More Questions on Indian Railway
- Q. Competency certificate of the gateman of interlocked engineering gate is signed by
A)Both
B)SSE/P.way
C)SSE/Sig.
D)None of these
Answer: Both
- Q. Not more than ________ persons including trollyman shall go on a trolly.
A)9
B)10
C)3
D)4
Answer: 10
- Q. Derailment will come under accident class ________.
A)C
B)A
C)B
D)D
Answer: D
- Q. When was the Central Railway established?
A)14th April 1951
B)5th Nov 1951
C)14th Nov 1951
D)16th August, 1951
Answer: 5th Nov 1951
- Q. When was the North-Eastern frontier Railway (NFR) established?
A)2nd January, 1956
B)15th January, 1958
C)15th January, 1955
D)14th April, 1952
Answer: 15th January, 1958
- Q. When a stream engine is running tender foremost the speed shall not exceed ________.
A)30 kmph
B)40 kmph
C)20 kmph
D)None of these
Answer: 40 kmph
- Q. Railway staff collage is situated at ________.
A)Chennai
B)Vadodara
C)Kanyakumari
D)New Delhi
Answer: Vadodara
- Q. BSLB determines the limits of block section and ________ .
A)Station Limit
B)Block Section
C)Station Section
D)None of these
Answer: Station Section
- Q. Authority to pass IBS has been issued from station in rear.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 15 kmph
- Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
A)Both 1 & 2
B)1 Only
C)2 Only
D)Neither 1 nor 2
Answer: 2 Only
- Q. Approved special instructions are issued by ________.
A)PCOM
B)CRS
C)MT
D)None of these
Answer: CRS
- Q. Termination indication boards post will be pointed alternatively black and white with ________ CM high bands.
A)15
B)20
C)25
D)30
Answer: 30
- Q. Load table is mentioned in the ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: WTT
- Q. Shunting to be done in D/L block section
A)T-806
B)PLCT
C)T-369(3b)
D)Simple memo
Answer: T-806
- Q. Speed of train when whistle becomes defective is ________ km/h.
A)45/8
B)30/8
C)25/8
D)40/8
Answer: 25/8
- Q. Adequate distance kept beyond the starter signal to take off the home signal is called as ________.
A)Block instrument
B)Signal over lap
C)Over lap
D)None of these
Answer: Signal over lap
- Q. Time taken by train running at MPS is called as ________.
A)Normal running time
B)Long time
C)Minimum running time
D)None of these
Answer: Minimum running time
- Q. Indian Railway will be provided a device to their Gang Men which would be wireless enabled and will intimate them about approaching trains. The Device will be called:
A)Shaktimaan
B)Surakhsha
C)Rail Rakshak
D)Rakshak
Answer: Rakshak
- Q. On double line, when a running line is blocked by stabled load , the point to be set against are
A)Advance point
B)Either side points
C)Rear points
D)None of these
Answer: Rear points
- Q. When a signal is out of use two cross bars will be put across with ________ long and 10 CM wide.
A)03 meter
B)01 meter
C)02 meter
D)04 meter
Answer: 01 meter
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports
- State