Q. ________ must be issued during thick or foggy weather.

Correct Answer

Caution Order

More Questions on Indian Railway

  • Q. If the motorman of EMU passes the automatic stop signal at ON, he shall proceed at a speed of 15/8 km/h and stop the train before ________ meters of the obstruction on the track.
    A)80
    B)70
    C)75
    D)85
    Answer: 75
  • Q. Trap indicator is provided to indicate ________.
    A)Provision Switch
    B)Indication Switch
    C)Derailing switch
    D)None of these
    Answer: Derailing switch
  • Q. P marker is provided for a
    A)Semaphore warner
    B)Colour light distance
    C)Semaphore distant
    D)None of these
    Answer: Colour light distance
  • Q. Gorakhpur which has the longest railway platform in the world is located in which of the following states?
    A)Uttar Pradesh
    B)Odisha
    C)West Bengal
    D)Chhattisgarh
    Answer: Uttar Pradesh
  • Q. passing through station during day when running without brakevan and tail board.
    A)25 kmph
    B)10 kmph
    C)20 kmph
    D)Normal speed
    Answer: 20 kmph
  • Q. To receive a train on unsignalled line, ________ authority is issued.
    A)T/369(4b) Pilot in MEMU
    B)T/369(3b) Pilot in MEMO
    C)T/369(2B) Pilot in MEMO
    D)T/369(5b) Pilot in MEMU
    Answer: T/369(3b) Pilot in MEMO
  • Q. Which of the following is India’s first green railway corridor?
    A)Chennai to Manamadurai
    B)Barmer to Munawab
    C)Manamadurai to Rameswaram
    D)Puri to Visakhapatnam
    Answer: Manamadurai to Rameswaram
  • Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 15 kmph
  • Q. Loco Pilot shall sound _________ whistle to acknowledge the Guard hand signal.
    A)Three Long
    B)One Long
    C)Two Long
    D)None of these
    Answer: One Long
  • Q. If the passenger train is not arrived ________ minutes beyond its normal running time, it is treated as delayed train.
    A)4
    B)10
    C)9
    D)3
    Answer: 10
  • Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
    A)Both
    B)Temporary Working Order.
    C)Permanent working order.
    D)None of these
    Answer: Temporary Working Order.
  • Q. All the authorities related to TSL working are examined by TI and its report is submitted to DRM within ________ days of resumption of normal working.
    A)10
    B)7
    C)9
    D)15
    Answer: 7
  • Q. Maximum number of explosive unit wagons in a mixed train is
    A)3
    B)5
    C)7
    D)None of these
    Answer: 3
  • Q. Shunting restrictions of station is written in ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: SWR
  • Q. EMU trains of harbour line has ________ number of wooden wedges.
    A)6
    B)2
    C)4
    D)8
    Answer: 4
  • Q. In the work of short duration the first flag man to the approaching train must started at not less than ________ Metres from the last detonator.
    A)145
    B)45
    C)90
    D)150
    Answer: 45
  • Q. When unsafe condition of river bund is reported. CO to be issued for speed for day is
    A)20 kmph
    B)10 kmph
    C)15 kmph
    D)None of these
    Answer: 15 kmph
  • Q. In the event of an accident falling in more than one class it should be treated as an accident in the ________ class.
    A)Both
    B)Lowest
    C)Highest
    D)None of these
    Answer: Highest
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
    A)LI
    B)TI
    C)CI
    D)None of these
    Answer: TI