B)1956
    C)1963
    D)1965
    Answer: 1965
  • Q. In two aspects areas where shunting in the face of approaching train is not permitted, shunting can be permitted during ________ and under certain conditions (UP to FSS).
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. When was the North-Eastern frontier Railway (NFR) established?
    A)2nd January, 1956
    B)15th January, 1958
    C)15th January, 1955
    D)14th April, 1952
    Answer: 15th January, 1958
  • Q. In how many zones Indian Railway has been divided?
    A)17
    B)14
    C)16
    D)20
    Answer: 17
  • Q. Which of the following is / are Union Subjects as per seventh schedule of the Constitution of India? 1)Armed Forces 2)Paramilitary Forces 3)Railway Police 4)Cantonment Areas Select the correct option from the codes given below:
    A)Only 1, 2 & 4
    B)Only 1 & 2
    C)Only 1, 2 & 3
    D)1, 2, 3 & 4
    Answer: Only 1, 2 & 4
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. During TFC in double line which authority to serve the driver for train operation?
    A)TC-602
    B)TC-1425
    C)TA-602
    D)TD-1425
    Answer: TC-602
  • Q. Joint sighting committee shall inspect the visibility of signals once in
    A)6 months
    B)A month
    C)3 months
    D)None of these
    Answer: 3 months
  • Q. The distance between two automatic signals is normally
    A)3 km
    B)2 km
    C)1 km
    D)None of these
    Answer: 1 km
  • Q. Which research arm of Indian Railways has launched “New Online Vendor Registration System”?
    A)National Academy of Indian Railways
    B)Indian Railway Institute of Signal Engineering and Telecommunication
    C)Research Designs and Standards Organisation
    D)Indian Railway Service of Electrical Engineers
    Answer: Research Designs and Standards Organisation
  • Q. Station Master shall give line clear with ________ while granting line clear.
    A)Calling-on
    B)Shunt signal
    C)Private No.
    D)None of these
    Answer: Private No.
  • Q. When a motor trolley is in charge of office, the motor trolley can go upto outer most facing points after waiting for ________ minutes.
    A)20
    B)10
    C)15
    D)25
    Answer: 10
  • Q. Passenger warning board is placed at a distance of ________ meters from the first stop signal.
    A)1500
    B)1200
    C)1000
    D)1800
    Answer: 1000
  • Q. In case of train parting ________ bell code is given on block instrument.
    A)000000-000
    B)00000-0
    C)000000-0
    D)0000-00
    Answer: 000000-000
  • Q. Which whistle code shall be used by loco pilot while Guard’s assistance is required?
    A)Three short
    B)Long continue
    C)Intermediate long continue
    D)Three long
    Answer: Three short
  • Q. Loco pilot must have ________ sets of spectacles in his personal store.
    A)Three
    B)Two
    C)One
    D)None of these
    Answer: Two
  • Q. Minimum depth of space for wheel flange from rail level in BG is
    A)3"
    B)2"
    C)1 (1/2)"
    D)None of these
    Answer: 1 (1/2)"
  • Q. In automatic block system SL, the minimum equipment of signal shall be
    A)Home, Starter, Advance Starter
    B)Home, Starter
    C)Distance Home Starter
    D)None of these
    Answer: Home, Starter
  • Q. Trap indicator is provided to indicate ________.
    A)Provision Switch
    B)Indication Switch
    C)Derailing switch
    D)None of these
    Answer: Derailing switch
  • Q. A vehicle which can be bodily lifted off the line by ________ is a trolley
    A)3 man
    B)02 man
    C)04 man
    D)None of these
    Answer: 04 man