- Q. The form number of authority to proceed without line clear is ________.
A)T/B1408
B)T/1408
C)T/A1408
D)None of these
Answer: T/1408
- Q. Signal that controls the entry of trains into the block section in advance is called as
A)Last Stop signal
B)Fisrt Stop signal
C)Stop signal
D)None of these
Answer: Last Stop signal
- Q. Normally maximum gradient in station yards in BG is (at present)
A)1 in 1000
B)1 in 260
C)1 - 400
D)None of these
Answer: 1 - 400
- Q. At A class station, Neutral zone is the portion between starter and ________ signal.
A)Home signal
B)Advance starter
C)Starter
D)None of these
Answer: Advance starter
- Q. The first officer of the ________ department to arrive or present shall be responsible for the marshaling of the BD Special.
A)C & W
B)Engineering
C)Mechanical
D)None of these
Answer: Mechanical
- Q. Speed of the following tower wagon is ________ km/h.
A)9
B)10
C)8
D)4
Answer: 8
- Q. Knowledge of subsidiary rules is examined by ________ if train working staff of another Railway is required to work on our Railway.
A)LI
B)TI
C)CI
D)None of these
Answer: TI
- Q. How an automatic stop signal can be recognized?
A)Eliminated A marker
B)A marker on white disk
C)No mark
D)Four aspects
Answer: A marker on white disk
- Q. Motor vehicle in closed wagon shall be attached ________ position from engine on a passenger train.
A)Third
B)First
C)Second
D)None of these
Answer: Third
- Q. Passenger warning board is placed at a distance of ________ meters from the first stop signal.
A)1500
B)1200
C)1000
D)1800
Answer: 1000
- Q. Second train during all communication failure shall be dispatched after an interval of
A)35
B)20
C)25
D)30
Answer: 30
- Q. The largest national enterprise of India is
A)Airways
B)Indian Railway
C)Indian Shipyard
D)Waterways
Answer: Indian Railway
- Q. Signal has extinguished.
A)------00
B)___0___
C)0___0
D)00___
Answer: ------00
- Q. Your train is first during TSL on double line.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 25 kmph
- Q. When the section is occupied, the arrow indication in the panel in Twin single line working will be
A)No light
B)White
C)Red
D)None of these
Answer: Red
- Q. If the signal is continuously bobbing/flickering, the signal is treated as showing ________ aspect.
A)Rectified
B)Most Restrictive
C)Restrictive
D)None of these
Answer: Most Restrictive
- Q. What is the position of the Indian Railway in the world according to the length of rail lines?
A)Third
B)First
C)Second
D)Fourth
Answer: Fourth
- Q. The Rangpo – Sivok Railway line, connects which among the following two states of India?
A)West Bengal ↔ Tripura
B)Arunachal Pradesh ↔ Tripura
C)Sikkim ↔ West Bengal
D)Arunachal Pradesh ↔ Assam
Answer: Sikkim ↔ West Bengal
- Q. Which of the following zones administers the Matheran Hill Railway?
A)Central Railways
B)Konkan Railways
C)Western Railways
D)Southern Railways
Answer: Central Railways
- Q. Hand shunting of wagons is totally prohibited in gradients
A)1 in 260
B)1 in 400 OR Steeper
C)ST 1- IN 400
D)None of these
Answer: 1 in 400 OR Steeper